Gujarat High Court
Civil Procedure and EvidenceAdministrative and Public Law

Delay in restoring a dismissed proceeding must be considered under Section 5 of the Limitation Act, 1963.

MALI LAKHMAJI NEMAJI vs COMPETENT AUTHORITY AND DEPUTY COLLECTOR

Gujarat High CourtJUDGMENT: August 20, 20263 MIN READSOURCE JUDGMENT
Delay in restoring a dismissed proceeding must be considered under Section 5 of the Limitation Act, 1963.. MALI LAKHMAJI NEMAJI vs COMPETENT AUTHORITY AND DEPUTY COLLECTOR. Gujarat High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioner, a landowner dissatisfied with the compensation determined under Section 10(2) of the Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962, had filed an application under Section 10 of the Act, registered as CMA DC No. 116 of 2023.

Source reference: p. 3, para. 6

The application remained pending for approximately two years and was dismissed on 6 September 2025 for want of prosecution due to the absence of the petitioner’s advocate.

Source reference: p. 3, para. 6

The petitioner subsequently filed a restoration application seeking recall of the dismissal order, accompanied by an application under Section 5 of the Limitation Act, 1963, involving a delay of 37 days.

Source reference: p. 2, paras. 3, 6

The 6th Additional Sessions Judge, Banaskantha at Deesa, rejected the delay-condonation application on 17 March 2026.

Source reference: p. 2, para. 3
02

Issues

Whether the application for condonation of delay in filing the restoration application was required to be considered under Section 5 of the Limitation Act, 1963 and the applicable procedure governing restoration applications, rather than by examining whether the Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962 independently provided for condonation of delay.

Source reference: p. 2, paras. 3–5

Whether the petitioner was entitled to condonation of the 37-day delay and restoration of the application under Section 10 of the 1962 Act dismissed for want of prosecution.

Source reference: p. 3, paras. 6–7
03

Law Applied

The court applied Section 10(2) of the Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 1962, which permits an aggrieved landowner dissatisfied with the compensation determined by the competent authority to seek adjudication and does not prescribe a limitation period for such an application.

Source reference: p. 3, para. 6

It further applied Section 5 of the Limitation Act, 1963, under which delay may be condoned when sufficient cause is shown, and held that an application seeking condonation of delay in filing a restoration application must be considered in accordance with that provision and the procedure applicable under the Code of Civil Procedure, 1908.

Source reference: p. 2, para. 5; p. 3, para. 6

The court also recognized that a restoration application seeking recall of an order dismissing proceedings for default is procedurally distinct from the original application under Section 10 of the 1962 Act.

Source reference: p. 2, para. 5
04

Reasoning

The High Court held that the subordinate court had addressed the wrong question.

Source reference: p. 2, para. 5

The delay-condonation application accompanied the restoration application and did not relate to the filing of the original Section 10 application; therefore, there was no occasion to inquire whether the 1962 Act itself contained a provision for condonation of delay.

Source reference: p. 2, para. 5

The relevant inquiry was whether the 37-day delay in filing the restoration application should be condoned under Section 5 of the Limitation Act and the procedure governing restoration.

Source reference: p. 3, para. 6

The subordinate court instead rejected the application after refusing the advocate’s request for time to respond to the court’s query and to engage a new advocate, and it incorrectly inferred that the request was intended to delay the proceedings.

Source reference: p. 2, para. 4

Since the relevant statutory provisions and procedural principles had not been considered, the rejection order could not stand.

Source reference: p. 3, paras. 6–7
05

Holding

The High Court allowed the petition and set aside the order dated 17 March 2026 rejecting the delay-condonation application.

It allowed the application under Section 5 of the Limitation Act, 1963 and condoned the 37-day delay.

Source reference: p. 4, paras. 7–8

It also allowed the restoration application, recalled the order dated 6 September 2025, and restored CMA DC No. 116 of 2023, filed under Section 10 of the 1962 Act, to its original number.

Source reference: p. 4, paras. 7–8

The concerned court was directed to decide that application on its merits and strictly in accordance with law.

Source reference: p. 4, paras. 7–8
06

Acts & Sections Cited

2 provisions across 2 statutes referred to in this judgment. Each provision opens on LawLens.

Petroleum and Minerals Pipelines (Acquisition of Right of User in Land) Act, 19621

Limitation Act, 19631

Gujarat High Court

Original Court PDF

MALI LAKHMAJI NEMAJIvsCOMPETENT AUTHORITY AND DEPUTY COLLECTOR

Gujarat High Court · August 20, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment