Facts
The Respondent entered into a contract with the Appellant for the supply of LPG cylinders from June 7, 2004, to June 6, 2005
Source reference: para. 3The Respondent claimed unpaid dues of Rs. 5,48,478, while the Appellant sought to recover approximately Rs. 52,00,000 as liquidated damages for alleged short supply during the contract period
Source reference: para. 3, 5An Arbitrator allowed the Appellant’s counter-claim, computing the limitation period from February 14, 2006 (the date of the last correspondence), rather than the contract’s end date
Source reference: para. 4The Respondent challenged this under Section 34 of the Arbitration Act, and the learned Single Judge set aside the award, holding the counter-claim barred by limitation
Source reference: para. 1, 5The Appellant subsequently filed this appeal under Section 37
Source reference: para. 1, 8Issues
1. Whether the limitation period for filing a counter-claim for liquidated damages commences from the date of the breach/expiry of the contract or from the date of the last correspondence between the parties
Source reference: para. 4, 5, 72. Whether the High Court can re-appreciate facts and evidence while exercising jurisdiction under Section 34 or Section 37 of the Arbitration Act, 1996
Source reference: para. 8, 9Law Applied
The court applied the Limitation Act, 1963, specifically the principle that a claim for liquidated damages must be initiated within three years from the date the cause of action accrues
Source reference: para. 5, 7It also interpreted the scope of judicial interference under Sections 34 and 37 of the Arbitration and Conciliation Act, 1996, which prohibits the re-appreciation of evidence or facts by the court
Source reference: para. 8Reasoning
The Court rejected the Appellant’s contention that the cause of action arose on February 14, 2006, via correspondence
Source reference: para. 6.1, 7It reasoned that the alleged liability for liquidated damages for short supply necessarily arose during the subsistence of the contract, which concluded on June 6, 2005
Source reference: para. 5, 7Consequently, the three-year limitation period expired on June 5, 2008. Since the counter-claim was filed on September 8, 2008, it was demonstrably time-barred
Source reference: para. 7The Court further noted that the Arbitrator’s calculation showed a "complete non-application of mind to the relevant law"
Source reference: para. 5Finally, the Court emphasized that under Sections 34 and 37, it is not permissible to engage in a merits-based re-evaluation of the evidence already considered by the lower forum
Source reference: para. 8Holding
The Court answered that the cause of action accrued on the expiry of the contract (June 6, 2005) and the counter-claim filed in September 2008 was barred by limitation
The Court upheld the Single Judge's order setting aside the Arbitral Award, holding that the impugned order suffered from no error in law or facts. The Appeal was dismissed for lack of merit
Source reference: para. 9, 10Original Court PDF
Hindustan Petroleum Corporation LtdvsM/S. Nandi Cylinder Pvt. Ltd.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in