Delhi High CourtArbitration and MediationCivil Procedure and Evidence

Court May Extend Arbitral Mandate Under Section 29A Even After Expiry of the Prescribed Period.

Delhi Development Authorityv.Dharamvir And Co

Court May Extend Arbitral Mandate Under Section 29A Even After Expiry of the Prescribed Period.. Delhi Development Authority vs Dharamvir And Co. Delhi High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the petition for extension of the arbitral mandate, previously withdrawn, should be restored to its original position.

The court held

The Court allowed the restoration of the petition.

It also directed

It further granted a three-month extension of the Arbitrator’s mandate from the date of the order to conclude the proceedings and render the award.

The court ordered that the period from the expiry of the previous mandate (07.10.2025) to the date of the judgement (21.05.2026) be regularized for the purposes of Section 29A of the Act.

01Facts

The Petitioner (DDA) and the Respondent entered into an agreement on 15.03.2011.

Following disputes, a Sole Arbitrator was appointed by the Delhi High Court on 09.10.2023.

p. 2

The Arbitrator entered reference on 03.11.2023, and pleadings were completed on 23.04.2024.

p. 3

The statutory 12-month mandate expired on 22.04.2025, but was extended by mutual consent for six months until 06.10.2025.

p. 3

The Petitioner initially filed this petition for extension on 26.11.2025 but withdrew it on 12.12.2025.

pp. 2-3

Subsequently, the Petitioner filed I.A. 14263/2026 seeking restoration of the petition, which the Respondent did not oppose.

p. 2

02Issues

i.1. Whether the petition for extension of the arbitral mandate, previously withdrawn, should be restored to its original position.

p. 2, para 5

ii.2. Whether the mandate of the Arbitral Tribunal should be extended under Section 29A of the Arbitration and Conciliation Act, 1996, despite the expiry of the previous mandate.

p. 3, para 7 · p. 4, para 13

03Law Applied

The court applied Section 151 of the Code of Civil Procedure, 1908, regarding the inherent powers of the court to restore a withdrawn petition.

p. 1

Section 29A of the Arbitration and Conciliation Act, 1996, which mandates a 12-month timeline for awards (sub-section 1), allows for a 6-month mutual extension (sub-section 3), and empowers the Court to grant further extensions for sufficient cause (sub-sections 4 and 5).

pp. 4-5

The court also referenced the Supreme Court’s interpretation of Section 29A in Rohan Builders (India) Private Limited v. Berger Paints India Limited [2024 SCC OnLine SC 2494].

p. 5, para 16

Provisions in the judgment · 2 · Linked ones open on LawLens

Code of Civil Procedure, 1908 Section 151

Arbitration and Conciliation Act, 1996 Section 23

04Reasoning

The court first addressed the procedural hurdle by allowing the restoration application (I.A. 14263/2026), noting that the Respondent had no objection to the revival of the petition.

p. 2

Regarding the extension of the mandate, the court reviewed the timeline of proceedings: the pleadings were completed on 23.04.2024, and the mutually extended mandate had expired on 06.10.2025.

p. 3

Under Section 29A(4) and (5), the Court determined that sufficient cause existed to prevent the termination of the arbitrator's mandate.

The court observed that the Petitioner sought the extension specifically for the rendering of the award.

pp. 3-4

Given the "no objection" from the Respondent and the need to ensure the proceedings conclude in accordance with law, the court found it appropriate to exercise its discretion to extend the mandate and regularize the intervening period.

p. 5

05Holding

The Court allowed the restoration of the petition.

p. 2, para 5

It further granted a three-month extension of the Arbitrator’s mandate from the date of the order to conclude the proceedings and render the award.

p. 5, para 17

The court ordered that the period from the expiry of the previous mandate (07.10.2025) to the date of the judgement (21.05.2026) be regularized for the purposes of Section 29A of the Act.

p. 5, para 18
Delhi High Court

Original Court PDF

Delhi Development AuthorityvsDharamvir And Co

Delhi High Court · May 21, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment