Delhi High Court

Court Extends Arbitral Mandate Under Section 29A(5) Following Party Consent and Significant Procedural Delays

Supreme Panvel Indapur Tollway Private Limited vs National Highways Authority Of India

Delhi High CourtJUDGMENT: May 29, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Petitioner and Respondent entered into a Concession Agreement on 21.01.2011

Source reference: p. 1, para. 2

Following disputes, a three-member Arbitral Tribunal was constituted. The proceedings suffered delays due to challenges to interim orders, appellate proceedings, and Corporate Insolvency Resolution Process (CIRP) proceedings initiated against one party

Source reference: p. 2, para. 3

After the statutory period expired, the parties mutually extended the mandate by six months under Section 29A(3) of the Arbitration and Conciliation Act, 1996; however, this period also expired while the proceedings were still at the stage of pleadings

Source reference: p. 2, paras. 4-5

The Petitioner sought a further judicial extension of the mandate through the present petition

Source reference: p. 1, para. 1
02

Issues

1. Whether there exists "sufficient cause" to grant an extension of the mandate of the Arbitral Tribunal under Section 29A(5) of the Arbitration and Conciliation Act, 1996

Source reference: p. 3, para. 9

2. Whether the period between the expiry of the previous mandate and the date of the court order can be regularized

Source reference: p. 4, para. 12
03

Law Applied

The court applied Section 29A of the Arbitration and Conciliation Act, 1996, which mandates that an award must be made within twelve months from the completion of pleadings, allowing for a six-month extension by mutual consent, after which only the Court may extend the mandate for "sufficient cause"

Source reference: pp. 2-3, para. 9

The Court further relied on the precedent set by the Hon’ble Supreme Court in Rohan Builders (India) Private Limited v. Berger Paints India Limited (2024 SCC OnLine SC 2494), which clarified the scope, ambit, and timeline requirements for extending an arbitrator's mandate under Section 29A

Source reference: pp. 3-4, para. 10
04

Reasoning

The Court observed that despite the previous six-month mutual extension, the arbitral proceedings had not progressed beyond the pleadings stage due to complex intervening developments, including litigation in appellate forums and insolvency proceedings

Source reference: p. 2, paras. 3-5

The Court reasoned that since both parties were ad idem (in agreement) regarding the necessity of the extension and no objection was raised by the Respondent, granting the relief was necessary for the interest of justice to ensure continuity and consistency in the adjudication of the dispute

Source reference: p. 2, paras. 6-8

Applying the "sufficient cause" standard under Section 29A(5), the Court determined that the procedural history justified a further twelve-month extension

Source reference: p. 4, para. 11
05

Holding

The Court allowed the petition and extended the mandate of the learned Arbitral Tribunal for a further period of twelve months, effective until 30.05.2027

Additionally, the Court regularized the "gap" period from 07.08.2023 until the date of the order (29.05.2026) to ensure the validity of the tribunal's mandate

Source reference: p. 4, para. 12

The petition and all pending applications were disposed of accordingly

Source reference: p. 4, para. 13
Delhi High Court

Original Court PDF

Supreme Panvel Indapur Tollway Private LimitedvsNational Highways Authority Of India

Delhi High Court · May 29, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment