Facts
The petitioners sought new electricity connections for premises situated in the Rajiv Nagar and Digha areas of Patna.
Source reference: p. 3They alleged that their online applications were not accepted and that they were informed that electricity connections would not be granted to premises situated in the Rajiv Nagar area.
Source reference: p. 3Relying on Clause 4.13(B) of Chapter 4 of the Bihar Electricity Supply Code, 2007, the petitioners contended that electricity connections could be granted even in respect of encroached Government, semi-Government, or public land, subject to submission of the prescribed documents and payment of requisite charges.
Source reference: p. 3–4The respondents stated that, if the petitioners submitted online applications along with all requisite documents, the competent authorities would consider them in accordance with law within one month.
Source reference: p. 4Issues
1. Whether the respondents could be directed to accept and consider the petitioners’ applications for new electricity connections in accordance with the Bihar Electricity Supply Code, 2007?
Source reference: p. 2–42. Whether the petitioners were entitled to an electricity connection despite the alleged location of their premises on encroached Government, semi-Government, or public land, subject to compliance with the prescribed requirements?
Source reference: p. 3–43. Whether the respondents were required to take an appropriate decision on the petitioners’ applications within a stipulated period?
Source reference: p. 4–5Law Applied
Section 43 of the Electricity Act, 2003, as invoked in the petitioners’ reliefs, imposes a duty upon a distribution licensee to supply electricity to an owner or occupier of premises upon receipt of an application, subject to the statutory and regulatory requirements.
Source reference: p. 2–3Clause 4.13(B) of Chapter 4 of the Bihar Electricity Supply Code, 2007, was relied upon as permitting consideration of applications even where the applicant could not produce conventional proof of ownership, including applications concerning encroached Government, semi-Government, or public land, provided the prescribed documents and requirements were furnished.
Source reference: p. 3–4The petitioners also relied upon the Supreme Court’s decision in Sri Chandu Khamaru v. Smt. Nayan Malik & Others, Civil Appeal No. 7572 of 2011, concerning the statutory right to seek an electricity connection.
Source reference: p. 2–3The High Court, however, ultimately directed only consideration of the applications in accordance with law and did not conclusively adjudicate the petitioners’ entitlement to connections.
Source reference: p. 4–5Reasoning
The Court recorded the petitioners’ grievance that their online applications had not been accepted and that they had been denied connections solely because of the location of their premises.
Source reference: p. 3Since the petitioners asserted their willingness to furnish all documents and pay the requisite charges under Clause 4.13(B), and the respondents agreed that compliant applications would be considered in accordance with law, the Court treated consideration of the applications—not automatic grant of electricity connections—as the appropriate relief.
Source reference: p. 4Accordingly, the Court required the petitioners to submit online applications with all requisite documents and obliged Respondent Nos. 5 and 6 to examine and decide those applications within the prescribed period.
Source reference: p. 4–5Holding
The writ petition was disposed of with a direction to the petitioners to submit online applications, along with all requisite documents, within two weeks from 06 August 2026.
If such applications were filed, Respondent Nos. 5 and 6—the Executive Engineer and Assistant Electrical Engineer concerned—were directed to consider them and take an appropriate decision in accordance with law within one month from receipt of the applications.
Source reference: p. 5The Court did not order the immediate grant of electricity connections; it directed lawful consideration of the applications.
Source reference: p. 5Acts & Sections Cited
1 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Electricity Act, 20031
Original Court PDF
Rajesh KumarvsThe Bihar State Power Holding Company Limited
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
