Facts
The Petitioner (MCD) awarded a contract to Respondent No. 1 in 2004 for the construction of a Zonal Building at Narela
Source reference: para 5-6Following disputes over claims such as escalation under Clause 10CC and watch and ward expenses, the matter was referred to a Sole Arbitrator
Source reference: para 7On 01.04.2011, the Arbitrator awarded the Respondent’s claims along with interest at 18% per annum from 08.03.2004
Source reference: para 8After a complex procedural history involving a previous Section 34 judgment and a subsequent modification that set aside the interest component, the Division Bench remanded the matter for fresh adjudication confined strictly to the limited issue of the grant of interest
Source reference: para 3, 15-16Issues
1. Whether the award of interest at 18% per annum is excessive, arbitrary, or contrary to the Interest Act, 1978 and Section 31(7) of the Arbitration and Conciliation Act, 1996
Source reference: para 17-192. Whether the award constitutes impermissible "interest on interest" prohibited under Section 3(3)(c) of the Interest Act
Source reference: para 183. Whether the Arbitrator erred in fixing the commencement date for interest as 08.03.2004
Source reference: para 22-23Law Applied
The Court applied Section 31(7) of the Arbitration and Conciliation Act, 1996 (pre-2015 amendment), which grants arbitrators wide discretion to award interest at "reasonable" rates and establishes 18% per annum as the statutory default rate for post-award interest
Source reference: para 46-49It relied on Hyder Consulting (UK) Ltd. v. Governor, State of Orissa, which defined the "sum" in Section 31(7)(b) to include pre-award interest, thus permitting interest on the aggregate amount
Source reference: para 53The Court also followed Shahi & Associates v. State of U.P. [para 57] and Larsen Air Conditioning & Refrigeration Co. v. Union of India [para 58], affirming that 18% interest is a valid legislative benchmark under the unamended Act.
Source reference: para 57, 58Finally, it referenced Gayatri Balasamy v. M/s ISG Novasoft Technologies Limited regarding the limited power to modify interest components under Section 34
Source reference: para 66-67Reasoning
The Court held that since the arbitration commenced in 2008, the pre-2015 amendment regime applied, where Section 31(7)(a) provides unfettered discretion to award interest unless contractually prohibited
Source reference: para 46-48The Petitioner’s reliance on the Interest Act to cap rates at current bank rates was rejected because the 18% rate was a statutorily recognized benchmark in Section 31(7)(b)
Source reference: para 49-50Regarding the "interest on interest" argument, the Court applied the Hyder Consulting principle, stating that once interest is included in the "sum" awarded, the total constitutes a single amount upon which post-award interest may run
Source reference: para 53-55However, the Court found a "patent illegality" regarding the commencement date. The Arbitrator awarded interest from 08.03.2004 (tender date), despite the Respondent only claiming interest from 01.01.2007
Source reference: para 64Granting relief beyond what was prayed for (extra petita) was held legally untenable
Source reference: para 65Holding
The Court upheld the interest rate of 18% per annum as a reasoned exercise of arbitral discretion
However, it modified the commencement date to 06.07.2008 (the date of invocation of arbitration) to ensure the award aligned with permissible legal parameters and the claimant's own demands
Source reference: para 68-69The Petition was disposed of with the direction that interest shall run from 06.07.2008 until realization
Source reference: para 69-70No order as to costs
Source reference: para 72Original Court PDF
McdvsAnil Gupta And Ors
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in