01Facts
The Petitioner and Respondent entered into a Sub-lease Agreement dated 15.09.2018.
pp. 1-2Following disputes, the Petitioner invoked the arbitration clause on 17.02.2022, leading to the appointment of a Sole Arbitrator on 25.09.2023.
p. 2Arbitral proceedings commenced in October 2023 and pleadings were completed by 08.02.2024.
p. 2The mandate was previously extended by the Arbitrator and subsequently by the High Court until 27.02.2026.
p. 2The Petitioner approached the Court seeking a second extension of six months, citing delays due to the Respondent's requests for adjournments and the ill health of a 75-year-old witness whose cross-examination remained incomplete.
p. 202Issues
i.Whether sufficient cause exists under Section 29A(4) and (5) of the Arbitration and Conciliation Act, 1996, to grant a further extension of the Arbitrator’s mandate.
pp. 2-303Law Applied
The Court applied Section 29A of the Arbitration and Conciliation Act, 1996, which mandates that an award must be made within twelve months of the completion of pleadings, unless extended by the consent of parties (for six months) or by the Court upon an application showing "sufficient cause".
pp. 3-4The Court further referenced the Supreme Court’s interpretation of the scope and mandate of Section 29A in Rohan Builders (India) Private Limited v. Berger Paints India Limited.
p. 4Additionally, the court noted Section 7 of the Commercial Courts Act, 2015, regarding jurisdiction.
p. 1Provisions in the judgment · 2 · Linked ones open on LawLens
Commercial Courts Act, 2015 Section 7
Arbitration and Conciliation Act, 1996 Section 23
04Reasoning
The Court examined the procedural history and the reasons for the delay, noting that the proceedings were at an advanced stage but could not be concluded due to circumstances beyond the Petitioner’s control, specifically the incomplete cross-examination of an elderly witness and pending final arguments.
p. 2The Court observed that the Respondent, appearing through a partner, explicitly stated they had no objection to the extension.
pp. 2-3Applying the statutory requirement of "sufficient cause" under Section 29A(5), the Court determined that the need to complete evidence and hear final arguments justified the extension to prevent the termination of the mandate and ensure the resolution of the dispute.
p. 405Holding
The Court answered the issue in the affirmative, finding sufficient cause for the extension.
p. 4It allowed the petition and extended the mandate of the learned Sole Arbitrator for a further period of six months beyond 27.02.2026.
p. 4The Court ordered the disposal of the petition and all pending applications accordingly.
p. 4Original Court PDF
AVG Logistics Limited v. MS Shree Shyam Palace [O.M.P.(MISC.)(COMM.) 186/2026]
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
![Court Extends Arbitral Mandate under Section 29A Following Mutual Consent and Sufficient Cause shown.. AVG Logistics Limited v. MS Shree Shyam Palace [O.M.P.(MISC.)(COMM.) 186/2026]. Delhi High Court. LawLens](/stories/thumbnails/court-extends-arbitral-mandate-under-section-29a-following-mutual-consent-and-sufficient-c-cab88ad8ea5e4c6884897dd728def78b.webp)