Facts
The petitioner executed contractual works for the operation and maintenance of fire safety and CCTV systems at Government Medical College & Hospital, Shahdol between 2020 and 2022.
Source reference: para. 2The petitioner approached the High Court seeking a writ of mandamus for the release of outstanding dues, refund of "illegally deducted" EPF/ESIC contributions (as the petitioner employed fewer than 20 workers and was statutorily exempt), and the application of a revised GST rate of 18% as per Government notifications.
Source reference: para. 1-2Internal departmental communications dated 23.07.2024 and 11.09.2024 expressly acknowledged the petitioner’s entitlement to these amounts.
Source reference: para. 4-5Despite budgetary allotments being sanctioned on 18.01.2024, the respondents failed to disburse the payments.
Source reference: para. 2, 5Issues
1. Whether the respondent authorities are liable to release admitted contractual dues and refund EPF/ESIC deductions acknowledging the petitioner’s statutory exemption.
Source reference: p. 4 / para. 3-52. Whether the petitioner is entitled to the revised GST rate of 18% on pending bills pursuant to GST Notification No. 11/2017 and subsequent PWD orders.
Source reference: p. 3 / para. 43. Whether interest is payable on the delayed disbursement of admitted dues.
Source reference: p. 5 / para. 8Law Applied
The Court relied on the provisions of the Employees' Provident Funds and Miscellaneous Provisions Act, 1952, noting that the mandatory deduction of EPF applies only when 20 or more workers are employed.
Source reference: para. 3Regarding tax, the Court referenced GST Notification No. 11/2017 (dated 13.07.2022) and the Public Works Department order (dated 31.10.2022), which revised the GST rate for works contracts from 12% to 18%.
Source reference: para. 2, 4On the issue of interest for delayed payments, the Court applied the principle established by the Hon’ble Supreme Court in Union of India vs. Willowood Chemicals (P) Ltd. (2022) 9 SCC 341, which justifies the award of interest on withheld entitlements.
Source reference: para. 8Reasoning
The Court observed that the respondents’ own internal documents (Annexures P/22 and P/30) admitted the petitioner’s claims.
Source reference: para. 3Specifically, the authorities acknowledged that since only eight workers were engaged, EPF/ESIC deductions were not legally required under the 1952 Act.
Source reference: para. 3Furthermore, the departments had already issued internal directions to process bills at the 18% GST rate and had received the necessary budgetary sanctions.
Source reference: para. 4-5Since the liability was "admitted" by the State through its internal correspondence and notifications, the Court found no justification for the continued withholding of funds.
Source reference: para. 6, 8The Court linked these factual admissions to the legal obligation of the State to act fairly and expeditiously once a debt is acknowledged.
Source reference: para. 6, 8Holding
The High Court disposed of the petition by directing Respondent No. 2 (Chief Engineer, PWD) to decide on the petitioner's representation (Annexure P/34) within 90 days.
The Court held that the authority must take specific note of the admitted positions in Annexures P/22, P/24, and P/30.
Source reference: para. 8If found entitled, the petitioner must be paid the outstanding amounts along with interest @ 6% per annum from the date of entitlement until actual payment, following the Willowood Chemicals precedent.
Source reference: para. 8The petition was disposed of without costs.
Source reference: para. 10Original Court PDF
M/S Shalini Construction Company v. The State of Madhya Pradesh and Others [2026:MPHC-JBP:20431 (WP No. 6733 of 2026)]
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in