Facts
The Applicant, a power sector company, was awarded a contract by the Respondent (a State Government undertaking) for the supply of ACSR Conductors via a Letter of Intent dated 16.08.2023
Source reference: para. 3Following inspection and delivery, the Respondent rejected a portion of the goods, withheld materials worth ₹1,61,73,075/-, and imposed a penalty of ₹60,82,107.37/- for alleged delays
Source reference: para. 3The Applicant invoked the arbitration clause (Clause 21 of the General Terms and Conditions) via notice on 13.09.2025
Source reference: para. 3The Respondent failed to appoint an arbitrator, prompting this application under Section 11(6)
Source reference: para. 4The Respondent initially contested the application, arguing the Applicant failed to follow the contractual procedure which mandated a three-member tribunal (two arbitrators and an umpire)
Source reference: para. 6Issues
Whether the High Court should exercise its jurisdiction under Section 11(6) of the Arbitration and Conciliation Act, 1996, to appoint a sole arbitrator despite a contractual clause stipulating a different appointment procedure?
Source reference: para. 9Law Applied
The Court primarily applied Section 11(6) of the Arbitration and Conciliation Act, 1996, which empowers the Chief Justice or their designate to take necessary measures for the appointment of an arbitrator when a party fails to act as required under an agreed appointment procedure
Source reference: para. 1, 9The Court also recognized the principle of party autonomy, allowing parties to mutually waive contractual stipulations regarding the composition of the Arbitral Tribunal in favor of a more "expeditious resolution"
Source reference: para. 9Reasoning
The Court examined the arbitration agreement and the subsequent deadlock in the appointment process.
Source reference: para. 5, 9While the Respondent initially argued that the application was premature and bypassed the three-member tribunal procedure established in Clause 21, the nature of the proceedings shifted during the hearing.
Source reference: para. 6The Court observed that both parties eventually reached a mutual consensus to waive the specific contractual requirement for a multi-member tribunal
Source reference: para. 9By exercising its discretion under Section 11(6) in light of this joint consensus, the Court determined that appointing a sole arbitrator was the most appropriate method for the "expeditious resolution" of the dispute
Source reference: para. 9The Court also noted the validity of the arbitration agreement and the existence of a live dispute regarding rejected goods and penalties
Source reference: para. 5, 9Holding
The Court allowed the application and held that a sole arbitrator should be appointed to resolve the disputes
Consequently, Hon’ble Mr. Justice Deepak Kumar Tiwari (Retd.) was appointed as the Sole Arbitrator
Source reference: para. 10The Court directed the Registry to communicate the order to the appointed arbitrator and ordered that his remuneration be settled by mutual consent of the parties
Source reference: para. 11-12The Respondent was granted liberty to raise all objections before the appointed arbitrator
Source reference: para. 10Original Court PDF
Ms Mahavir Transmission LimitedvsChhattisgarh State Power Distribution Company Limited
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in