01Facts
The dispute arose from a Deed of Assignment of Development Rights dated December 6, 2010
¶ 2Following a Section 9 petition in 2019, the High Court referred the parties to arbitration and appointed a sole arbitrator
¶ 2After an interim order was passed on August 31, 2020, no further progress occurred for over two years
¶ 2, 16The Applicants subsequently filed a petition under Section 29A of the Arbitration and Conciliation Act, 1996 ("the Act") seeking an extension of the arbitrator’s mandate.
¶ 2, 16By an order dated October 18, 2024, the Court refused the extension, recording a specific finding that the Applicants had "abandoned the arbitration proceedings"
¶ 2, 16This order was upheld by the Supreme Court on February 14, 2025
¶ 2, 18The Applicants then issued a fresh notice invoking arbitration, alleging a continuous cause of action, and filed the present Section 11(6) application for the appointment of a new arbitrator
¶ 302Issues
i.1. Whether the Court can appoint an arbitrator under Section 11(6) of the Act after it has expressly refused to extend the mandate of a previous arbitrator under Section 29A due to the fault of the applicant
¶ 1, 20ii.2. Whether the refusal to extend a mandate under Section 29A results in the termination of the arbitral proceedings themselves, or merely the mandate of the specific arbitrator
¶ 1, 3003Law Applied
The Court analyzed the interplay between Section 11 (appointment of arbitrators), Section 29A (time limit for awards), and Section 32 (termination of proceedings) of the Act.
¶ 10, 34-35It relied on the Supreme Court’s decision in Rohan Builders (India) Private Limited v. Berger Paints India Limited, which established that while Section 29A(4) makes a tribunal functus officio, it does not terminate proceedings in absolute terms for a "faultless party"
¶ 10, 34-35The Court further applied the principle from Fedbank Financial Service Ltd. v. Narendra H Shelar, holding that arbitration clauses cannot be constantly revived if a party was remiss in diligent prosecution
¶ 8, 26-27It distinguished between the "termination of mandate" (Sections 14, 15, 29A) and "termination of proceedings" (Section 32), noting that while the former does not always cause the latter, a finding of "abandonment" by a competent court effectively ends the proceedings
¶ 22-24, 31Provisions in the judgment · 16 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 15 provisions
Section 9Section 11Section 12Section 13Section 14Section 15Section 17Section 21Section 23Section 25Section 32Section 33Section 34Section 37Section 43Code of Civil Procedure, 1908 Section 9
04Reasoning
The Court observed that while the expiration of a mandate under Section 29A(4) generally terminates the arbitrator's authority, it does not automatically terminate the arbitral proceedings under Section 32 unless the party is at fault
¶ 29-31Applying Rohan Builders, the Court held that the key determinant is whether the applicant is a "faultless party"
¶ 36In the present case, the Section 29A Court had already recorded a final, emphatic finding—upheld by the Supreme Court—that the Applicants had "abandoned" the proceedings due to gross negligence
¶ 17, 32The Court reasoned that if it were to appoint a new arbitrator under Section 11(6) after such a finding, it would essentially be sitting in appeal or review of the Section 29A order
¶ 31, 33The Court rejected the Applicants' plea of "continuous cause of action," noting that the fresh invocation was merely an attempt to re-litigate the same disputes covered by the abandoned proceedings and overreach the previous judicial refusal to extend the mandate
¶ 3905Holding
The Court dismissed the application, holding that a Section 11 application is not maintainable when a mandate extension under Section 29A was refused due to the applicant's own fault or abandonment
¶ 36, 41The Court concluded that where a party's conduct has led to a judicial finding of abandonment, the arbitral proceedings are terminated, and the referral court cannot exercise jurisdiction to appoint a substitute arbitrator, as the reference itself is no longer alive
¶ 37, 40Original Court PDF
Nalin Vallabhbhai PatelvsAtharva Realtors
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
