01Facts
The petitioner, a contractor, claimed payment of ₹7,45,525 as allegedly payable under his third and final bill for construction work undertaken for the Public Health Engineering Department, Government of Bihar.
p. 2The Engineer-in-Chief-cum-Special Secretary subsequently reduced the amount found payable to ₹2,29,434 after examining the completed work approximately six years later.
p. 2The petitioner relied on an earlier order dated 8 January 2015 in CWJC No. 19833 of 2014, whereby the High Court directed payment of admissible dues and observed that any dispute regarding deductions from the final bill or withholding of other amounts was to be pursued before the Arbitral Tribunal.
pp. 2–4As payment was allegedly not made, the petitioner initiated MJC No. 1325 of 2016.
p. 3By order dated 27 August 2018, the contempt proceeding was disposed of with a direction to deposit ₹52,132 upon the petitioner furnishing the requisite information, while granting him liberty to challenge the rejection of his remaining claims.
p. 3Instead of approaching the Arbitral Tribunal, the petitioner filed the present writ petition challenging the reduction of his claim and seeking payment of the balance amount with interest.
pp. 2, 4–502Issues
i.Whether the writ petition was maintainable when the petitioner’s grievance concerned deductions and claims arising out of a works contract and the earlier High Court order directed him to approach the Arbitral Tribunal for such disputes?
pp. 4–5ii.Whether the petitioner was required to pursue his remaining monetary claims before the Bihar Public Works Contracts Disputes Arbitration Tribunal constituted under the Bihar Public Works Contracts Disputes Arbitration Tribunal Act, 2008?
pp. 4–5iii.Whether the Arbitral Tribunal should consider the issue of limitation, particularly because the writ petition had been filed in 2019?
p. 603Law Applied
The Court applied the Bihar Public Works Contracts Disputes Arbitration Tribunal Act, 2008, under which the Tribunal is constituted to adjudicate disputes relating to works contracts involving the State Government or a public undertaking.
p. 4Section 2(e) of the Act defines “dispute” broadly to mean any difference relating to a claim arising out of the execution or non-execution of the whole or part of a contract for works or services, including rescission of the contract.
p. 4The Court also applied the binding direction issued in CWJC No. 19833 of 2014 that any grievance concerning deductions from the final bill or withholding of amounts was to be pursued by enforcing the contract before the Arbitral Tribunal.
pp. 3–4Accordingly, contractual monetary disputes falling within the statutory definition of “dispute” were required to be adjudicated by the designated Tribunal rather than through the present writ proceeding.
Provisions in the judgment · 1
Bihar Public Works Contracts Disputes Arbitration Tribunal Act, 2008 Section 2
04Reasoning
The petitioner’s challenge related directly to the reduction of the amount payable under his final bill and therefore constituted a dispute arising from execution of a works contract within Section 2(e) of the 2008 Act.
pp. 4–5The Court held that the earlier order in CWJC No. 19833 of 2014 had specifically directed the petitioner to approach the Arbitral Tribunal for any grievance regarding deductions or withheld amounts.
pp. 3–4Although the order in the contempt proceeding granted liberty to challenge the rejection of the remaining claims, that liberty did not alter the earlier direction regarding the appropriate contractual forum.
p. 3Since the petitioner had bypassed the statutory Tribunal and invoked writ jurisdiction in respect of the same contractual dispute, the writ petition was held not maintainable.
p. 5The Court nevertheless preserved the petitioner’s right to approach the Tribunal and directed that limitation be considered in view of the delay and the filing of the writ petition in 2019.
p. 605Holding
The Court declined to adjudicate the petitioner’s claim for the allegedly unpaid balance under the final bill, holding that the dispute was required to be brought before the Bihar Public Works Contracts Disputes Arbitration Tribunal under the 2008 Act and in accordance with the earlier order in CWJC No. 19833 of 2014.
p. 5The writ petition was disposed of with liberty and direction to the petitioner to approach the Arbitral Tribunal within one month from receipt of the judgment.
pp. 5–6The Tribunal was directed to decide the matter on merits within three months of the filing of the application, after granting the petitioner an opportunity of hearing, and to consider the question of limitation.
pp. 5–6All interlocutory applications, if any, were also disposed of.
p. 6Original Court PDF
Gaya SinghvsThe State of Bihar
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
