Facts
The petitioner challenged the Madhya Pradesh Housing and Infrastructure Development Board’s communication dated 21 September 2026 and the RFP dated 30 July 2026 concerning the Bhopal Collectorate re-densification project.
Source reference: para. 1–7The Board refused to consider the petitioner’s bid under the special eligibility criterion in Clause 19 of the Bid Summary, relying on a 9 February 2024 communication concerning a two-year delay in the petitioner’s Rewa Government Printing Press project and a penalty of ₹7.30 lakh.
Source reference: para. 1–7The petitioner argued that the delay was attributable, at least in part, to the employer and that the decision was predetermined, followed only by an ineffective post-decisional hearing.
Source reference: para. 3–4It also contended that the decision could have a blacklisting effect without notice.
Source reference: para. 3–4Issues
1. Whether the Board was justified in disqualifying the petitioner under Clause 19 of the Bid Summary on the basis of the recorded two-year delay and penalty in the Rewa project
Source reference: para. 6–92. Whether the petitioner’s claims of employer-attributable delay, denial of a meaningful hearing, or a blacklisting consequence warranted interference under Article 226
Source reference: para. 3–4, 9–10Law Applied
Article 226 permits judicial review of administrative and tender decisions, but the Court treated the tender process as contractual and considered that submission of a bid, by itself, creates no right to advance in the bidding process.
Source reference: para. 6, 10Under Clause 19 of the Bid Summary, a bidder is disqualified if it has completed an MPHIDB project with a delay of more than one year attributable to the bidder.
Source reference: para. 6The Court also noted that the tender document provided for dispute resolution, including arbitration, under Clause 21 of Section 1 of the Draft Concession-cum-Development Agreement.
Source reference: para. 6, 10No judicial precedent was cited.
Source reference: no citationReasoning
The record included the Executive Engineer’s communication attributing the two-year delay in the Rewa project to the petitioner and imposing a penalty, as well as the petitioner’s subsequent correspondence concerning that penalty.
Source reference: para. 6–8On that material, the Court found that the petitioner did not meet Clause 19’s eligibility requirement.
Source reference: para. 6–8The petitioner’s contention that the delay was actually attributable to the employer could not be determined in this petition because the Rewa communication had not been challenged and no appropriate forum had adjudicated attribution of the delay.
Source reference: para. 9The alleged blacklisting consequence was unsupported by the impugned communication.
Source reference: para. 10Given the contractual nature of the tender, the absence of an established right to proceed in the bidding process, and the public importance and time-bound nature of the project, the Court declined to interfere with the ongoing tender process.
Source reference: para. 10Holding
The Court held that the petitioner was disqualified under Clause 19 and found no basis for interference under Article 226.
It dismissed the writ petition.
Source reference: para. 11Acts & Sections Cited
1 provisions across 1 statute referred to in this judgment. Linked provisions open on LawLens.
Johannesburg Declaration On Sustainable Development1
Original Court PDF
M/S Samdariya Builders Private LimitedvsMadhya Pradesh Housing And Infrastructure Development Board
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
