Delhi High Court

Corporate Litigant Entitled to Condonation of Delay Where Bona Fide Personal Loss and Registry Inconsistency Constitute Sufficient Cause

M/S Progressive Constructions Limited vs M/S Sharma And Associates Constractor Pvt. Ltd

Delhi High CourtJUDGMENT: May 29, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Appellant filed an appeal against the judgment dated 03.12.2024, which upheld an Arbitral Award dated 20.03.2015 under the Arbitration Act, 1940

Source reference: p. 2

The appeal was filed with a delay of 26 days (excluding time for obtaining a certified copy) and suffered a subsequent delay of 155 days in re-filing due to Registry objections regarding maintainability and nomenclature

Source reference: p. 2-3

The Appellant's primary justification for the initial delay was the bereavement and unavailability of their Authorised Representative, who had handled the 1989 contract dispute for over three decades

Source reference: p. 3-4

Regarding the re-filing delay, they cited contradictory directions from the Registry and the time required to type voluminous, illegible records from 1989

Source reference: p. 4-5
02

Issues

1. Whether the Appellant showed "sufficient cause" under Section 5 of the Limitation Act, 1963 to condone the 26-day delay in filing the appeal?

Source reference: p. 8 / para. 15

2. Whether the 155-day delay in re-filing the appeal was justifiable and attributable to bona fide circumstances?

Source reference: p. 8 / para. 15
03

Law Applied

Section 5 of the Limitation Act, 1963, which allows for condonation of delay if the applicant satisfies the court of "sufficient cause"

Source reference: p. 8

The Supreme Court’s precedent in Collector, Land Acquisition, Anantnag v. Mst. Katiji, which held that the term "sufficient cause" should be applied elastically to ensure substantial justice and that a pedantic approach to "every day's delay" should be avoided

Source reference: p. 8-10

Basawaraj Anr. v. The Spl. Land Acquisition Officer regarding the rigors of limitation

Source reference: p. 14

Jain Irrigation Systems Ltd. v. Dura-Line India Pvt. Ltd., which established that re-filing delays are a matter between the Court and the litigant, where repeated attempts to cure defects indicate a bona fide intent to pursue the matter

Source reference: p. 13
04

Reasoning

The Court noted that the Respondent chose not to contest the Appellant’s detailed affidavit explaining the delays, thereby leaving the facts stated therein uncontroverted

Source reference: p. 8, 11

It found the initial delay of 26 days justified because the Authorised Representative’s personal tragedy and presence in Andhra Pradesh were critical given his unique knowledge of the 35-year-old dispute

Source reference: p. 11-12

Regarding re-filing, the Court observed that the Registry issued inconsistent instructions (switching nomenclature between FAO and FAO(OS)), which significantly contributed to the timeline

Source reference: p. 12

The court emphasized that the Appellant's continuous efforts to provide typed, legible copies of old records demonstrated diligence rather than negligence

Source reference: p. 13

Consequently, the court held that procedural technicalities should not override the interest of substantial justice when a party acts bona fide

Source reference: p. 14-15
05

Holding

The Court allowed CM. APPL. 53197/2025 and CM. APPL. 53193/2025, condoning the 26-day delay in filing and the 155-day delay in re-filing

The Court admitted the appeal and directed the requisition of digital Trial Court Records, subject to the Appellant paying costs of Rs. 50,000/- as a condition for the condonation

Source reference: p. 15
Delhi High Court

Original Court PDF

M/S Progressive Constructions LimitedvsM/S Sharma And Associates Constractor Pvt. Ltd

Delhi High Court · May 29, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment