Gujarat High Court

Damages for loss of profit require substantiating evidence and cannot be decreed on mere pleadings.

EXECUTIVE ENGINEER vs KATARIA CONSTRUCTION CO.

Gujarat High CourtJUDGMENT: March 25, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The appellant (Gujarat Water Supply and Sewerage Board) filed a suit for recovery of damages amounting to Rs. 17,28,855.65 against the defendant contractor for failing to complete construction of an ESR and underground sump within the stipulated 12-month period

Source reference: p. 2, para 2-2.1

The defendant filed a written statement-cum-counterclaim for Rs. 24,79,000 under Order 8 Rule 6A of the CPC, alleging that delays were caused by the plaintiff’s late approval of designs, unforeseen hard rock cutting, and price escalations

Source reference: p. 2-3, para 2.2

The trial court dismissed the plaintiff's suit and partly allowed the defendant’s counterclaim, awarding Rs. 6,52,050 with 12% interest

Source reference: p. 3, para 2.3

The plaintiff appealed only against the decree allowing the counterclaim

Source reference: p. 3, para 3
02

Issues

1. Whether the trial court committed a manifest error of law and fact by partly allowing the counterclaim in the absence of cogent evidence?

Source reference: p. 7, para 5

2. Whether the defendant established the necessary conditions to claim damages for loss of profit and escalation of costs?

Source reference: p. 10, para 12; p. 13, para 19
03

Law Applied

The court applied Order 8 Rule 6A of the Code of Civil Procedure, 1908, which dictates that a counterclaim has the same effect as a cross-suit and must be proved by the defendant with the same burden of proof as a plaintiff in a suit

Source reference: p. 7, para 5; p. 10, para 12

Regarding the claim for loss of profit, the court relied on the Supreme Court precedent in M/s Unibros v. All India Radio (2023 INSC 931), which established a four-prong test: (i) delay in completion, (ii) delay not attributable to the claimant, (iii) status as an established contractor, and (iv) credible evidence to substantiate the loss

Source reference: p. 13, para 19

The principle of contractual risk assumption was applied via Condition No. 2 of the tender notice (Exh. 120), which deems the contractor to have inspected the site and satisfied themselves of all work conditions

Source reference: p. 11, para 14
04

Reasoning

The High Court observed that the trial court allowed several claims (Nos. 2-6) without any supporting documentary evidence, relying merely on pleadings

Source reference: p. 10, para 12

Regarding Claim No. 2 (unpaid work), the court found that the plaintiff had already measured and paid for the work done (Exh. 147), which the defendant accepted without dispute

Source reference: p. 11, para 13

Claims for hard rock cutting (No. 3) and water pumping (No. 4) were barred by Condition No. 2 of the tender, which placed the risk of site conditions on the contractor

Source reference: p. 12, para 15

The court rejected Claim No. 5 (escalation) and Claim No. 6 (depreciation and loss of profit) because the defendant failed to produce books of account or prove that the delay was solely attributable to the plaintiff, thus failing the Unibros test

Source reference: p. 12-13, para 16-20

The court categorized the trial court's decision as being based on "no evidence"

Source reference: p. 14, para 22
05

Holding

The High Court allowed the appeal and modified the trial court's decree.

It held that the defendant was only entitled to the refund of the Security Deposit (FDR) of Rs. 55,000

Source reference: p. 14, para 23

The court struck down the award of compounded interest and granted simple interest at 12% per annum from the date of the counterclaim until realization

Source reference: p. 14-15, para 21-23

All other reliefs granted by the trial court regarding the counterclaim were quashed and set aside

Source reference: p. 15, para 23
Gujarat High Court

Original Court PDF

EXECUTIVE ENGINEERvsKATARIA CONSTRUCTION CO.

Gujarat High Court · March 25, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment