Facts
The Appellant filed an appeal against the judgment dated 03.12.2024, which upheld an Arbitral Award dated 20.03.2015 under the Arbitration Act, 1940
Source reference: p. 2The appeal was filed with a delay of 26 days (excluding time for obtaining a certified copy) and suffered a subsequent delay of 155 days in re-filing due to Registry objections regarding maintainability and nomenclature
Source reference: p. 2-3The Appellant's primary justification for the initial delay was the bereavement and unavailability of their Authorised Representative, who had handled the 1989 contract dispute for over three decades
Source reference: p. 3-4Regarding the re-filing delay, they cited contradictory directions from the Registry and the time required to type voluminous, illegible records from 1989
Source reference: p. 4-5Issues
1. Whether the Appellant showed "sufficient cause" under Section 5 of the Limitation Act, 1963 to condone the 26-day delay in filing the appeal?
Source reference: p. 8 / para. 152. Whether the 155-day delay in re-filing the appeal was justifiable and attributable to bona fide circumstances?
Source reference: p. 8 / para. 15Law Applied
Section 5 of the Limitation Act, 1963, which allows for condonation of delay if the applicant satisfies the court of "sufficient cause"
Source reference: p. 8The Supreme Court’s precedent in Collector, Land Acquisition, Anantnag v. Mst. Katiji, which held that the term "sufficient cause" should be applied elastically to ensure substantial justice and that a pedantic approach to "every day's delay" should be avoided
Source reference: p. 8-10Basawaraj Anr. v. The Spl. Land Acquisition Officer regarding the rigors of limitation
Source reference: p. 14Jain Irrigation Systems Ltd. v. Dura-Line India Pvt. Ltd., which established that re-filing delays are a matter between the Court and the litigant, where repeated attempts to cure defects indicate a bona fide intent to pursue the matter
Source reference: p. 13Reasoning
The Court noted that the Respondent chose not to contest the Appellant’s detailed affidavit explaining the delays, thereby leaving the facts stated therein uncontroverted
Source reference: p. 8, 11It found the initial delay of 26 days justified because the Authorised Representative’s personal tragedy and presence in Andhra Pradesh were critical given his unique knowledge of the 35-year-old dispute
Source reference: p. 11-12Regarding re-filing, the Court observed that the Registry issued inconsistent instructions (switching nomenclature between FAO and FAO(OS)), which significantly contributed to the timeline
Source reference: p. 12The court emphasized that the Appellant's continuous efforts to provide typed, legible copies of old records demonstrated diligence rather than negligence
Source reference: p. 13Consequently, the court held that procedural technicalities should not override the interest of substantial justice when a party acts bona fide
Source reference: p. 14-15Holding
The Court allowed CM. APPL. 53197/2025 and CM. APPL. 53193/2025, condoning the 26-day delay in filing and the 155-day delay in re-filing
The Court admitted the appeal and directed the requisition of digital Trial Court Records, subject to the Appellant paying costs of Rs. 50,000/- as a condition for the condonation
Source reference: p. 15Original Court PDF
M/S Progressive Constructions LimitedvsM/S Sharma And Associates Constractor Pvt. Ltd
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in