Facts
The Petitioners approached the Court under Section 9 of the Arbitration and Conciliation Act, 1996 ("the Act"), seeking various ad-interim measures against the Respondents.
Source reference: p. 2, para 1These measures included staying the operation of a Defect Cure Notice dated January 7, 2026, and seeking prohibitive injunctions to restrain Respondents from terminating a Kodak Lens Distribution Agreement, invoking share pledges, or enforcing security interests under a Master Settlement Agreement (MSA) dated April 4, 2023.
Source reference: p. 2, para 1Clause 19 of the MSA provided for the resolution of disputes via arbitration under the rules of the Delhi International Arbitration Centre (DIAC).
Source reference: p. 3, para 2During the hearing, counsel for both parties jointly submitted that the disputes should be referred to a Sole Arbitrator and the Section 9 petition be converted into a Section 17 petition for adjudication by the Tribunal.
Source reference: p. 3, para 3Issues
1. Whether the Court can waive the statutory requirements of Section 21 (Notice of Arbitration) and Section 11 (Appointment of Arbitrator) when parties are ad idem on the appointment of an arbitrator?
Source reference: p. 3, para 42. Whether a Section 9 petition can be converted into a Section 17 petition to be adjudicated by the appointed Arbitral Tribunal?
Source reference: p. 4, para 7Law Applied
Section 9 of the Arbitration and Conciliation Act, 1996, regarding interim measures by the Court.
Source reference: p. 2, para 1Section 17 regarding interim measures by the Arbitral Tribunal.
Source reference: p. 3, para 3The Court also invoked the principle of party autonomy and procedural efficiency to waive the requirements of Section 21 (commencement of proceedings) and Section 11 (formal petition for appointment of arbitrator) when both parties consent to the reference and the individual arbitrator.
Source reference: p. 3-4, para 4Reasoning
The Court noted that Clause 19 of the MSA clearly stipulated arbitration as the dispute resolution mechanism.
Source reference: p. 3, para 2Since the parties reached a consensus (ad idem) to refer the dispute—valued at approximately Rs. 17 Crores—to a specific retired Chief Justice, the Court held that the statutory requirements of a formal Section 21 notice and a Section 11 petition should be waived to avoid undue delay in adjudication.
Source reference: p. 3-4, para 4-6The Court reasoned that referring the pending application for interim relief directly to the arbitrator under Section 17 would be the most efficient course of action.
Source reference: p. 4, para 7To protect the parties' interests in the interim, the Court directed that the existing status quo/interim order dated February 26, 2026, would continue until the arbitrator could hear the converted Section 17 application.
Source reference: p. 4, para 10Holding
The Court referred the parties to arbitration and appointed Hon’ble Mr. Justice Rajiv Shakdher (Retd.) as the Sole Arbitrator under the aegis of the DIAC.
The Section 9 petition was converted into a Section 17 petition to be decided by the Arbitrator as expeditiously as possible.
Source reference: p. 4, para 7, 9The Court ordered that the interim protection granted on February 26, 2026, shall remain in effect until the Arbitrator takes up the Section 17 petition.
Source reference: p. 4, para 10All rights and contentions of the parties were kept open for the Arbitrator’s determination on merits.
Source reference: p. 5, para 14The petition was disposed of accordingly.
Source reference: p. 5, para 17Original Court PDF
Gkb Hi-Tech Lenses Private Limited & Ors.vsEssilor India Private Limited & Ors.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in