Karnataka High Court
Administrative and Public LawProperty and Real Estate Law

Court declined to revisit the tower-authorisation order after construction, preserving the petitioner’s right to pursue other remedies.

MR GANESH PANAMBUR vs KARNATAKA POWER TRANSMISSION CORPORATION LIMITED

Karnataka High CourtJUDGMENT: September 30, 20262 MIN READSOURCE JUDGMENT
Court declined to revisit the tower-authorisation order after construction, preserving the petitioner’s right to pursue other remedies.. MR GANESH PANAMBUR vs KARNATAKA POWER TRANSMISSION CORPORATION LIMITED. Karnataka High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioner claimed joint ownership and possession of land in Sy. No. 62/14, Kadandale village.

Source reference: p. 4–6

In connection with a proposed high-tension transmission line, KPTCL sought authority under Section 16(1) of the Telegraph Act, 1885, read with Section 164 of the Electricity Act, 2003, to proceed with Tower No. 7.

Source reference: p. 5

The petitioner challenged the Deputy Commissioner’s order dated 21 January 2025, alleging that it disregarded survey material and that the tower was to be located on another person’s land.

Source reference: p. 4–6

By the time the writ petition was heard, the towers had been laid and KPTCL had deposited compensation of Rs. 9,46,969.50 before the jurisdictional District Judge.

Source reference: p. 4–6

The petitioner acknowledged that little remained for consideration in the writ petition and sought liberty to pursue an appropriate remedy

Source reference: p. 4–6
02

Issues

1. Whether the Court should revisit the Deputy Commissioner’s order after the respondents had completed laying the towers.

Source reference: p. 6–7

2. Whether the petitioner should be left at liberty to pursue an appropriate remedy in accordance with law.

Source reference: p. 7
03

Law Applied

The order refers to Section 16(1) of the Telegraph Act, 1885, and Section 164 of the Electricity Act, 2003, as the statutory basis for the respondents’ application before the Deputy Commissioner.

Source reference: p. 5

It does not interpret these provisions, cite precedent, or set out a further substantive legal rule; the disposition rests on the circumstances and submissions before the Court.

Source reference: p. 6–7
04

Reasoning

The Court noted that the respondents had already laid the towers and deposited compensation before the jurisdictional District Judge.

Source reference: p. 6–7

In those circumstances, it declined to revisit the Deputy Commissioner’s order in the writ petition.

Source reference: p. 6–7

The petitioner’s stated intention to seek an appropriate remedy was preserved, without the Court determining the merits of the underlying dispute.

Source reference: p. 6–7
05

Holding

The writ petition was disposed of, with liberty to the petitioner to avail himself of any appropriate remedy in accordance with law.

All pending applications were closed.

Source reference: p. 7
06

Acts & Sections Cited

2 provisions across 2 statutes referred to in this judgment. Each provision opens on LawLens.

Indian Telegraph Act, 18851

Electricity Act, 20031

Karnataka High Court

Original Court PDF

MR GANESH PANAMBURvsKARNATAKA POWER TRANSMISSION CORPORATION LIMITED

Karnataka High Court · September 30, 2026