Jammu and Kashmir High Court

Court Appoints Independent Arbitrator as Party Employee is Ineligible Under Amended Arbitration Act

SHIVAM BUILD CON ASSOCIATES TH SHAILANDER VAID vs UNION OF INDIA TH CHIEF ENGINEER PROJECT BEACON 56 APO AND OTHERS

Jammu and Kashmir High CourtJUDGMENT: June 05, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioner, a proprietorship involved in road construction, was awarded a contract (No. CE(P) BCN/01/2023-24) by the respondents on 12.04.2023 for bituminous works on the Patnitop-Nathatop road

Source reference: p. 2, para. 2-3

Work was suspended for 29 days due to inclement weather and the contract value was subsequently reduced from Rs. 2,44,10,600 to Rs. 1,50,00,000 due to non-availability of funds

Source reference: p. 3, para. 4, 7

After completion, the petitioner sought reimbursement for losses via communication dated 13.08.2024

Source reference: p. 3, para. 5

Following the respondents' failure to respond, the petitioner invoked the arbitration clause on 13.12.2024

Source reference: p. 3, para. 5

The respondents admitted the contract and its suspension but contended that under Condition 70 of the General Conditions of Contract, disputes must be referred to an Engineer Officer appointed by the authority

Source reference: p. 3-4, para. 7-8
02

Issues

1. Whether an independent arbitrator should be appointed under Section 11(6) of the Arbitration and Conciliation Act, 1996, despite the contract specifying an "Engineer Officer" as the sole arbitrator

Source reference: p. 5, para. 9-10
03

Law Applied

Section 11(6) of the Arbitration and Conciliation Act, 1996, regarding the court's power to appoint an arbitrator when the agreed procedure fails

Source reference: p. 2, para. 1

The 2015/2019 amendments to the Act, which establish that an employee of one of the parties is ineligible to act as an arbitrator, thereby overriding contractual clauses that permit the appointment of departmental officers

Source reference: p. 5, para. 9
04

Reasoning

The Court found that the existence of the arbitration agreement (Clause 70) and its valid invocation by the petitioner were undisputed

Source reference: p. 5, para. 9

While the contract's original terms required the appointment of an "Engineer Officer," the Court reasoned that post-amendment statutory law mandates neutrality in arbitration

Source reference: p. 5, para. 9

Since an employee of the respondents is legally ineligible to serve as an arbitrator, the designated departmental authority could not fulfill the role

Source reference: p. 5, para. 9

Consequently, as the respondents failed to appoint an eligible arbitrator following the petitioner’s notice, the Court exercised its jurisdiction to ensure the resolution of the dispute through an independent third party

Source reference: p. 5, para. 10
05

Holding

Statutory amendments regarding arbitrator ineligibility supersede departmental appointment clauses

The Court allowed the petition and appointed Shri Vinod Gupta, Chief Engineer (Retired), as the Sole Arbitrator. The Arbitrator was directed to proceed under the Arbitration and Conciliation Act, 1996, with fees to be shared by both parties

Source reference: p. 5-6, para. 10-12
Jammu and Kashmir High Court

Original Court PDF

SHIVAM BUILD CON ASSOCIATES TH SHAILANDER VAIDvsUNION OF INDIA TH CHIEF ENGINEER PROJECT BEACON 56 APO AND OTHERS

Jammu and Kashmir High Court · June 05, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment