The question

1. Whether the arbitrator’s finding that Flowmore waived prototype inspection and granted manufacturing clearance for tower structures was supported by the correspondence and the purchase order, or was patently illegal.

The court held

The Court answered the issues in favour of Flowmore, holding that the findings on waiver of tower prototype inspection and the scrap-based loss assessment suffered from patent illegality.

It also directed

It allowed the appeal, set aside the arbitral award, and disposed of the pending applications.

01Facts

Flowmore placed a purchase order dated 2 March 2019 on Skipper for manufacture and supply of structural material for a JUSNL project.

pp. 2, 9–10 · ¶ 3.1, 7

The order required written manufacturing clearance and provided for prototype inspection; it also provided for a 10% advance against an advance bank guarantee and pro forma invoice during manufacturing clearance.

pp. 2, 9–10 · ¶ 3.1, 7

After a dispute over drawings, prototype inspection, manufacturing clearance and payment of the advance, Flowmore cancelled the purchase order on 25 July 2019.

pp. 3–4 · ¶ 3.2–3.7

The arbitrator awarded Skipper ₹8,15,05,674 with interest and dismissed Flowmore’s counterclaims; the Section 34 challenge was dismissed.

p. 4 · ¶ 3.8–3.9

The Supreme Court restored Flowmore’s Section 37 appeal, leaving all questions open.

pp. 5–6 · ¶ 3.10

02Issues

i.1. Whether the arbitrator’s finding that Flowmore waived prototype inspection and granted manufacturing clearance for tower structures was supported by the correspondence and the purchase order, or was patently illegal.

pp. 11–18 · ¶ 10–20

ii.2. Whether the arbitrator’s acceptance of Skipper’s claim that the manufactured goods had to be sold as scrap because they were customised ignored material evidence that the goods were similar to those for another JUSNL project.

pp. 23–25 · ¶ 26–27

iii.3. Whether the award could be interfered with under Sections 34 and 37 of the Arbitration and Conciliation Act, 1996, notwithstanding the limited scope of judicial review.

pp. 19–23 · ¶ 23–25

03Law Applied

Under Sections 34 and 37 of the Arbitration and Conciliation Act, 1996, judicial review of an arbitral award—and particularly an appeal under Section 37—is limited; courts cannot reassess the merits or reweigh evidence merely because another view is possible.

pp. 19–22 · ¶ 23.1–23.3

However, a domestic award may be set aside for patent illegality where, among other things, a finding is based on no evidence, ignores vital evidence, is perverse or irrational, or adopts a contract construction no reasonable person could take.

pp. 14–16 · ¶ 16, citing Delhi Metro Rail Corporation Ltd. v. Delhi Airport Metro Express Pvt. Ltd., 2024 INSC 292 · pp. 22–23 · ¶ 24, citing Parsa Kente Collieries Ltd. v. Rajasthan Vidyut Utpadan Nigam Ltd., (2019) 7 SCC 236

Contradictory findings in an award may also make it unsustainable.

p. 18 · ¶ 21, citing Union of India v. V. Pundarikakshudu and Sons, (2003) 8 SCC 168

The “no evidence” and ignored-vital-evidence grounds must be applied cautiously; scant or weak evidence is not equivalent to no relevant evidence.

p. 25 · ¶ 27, citing Ramesh Kumar Jain v. Bharat Aluminium Company Ltd., 2025 SCC OnLine SC 2857

Provisions in the judgment · 5 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 9Section 28Section 31Section 34Section 37

04Reasoning

The Court found that Flowmore’s 19 June 2019 email authorised mass production only of stubs and templates for five locations; it did not authorise tower production or waive tower prototype inspection.

pp. 12–14 · ¶ 11–14

The respondent’s 1 July email, stating that tower prototypes would be released for production that day and the next, further contradicted the finding that inspection had already been waived.

pp. 17–18 · ¶ 19–20

The arbitrator’s contrary finding therefore lacked evidentiary support, and the resulting conclusion that manufacturing clearance—and the stage for payment of the advance—had arisen was also unsustainable.

pp. 14–18 · ¶ 15–20

Separately, although the Court declined to reappraise the evidence supporting the finding that material had been manufactured, it held that the arbitrator had failed to consider Skipper’s assertion that the goods were similar to those for another JUSNL project when accepting that the goods were customised and had to be sold as scrap.

pp. 23–25 · ¶ 25–27

That omission concerned vital evidence and vitiated the scrap-based loss finding.

pp. 23–25 · ¶ 25–27

05Holding

The Court answered the issues in favour of Flowmore, holding that the findings on waiver of tower prototype inspection and the scrap-based loss assessment suffered from patent illegality.

p. 25 · ¶ 28

It allowed the appeal, set aside the arbitral award, and disposed of the pending applications.

p. 25 · ¶ 28
Delhi High Court

Original Court PDF

Flowmore LimitedvsM/S Skipper Limited

Delhi High Court · October 28, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment