Facts

The petitioner claimed co-ownership of the land under registered sale deeds and alleged that a partition order was passed in 2015 without impleading or notifying the concerned co-owners. Revenue records were amended on the basis of that order in 2025.

Source reference: paras. 1–2

After learning of the changes, the petitioner filed an appeal with an application under Section 5 of the Limitation Act, 1963, seeking condonation of delay. The Sub-Divisional Officer (SDO) dismissed both the application and the appeal on 26 December 2025. The petitioner challenged that order under Article 226 of the Constitution

Source reference: paras. 1–2
02

Issues

Whether the SDO properly considered the petitioner’s explanation for delay, including the alleged lack of notice and the petitioner’s asserted date of knowledge

Source reference: paras. 3, 6

Whether the delay should be condoned and the appeal restored for determination on its merits

Source reference: paras. 6–8
03

Law Applied

Section 5 of the Limitation Act, 1963, provides for condonation of delay where sufficient cause is established; the court considered whether the petitioner’s pleaded circumstances—including alleged non-impleadment, absence of notice, and discovery of the altered revenue entries in 2025—required consideration in assessing sufficient cause

Source reference: paras. 1, 6–7

The petition was brought under Article 226 of the Constitution, and the Court granted relief by setting aside the SDO’s order and remanding the appeal

Source reference: paras. 1, 8

No precedent is cited in the judgment.

Source reference: no citation
04

Reasoning

The Court found that the petitioner’s assertions that he was not a party to the partition proceedings and learned of the revenue changes only in 2025 required due consideration when assessing the delay

Source reference: para. 6

It concluded that the petitioner should have an opportunity to have the challenge examined on its merits and therefore condoned the delay.

Source reference: para. 7

The Court did not decide the underlying questions of title, partition, or the correctness of the revenue entries, leaving them open for the competent authority

Source reference: para. 9
05

Holding

The Court allowed the petition, condoned the delay, and set aside the SDO’s order dated 26 December 2025 insofar as it rejected the condonation application and dismissed the appeal on that basis

It remanded the matter to the SDO to restore the appeal and decide it afresh on the merits, after giving the petitioner, respondents Nos. 1 and 2, and any other affected parties an opportunity to be heard, and after passing a reasoned order

Source reference: para. 8

No opinion was expressed on the merits, and there was no order as to costs

Source reference: paras. 9–10
06

Acts & Sections Cited

1 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.

Limitation Act, 19631

Madhya Pradesh High Court

Original Court PDF

Power Builders Private Ltd. Through Its Director Arvind SinghvsRamesh Singh

Madhya Pradesh High Court · October 13, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment