Delhi High CourtArbitration and MediationContract Law

Eighteen percent arbitral interest is a valid exercise of statutory discretion under the pre-amendment regime.

Mcdv.Anil Gupta And Ors

Eighteen percent arbitral interest is a valid exercise of statutory discretion under the pre-amendment regime.. Mcd vs Anil Gupta And Ors. Delhi High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the award of interest at 18% per annum is excessive, arbitrary, or contrary to the Interest Act, 1978 and Section 31(7) of the Arbitration and Conciliation Act, 1996

The court held

The Court upheld the interest rate of 18% per annum as a reasoned exercise of arbitral discretion

It also directed

However, it modified the commencement date to 06.07.2008 (the date of invocation of arbitration) to ensure the award aligned with permissible legal parameters and the claimant's own demands

The Petition was disposed of with the direction that interest shall run from 06.07.2008 until realization

No order as to costs

01Facts

The Petitioner (MCD) awarded a contract to Respondent No. 1 in 2004 for the construction of a Zonal Building at Narela

¶ 5-6

Following disputes over claims such as escalation under Clause 10CC and watch and ward expenses, the matter was referred to a Sole Arbitrator

¶ 7

On 01.04.2011, the Arbitrator awarded the Respondent’s claims along with interest at 18% per annum from 08.03.2004

¶ 8

After a complex procedural history involving a previous Section 34 judgment and a subsequent modification that set aside the interest component, the Division Bench remanded the matter for fresh adjudication confined strictly to the limited issue of the grant of interest

¶ 3, 15-16

02Issues

i.1. Whether the award of interest at 18% per annum is excessive, arbitrary, or contrary to the Interest Act, 1978 and Section 31(7) of the Arbitration and Conciliation Act, 1996

¶ 17-19

ii.2. Whether the award constitutes impermissible "interest on interest" prohibited under Section 3(3)(c) of the Interest Act

¶ 18

iii.3. Whether the Arbitrator erred in fixing the commencement date for interest as 08.03.2004

¶ 22-23

03Law Applied

The Court applied Section 31(7) of the Arbitration and Conciliation Act, 1996 (pre-2015 amendment), which grants arbitrators wide discretion to award interest at "reasonable" rates and establishes 18% per annum as the statutory default rate for post-award interest

¶ 46-49

It relied on Hyder Consulting (UK) Ltd. v. Governor, State of Orissa, which defined the "sum" in Section 31(7)(b) to include pre-award interest, thus permitting interest on the aggregate amount

¶ 53

The Court also followed Shahi & Associates v. State of U.P. [para 57] and Larsen Air Conditioning & Refrigeration Co. v. Union of India [para 58], affirming that 18% interest is a valid legislative benchmark under the unamended Act.

¶ 57, 58

Finally, it referenced Gayatri Balasamy v. M/s ISG Novasoft Technologies Limited regarding the limited power to modify interest components under Section 34

¶ 66-67

Provisions in the judgment · 13 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 9 provisionsSection 18Section 28Section 31Section 34Section 36Section 37Section 75Section 81Section 85

Interest Act, 1978 Section 2Section 3

Indian Contract Act, 1872 Section 23

Code of Civil Procedure, 1908 Section 34

04Reasoning

The Court held that since the arbitration commenced in 2008, the pre-2015 amendment regime applied, where Section 31(7)(a) provides unfettered discretion to award interest unless contractually prohibited

¶ 46-48

The Petitioner’s reliance on the Interest Act to cap rates at current bank rates was rejected because the 18% rate was a statutorily recognized benchmark in Section 31(7)(b)

¶ 49-50

Regarding the "interest on interest" argument, the Court applied the Hyder Consulting principle, stating that once interest is included in the "sum" awarded, the total constitutes a single amount upon which post-award interest may run

¶ 53-55

However, the Court found a "patent illegality" regarding the commencement date. The Arbitrator awarded interest from 08.03.2004 (tender date), despite the Respondent only claiming interest from 01.01.2007

¶ 64

Granting relief beyond what was prayed for (extra petita) was held legally untenable

¶ 65

05Holding

The Court upheld the interest rate of 18% per annum as a reasoned exercise of arbitral discretion

¶ 62, 69

However, it modified the commencement date to 06.07.2008 (the date of invocation of arbitration) to ensure the award aligned with permissible legal parameters and the claimant's own demands

¶ 68-69

The Petition was disposed of with the direction that interest shall run from 06.07.2008 until realization

¶ 69-70

No order as to costs

¶ 72
Delhi High Court

Original Court PDF

McdvsAnil Gupta And Ors

Delhi High Court · April 06, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment