01Facts
The petitioner had undertaken construction of houses under the Pradhan Mantri Awas Yojana, Mohaniya, for the Municipal Corporation, Jabalpur.
¶ 2Following disputes over its claims, it filed W.P. No. 18233 of 2020; the High Court directed the arbitrator to decide the jurisdictional issue.
¶ 2After contempt proceedings, the Additional Commissioner issued an order dated 5 October 2023 rejecting the petitioner’s representation.
¶ 2The petitioner challenged that order, alleging that it addressed only the running bill and omitted other claims.
¶ 2–4The respondents argued that the contractual dispute-resolution process provided an alternative remedy.
¶ 2–402Issues
i.1. Whether the petitioner could obtain relief under Article 226 when the agreement provided a staged dispute-resolution process, including an appeal from the Competent Authority’s decision.
¶ 4–7ii.2. Whether the petitioner’s challenge to the order dated 5 October 2023 should first be pursued before the contractual Appellate Authority.
¶ 5–803Law Applied
Article 226 of the Constitution was invoked, but the Court resolved the matter by applying Clause 12 of the agreement.
¶ 1, 6Under that clause, disputes must first be referred in writing to the Competent Authority; an appeal from that authority’s decision may be filed before the Appellate Authority within 30 days; and a further appeal lies to the Madhya Pradesh Arbitration Tribunal constituted under the Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983.
¶ 1, 6The Competent Authority and Appellate Authority are each required by the clause to decide disputes within 45 days.
¶ 604Reasoning
The Court treated the order dated 5 October 2023 as the Competent Authority’s decision under Clause 12.2.
¶ 6–9It therefore held that the contractual next step was an appeal to the Appellate Authority under Clause 12.4, rather than immediate recourse to the Arbitration Tribunal.
¶ 6–9Without expressing any view on the merits of the petitioner’s claims, the Court directed the petitioner to pursue that remedy and preserved its further recourse to the Tribunal if unsuccessful.
¶ 6–905Holding
The High Court disposed of the writ petition without deciding the merits.
¶ 8–10It directed that, if the petitioner approached the Appellate Authority within 30 working days, that authority must pass a reasoned order within a further 90 days after hearing the concerned parties.
¶ 8–10If the appeal proved unsuccessful, the petitioner remained at liberty to invoke the jurisdiction of the Madhya Pradesh Arbitration Tribunal under the 1983 Adhiniyam.
¶ 8–10Original Court PDF