Delay in land acquisition appeals may be condoned, but no statutory benefits or interest accrue for the delayed period.

Prem B. Dattav.State Of Haryana And Ors

Delay in land acquisition appeals may be condoned, but no statutory benefits or interest accrue for the delayed period.. Prem B. Datta vs State Of Haryana And Ors. Punjab and Haryana High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the delay of 2835 days in filing the appeal should be condoned in a land acquisition matter where the landowner seeks enhanced compensation.

The court held

The delay of 2835 days is condoned, subject to the condition that the appellant is not entitled to interest for the delayed period.

It also directed

The RFA is allowed in terms of BESCO Ltd., with the express proviso that no interest is payable for the 2835-day delay. CR-8064-2026 is allowed, and the Executing Court's order dated 18.09.2026 is set aside.

01Facts

The appellant, an 87-year-old widow, is the successor of a landowner whose husband filed a reference petition against the Collector's award.

¶ 10

The Reference Court enhanced compensation by judgment dated 21.11.2018 of the Additional District Judge, Rewari.

¶ 10 · RFA para. 1

The State and HSIIDC appealed, and other landowners also appealed.

¶ 10

On 02.11.2021 the High Court dismissed the State's appeals and further enhanced compensation.

¶ 10

The appellant's husband filed Execution Petition No. 416 of 2021.

¶ 10

The Supreme Court, on 23.08.2023, further enhanced compensation in the landowners' appeals.

¶ 10

The appellant sought compensation in line with the Supreme Court judgment by application dated 18.12.2024 and letter dated 03.04.2026.

¶ 10

The Executing Court allowed the execution application by order dated 18.09.2026, which HSIIDC challenged in CR-8064-2026.

¶ 10

The appellant's appeal under Section 54 of the Land Acquisition Act, 1894 was filed with a delay of 2835 days, and the appellant sought condonation through CM-4804-CI-2026.

¶ 2, 10 · RFA para. 1

02Issues

i.1. Whether the delay of 2835 days in filing the appeal should be condoned in a land acquisition matter where the landowner seeks enhanced compensation.

¶ 2, 4–5, 12–13

ii.2. Whether the landowner, having approached the Court after inordinate delay, is entitled to statutory benefits and interest under the Land Acquisition Act, 1894 for the period of delay.

¶ 4, 7, 11–13

iii.3. Whether the Executing Court's order dated 18.09.2026 granting enhanced compensation with interest for the delayed period is sustainable.

¶ 8, 10

03Law Applied

Section 5 of the Limitation Act, 1963, under which delay may be condoned on sufficient cause, a discretion that must be exercised with regard to inordinate delay and due diligence, as summarised in Pathapati Subba Reddy v. Special Deputy Collector (2024) 12 SCC 336.

¶ 5

The stringent view in Shivamma v. Karnataka Housing Board (2025 SCC OnLine SC 1969) that State authorities' lethargy is not sufficient cause and that delay must not be condoned mechanically.

¶ 6

New OKHLA Industrial Development Authority v. Rameshwar (2022 SCC OnLine SC 1599), holding that delay may be condoned and enhanced compensation granted, but the acquiring body and beneficiary cannot be saddled with statutory benefits and interest for the delayed period.

¶ 7

Suresh Kumar v. State of Haryana (2025 SCC OnLine SC 896), which requires a justice-oriented and liberal approach to condonation and denies interest for the period of delay.

¶ 8

Urban Improvement Trust v. Vidhya Devi (2024 SCC OnLine SC 3725), which deprecates hyper-technical rejection of landowners' appeals and reaffirms that delay is not a ground to deny just compensation.

¶ 9

BESCO Ltd. v. State of Haryana (2024) 13 SCC 515 as the governing authority for the appellant's claim.

RFA para. 4–6

Provisions in the judgment · 2 · Linked ones open on LawLens

Limitation Act, 1963 Section 3Section 5

04Reasoning

The Court first noted the Supreme Court's strict approach to delay under Pathapati and Shivamma.

¶ 5–6

The Court then held that, in land acquisition cases, the liberal approach in Suresh Kumar, Vidhya Devi and NOIDA governs, because delay is not a ground to deny compensation that is just, fair and reasonable.

¶ 8–9

Counsel for the appellant conceded he could not controvert that the appellant was not entitled to interest in view of the inordinate delay. The Court therefore condoned the 2835-day delay but made the condonation conditional on the appellant forgoing interest for the delayed period, which reconciles the landowner's right to compensation with the rule that the acquiring body should not bear interest for the appellant's delay. The Court also noted that the appellant's claim is covered by BESCO. The Executing Court's order, which granted benefits without this limitation, was therefore set aside as inconsistent with the condition imposed in the RFA.

¶ 11–13 · RFA para. 4–5 · CR para. 8

05Holding

The delay of 2835 days is condoned, subject to the condition that the appellant is not entitled to interest for the delayed period.

¶ 13

The RFA is allowed in terms of BESCO Ltd., with the express proviso that no interest is payable for the 2835-day delay. CR-8064-2026 is allowed, and the Executing Court's order dated 18.09.2026 is set aside.

RFA para. 6 · CR para. 8
Punjab and Haryana High Court

Original Court PDF

Prem B. DattavsState Of Haryana And Ors

Punjab and Haryana High Court · November 23, 2026

Click to open original judgment