Delhi High Court

Derivative claims under Section 9 are unsustainable once the underlying contractual authority is negatived by an arbitral award.

Mr Bhanu Arora vs Mr Aditya Bhutani & Anr.

Delhi High CourtJUDGMENT: May 20, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Petitioner (Bhanu Arora) entered into an Agreement to Sell (ATS) dated 10.03.2023 with Respondent No. 1 (Aditya Bhutani) for the purchase of the first floor of a property in Greater Kailash-I

Source reference: para. 1, 7

Respondent No. 1’s rights to the property were derived from a Collaboration Agreement dated 06.01.2023 with the owner, Respondent No. 2

Source reference: para. 5, 27

Subsequent disputes between the Respondents led to an arbitral award dated 03.02.2026, which rejected Respondent No. 1’s claims and authority to sell portions of the property

Source reference: para. 6, 14, 28

Meanwhile, in a Section 11 petition filed by the Petitioner, the Court appointed an arbitrator for disputes between the Petitioner and Respondent No. 1 but deleted Respondent No. 2 from the array of parties as they were a non-signatory

Source reference: para. 11, 31

The Petitioner approached the High Court under Section 9 of the Arbitration and Conciliation Act, 1996, seeking a status quo order and restraint against third-party rights

Source reference: para. 1-3
02

Issues

1. Whether a Section 9 petition for interim measures is maintainable when the underlying contractual authority (the Collaboration Agreement) of the vendor has been extinguished by a prior arbitral award

Source reference: para. 8, 29

2. Whether interim reliefs can be granted against a third party (Respondent No. 2) who is a non-signatory to the arbitration agreement and has already been deleted from the Section 11 proceedings

Source reference: para. 12, 32
03

Law Applied

The court applied Section 9 of the Arbitration and Conciliation Act, 1996, which provides for interim measures by the court

Source reference: para. 1

It relied on the principle of "derivative rights," holding that a party cannot claim greater rights than those held by their predecessor-in-interest

Source reference: para. 27, 30

Furthermore, it applied the principle that Section 9 reliefs generally cannot be granted against non-signatories who are neither necessary nor proper parties to the arbitration agreement

Source reference: para. 31-32

The court also respected the finality of arbitral awards under the Act, noting that an existing award binds the parties unless stayed or set aside

Source reference: para. 28
04

Reasoning

The Court reasoned that the Petitioner’s claim was entirely parasitic upon the rights of Respondent No. 1

Source reference: para. 27

Since the arbitral award dated 03.02.2026 expressly rejected Respondent No. 1’s authority to deal with the property, the "legal foundation" of the Petitioner’s ATS stood extinguished

Source reference: para. 29-30

Consequently, the Court could not grant interim protection for rights that no longer legally exist

Source reference: para. 19, 34

Regarding Respondent No. 2, the Court found that as a non-signatory who had been formally deleted from the Section 11 appointment proceedings, they could not be subjected to interim injunctions in a proceeding arising from an agreement to which they were not a party

Source reference: para. 31-32
05

Holding

The Court held that the petition was not maintainable as the substratum of the Petitioner’s claim (Respondent No. 1’s authority) was negatived by a binding arbitral award

The Court dismissed the petition but clarified that the Petitioner remains at liberty to pursue independent claims for damages or other remedies against Respondent No. 1 before the already-constituted Arbitral Tribunal

Source reference: para. 33, 36

No orders were passed against Respondent No. 2

Source reference: para. 32
Delhi High Court

Original Court PDF

Mr Bhanu AroravsMr Aditya Bhutani & Anr.

Delhi High Court · May 20, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment