Facts
The dispute arose from a 2014 works contract for the construction of dwelling units in Jodhpur
Source reference: para 3.IAlthough the work was completed on 10.03.2017, disputes emerged regarding delayed payments of the final bill and Running Account Receipts (RARs)
Source reference: para 3.II-IIIAn Arbitrator was appointed on 15.09.2020, and pleadings were allegedly completed on 24.05.2021
Source reference: para 3.IV, 3.VIIOn 10.04.2023, the Petitioner (UOI) filed an application under Section 29A of the Arbitration and Conciliation Act, 1996 ("A&C Act"), asserting that the Tribunal’s mandate had expired on 24.05.2022
Source reference: para 3.VIII, 5Despite this objection, the Petitioner continued to participate in merit-based arguments through May 2023
Source reference: para 19, 49The Arbitrator pronounced the Award on 27.08.2023, granting the Respondent approximately ₹6 crores plus 12% interest
Source reference: para 3.IXThe Petitioner challenged the Award under Section 34, primarily on the grounds of expired mandate and excessive interest
Source reference: para 2Issues
1. Whether the mandate of the Sole Arbitrator had terminated under Section 29A of the A&C Act prior to the pronouncement of the Award on 27.08.2023
Source reference: para 352. Whether the Arbitral Tribunal’s grant of interest at the rate of 12% per annum was patently illegal or contrary to the contract
Source reference: para 35, 58Law Applied
The Court applied Section 29A of the A&C Act, which prescribes a 12-month limit for awards (extendable by 6 months by consent) from the completion of pleadings
Source reference: para 36It relied on the Supreme Court’s directions in Suo Motu Writ Petition (C) No. 3 of 2020, which excluded the period from 15.03.2020 to 28.02.2022 from limitation periods due to COVID-19
Source reference: para 44Regarding the nature of the mandate, the Court applied Rohan Builders (India) Pvt Ltd v. Berger Paints India Limited, holding that termination under Section 29A is not absolute and is subject to the Court’s power to extend
Source reference: para 41On the issue of interest, the Court applied Section 31(7) of the A&C Act, which grants arbitrators wide discretion to award interest unless otherwise agreed by parties
Source reference: para 63, 65The scope of judicial intervention was governed by Section 34, as interpreted in OPG Power Generation (P) Ltd. v. Enexio Power Cooling Solutions (India) (P) Ltd., limiting interference to cases of patent illegality or conflict with public policy
Source reference: para 34Reasoning
The Court rejected the jurisdictional challenge, noting that when the COVID-19 exclusion period (ending 28.02.2022) is applied, the cumulative 18-month period (12 months under Section 29A(1) plus 6 months under 29A(3)) extended until 31.08.2023
Source reference: para 53Thus, the Award dated 27.08.2023 was within the permissible timeframe
Source reference: para 53Furthermore, the Court observed that the Petitioner’s active participation in hearings throughout April and May 2023, coupled with its post-award application for correction under Section 33, constituted an implied waiver of the objection and acceptance of the Tribunal’s jurisdiction
Source reference: para 49-50, 52Regarding interest, the Court found that the Arbitrator provided a reasoned basis for the 12% rate, identifying it as compensatory for the Respondent's deprivation of funds
Source reference: para 61-62Following Sri Lakshmi Hotel Pvt. Ltd. v. Sriram City Union Finance Ltd., the Court held that the rate of interest is a matter of arbitral discretion and does not warrant interference unless it "shocks the conscience," which was not the case here
Source reference: para 66, 69Holding
The Court dismissed the Section 34 petition, holding that the Arbitral Tribunal acted within its mandate and the award of interest was legally sound
It held that the statutory timeline must be reckoned from the expiry of the COVID-19 exclusion period and that a party cannot "approbate and reprobate" by participating in proceedings and then challenging the mandate after an unfavorable outcome
Source reference: para 50, 53The Court further allowed the Respondent's application (I.A. 43484/2024) to withdraw the ₹3,44,13,536/- deposited by the Petitioner, subject to a corporate guarantee
Source reference: para 74Original Court PDF
Union Of IndiavsM/S Varindera Constructions Ltd
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in