Facts
The Petitioner challenged two Arbitral Awards dated 20.07.2024 rendered by a three-member Tribunal concerning Contract Agreements for power infrastructure.
Source reference: para 1-2The Tribunal had rejected the Petitioner’s claims for interest on bank guarantee extension charges (Claim No. 2) and loss of profits due to contract prolongation (Claim No. 7).
Source reference: para 6The Tribunal based its rejection on a specific interpretation of Clause 26 of the General Conditions of Contract (GCC), which limited liability for certain types of losses.
Source reference: para 7-8The Petitioner approached the High Court under Section 34 of the Arbitration and Conciliation Act, 1996, alleging patent illegality and misinterpretation of the contract.
Source reference: para 9-12Issues
1. Whether the Arbitral Tribunal’s interpretation of Clause 26 of the GCC, excluding "loss of profits" and "interest costs" as independent categories of non-recoverable loss, was perverse or patently illegal.
Source reference: para 92. Whether the denial of interest on bank guarantee extension charges (Claim No. 2) was justified in the absence of evidence showing actual interest outflow.
Source reference: para 13, 183. Whether the rejection of the claim for loss of profits (Claim No. 7) was valid given the Petitioner relied solely on Hudson’s Formula without evidence of actual loss of opportunity.
Source reference: para 22-23Law Applied
Section 34 of the Arbitration and Conciliation Act, 1996, which restricts judicial interference to grounds of "patent illegality" or conflict with the "public policy of India".
Source reference: para 31, 47The narrow scope of "public policy" post-2015 Amendment as laid down in OPG Power Generation (P) Ltd. v. Enexio Power Cooling Solutions.
Source reference: para 31The principle that the Arbitrator is the "ultimate master" of evidence and interpretation unless the view is implausible.
Source reference: para 31, 35For loss of profit claims, standards set in Unibros v. All India Radio and Batliboi Environmental Engineers v. HPCL mandate proof of actual loss/opportunity cost before applying mathematical formulae.
Source reference: para 56Reasoning
The court found that the Tribunal’s interpretation of Clause 26 was a "plausible view" derived from a grammatical and syntactical analysis of the "Oxford comma" and disjunctive conjunctions in the text.
Source reference: para 37-38The court held that interpreting "loss of profits" and "interest costs" as distinct excluded categories—rather than just examples of "indirect loss"—was a reasonable exercise of the Tribunal’s jurisdiction.
Source reference: para 38Regarding Claim No. 2, the court reasoned that the Petitioner failed to prove an actual "interest cost" (outflow) through borrowings, and notional "interest loss" was contractually barred.
Source reference: para 44-45On Claim No. 7, the court affirmed the Tribunal’s distinction between contract termination (where profit is presumed) and prolongation (where actual loss of other work must be evidenced).
Source reference: para 52-53Since the Petitioner only provided Hudson’s Formula without contemporaneous documents showing lost opportunities, the rejection was legally sound.
Source reference: para 54-55Holding
The court dismissed the Petitions, holding that the Petitioner failed to establish any patent illegality or perversity in the Awards.
The court concluded that the Tribunal’s findings were reasoned and consistent with the contract and settled law.
Source reference: para 58The denial of interest and loss of profits was upheld as the Petitioner failed to meet the requisite evidentiary thresholds.
Source reference: para 48, 56Final order: Petitions dismissed; no order as to costs.
Source reference: para 63Original Court PDF
Deepak Cables (India) LimitedvsPower Grid Corporation Of India Limited
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in