Delhi High Court
Administrative and Public LawContract Law

Debarment of a joint-venture partner before LoA permits tender annulment despite eligibility at bid opening.

Ms Sterling Indo Tech Consultants Pvt Ltd vs National Highway Authority Of India

Delhi High CourtJUDGMENT: August 18, 20263 MIN READSOURCE JUDGMENT
Debarment of a joint-venture partner before LoA permits tender annulment despite eligibility at bid opening.. Ms Sterling Indo Tech Consultants Pvt Ltd vs National Highway Authority Of India. Delhi High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioner challenged the National Highway Authority of India’s decision dated 27 July 2026 annulling Tender ID No. 2026-NHAI-268092-I and the subsequent Notice Inviting Tender dated 29 July 2026 for the same supervision consultancy project.

Source reference: p.1–2; paras. 1–2

The bid had been submitted by a joint venture comprising the petitioner, M/s Yongma Engineering Co. Ltd., and M/s Manglam Infra & Engineering Ltd., and the joint venture had been declared the H-1/successful bidder on 5 June 2026.

Source reference: p.2–3; paras. 3, 6, 9

However, M/s Yongma was subsequently debarred by NHAI on 18 July 2026 as a non-performer for six months under Clause 7.4.2 of the Consultancy Agreement.

Source reference: p.3; paras. 5, 7

No Letter of Award (LoA) had been issued before the debarment.

Source reference: p.3–4; paras. 6–7

NHAI relied on Clause 1.4 of the agreement, which reserved its right to annul the selection process before award of the contract without liability.

Source reference: p.4; para. 8
02

Issues

Whether the writ petition was maintainable when it was filed by only one partner of the joint venture, without impleading the other two joint-venture partners?

Source reference: p.4–5; paras. 9–11

Whether NHAI could annul the tender after one of the joint-venture partners was debarred between the opening of the tender and the issuance of the LoA?

Source reference: p.5; paras. 12–13

Whether the petitioner was entitled to a direction requiring NHAI to issue the LoA and execute the contract in its favour despite the intervening debarment?

Source reference: p.2, 4–5; paras. 1, 10, 12–14
03

Law Applied

The Court applied the principle that a party seeking relief concerning rights and obligations arising from a joint venture must ordinarily implead all constituent partners, particularly where the relief sought is issuance of an LoA and execution of the contract in favour of the joint venture.

Source reference: p.4–5; paras. 9–11

Clause 1.4 of the agreement reserved NHAI’s right to annul the selection process at any time before award of the contract without incurring liability to the consultants.

Source reference: p.4; para. 8

Clause 7(b) stipulated that contracts could not be placed with debarred firms and that firms must be neither debarred on the date of opening of the tender nor on the date of contract, i.e., the date of issuance of the LoA.

Source reference: p.5; para. 12

Clause 10.1 of NHAI’s 2022 Standard Operating Procedure provided that bids could be considered only from firms not debarred on either the date of tender opening or the date of issuance of the LoA; contracts concluded before the debarment order, however, would remain unaffected.

Source reference: p.5; para. 13
04

Reasoning

The Court held that the petitioner’s claim was inseparable from the rights of the joint venture and its other partners.

Source reference: p.4–5; paras. 9–11

Since M/s Yongma and M/s Manglam were not parties to the petition, and the petitioner sought issuance of the LoA and execution of the contract in favour of the joint venture, the relief could not be effectively granted in their absence.

Source reference: p.4–5; paras. 9–11

Although Yongma was not debarred when the tender was opened, it was debarred on 18 July 2026, before issuance of the LoA and before execution of the contract.

Source reference: p.5–6; paras. 12–13

Clause 7(b) expressly required the bidder to be free from debarment both on the tender-opening date and on the contract date.

Source reference: p.5–6; paras. 12–13

Since no LoA had been issued by the date of debarment, the tender had not matured into a concluded contract and NHAI was entitled to treat the debarment as affecting the proposed award.

Source reference: p.5–6; paras. 12–13

The Court therefore found the annulment consistent with the contractual clause and the applicable NHAI procedure.

Source reference: p.5–6; paras. 12–13
05

Holding

The Court dismissed the writ petition on two grounds: it was not maintainable because the other joint-venture partners had not been impleaded, and it was devoid of merit because the debarment of one partner occurred before issuance of the LoA and execution of the contract.

The Court declined to direct NHAI to issue the LoA or execute the contract.

Source reference: p.6; para. 14

The respondent’s statement that the petitioner, in its individual capacity, could participate in the fresh tender—whose last date for submission was 24 August 2026—was taken on record.

Source reference: p.6; para. 15

The pending applications were dismissed as infructuous.

Source reference: p.6; para. 16
06

Acts & Sections Cited

4 provisions across 1 statute referred to in this judgment. Linked provisions open on LawLens.

Consultancy Agreement4

Section 7.4.2Section 1.4Section 7Section 10.1
Delhi High Court

Original Court PDF

Ms Sterling Indo Tech Consultants Pvt LtdvsNational Highway Authority Of India

Delhi High Court · August 18, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment