01Facts
The Petitioner (MCD) awarded a contract to Respondent No. 1 in 2004 for the construction of a Zonal Building at Narela
¶ 5-6Following disputes over claims such as escalation under Clause 10CC and watch and ward expenses, the matter was referred to a Sole Arbitrator
¶ 7On 01.04.2011, the Arbitrator awarded the Respondent’s claims along with interest at 18% per annum from 08.03.2004
¶ 8After a complex procedural history involving a previous Section 34 judgment and a subsequent modification that set aside the interest component, the Division Bench remanded the matter for fresh adjudication confined strictly to the limited issue of the grant of interest
¶ 3, 15-1602Issues
i.1. Whether the award of interest at 18% per annum is excessive, arbitrary, or contrary to the Interest Act, 1978 and Section 31(7) of the Arbitration and Conciliation Act, 1996
¶ 17-19ii.2. Whether the award constitutes impermissible "interest on interest" prohibited under Section 3(3)(c) of the Interest Act
¶ 18iii.3. Whether the Arbitrator erred in fixing the commencement date for interest as 08.03.2004
¶ 22-2303Law Applied
The Court applied Section 31(7) of the Arbitration and Conciliation Act, 1996 (pre-2015 amendment), which grants arbitrators wide discretion to award interest at "reasonable" rates and establishes 18% per annum as the statutory default rate for post-award interest
¶ 46-49It relied on Hyder Consulting (UK) Ltd. v. Governor, State of Orissa, which defined the "sum" in Section 31(7)(b) to include pre-award interest, thus permitting interest on the aggregate amount
¶ 53The Court also followed Shahi & Associates v. State of U.P. [para 57] and Larsen Air Conditioning & Refrigeration Co. v. Union of India [para 58], affirming that 18% interest is a valid legislative benchmark under the unamended Act.
¶ 57, 58Finally, it referenced Gayatri Balasamy v. M/s ISG Novasoft Technologies Limited regarding the limited power to modify interest components under Section 34
¶ 66-67Provisions in the judgment · 13 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 9 provisions
Section 18Section 28Section 31Section 34Section 36Section 37Section 75Section 81Section 85Interest Act, 1978 Section 2Section 3
Indian Contract Act, 1872 Section 23
Code of Civil Procedure, 1908 Section 34
04Reasoning
The Court held that since the arbitration commenced in 2008, the pre-2015 amendment regime applied, where Section 31(7)(a) provides unfettered discretion to award interest unless contractually prohibited
¶ 46-48The Petitioner’s reliance on the Interest Act to cap rates at current bank rates was rejected because the 18% rate was a statutorily recognized benchmark in Section 31(7)(b)
¶ 49-50Regarding the "interest on interest" argument, the Court applied the Hyder Consulting principle, stating that once interest is included in the "sum" awarded, the total constitutes a single amount upon which post-award interest may run
¶ 53-55However, the Court found a "patent illegality" regarding the commencement date. The Arbitrator awarded interest from 08.03.2004 (tender date), despite the Respondent only claiming interest from 01.01.2007
¶ 64Granting relief beyond what was prayed for (extra petita) was held legally untenable
¶ 6505Holding
The Court upheld the interest rate of 18% per annum as a reasoned exercise of arbitral discretion
¶ 62, 69However, it modified the commencement date to 06.07.2008 (the date of invocation of arbitration) to ensure the award aligned with permissible legal parameters and the claimant's own demands
¶ 68-69The Petition was disposed of with the direction that interest shall run from 06.07.2008 until realization
¶ 69-70No order as to costs
¶ 72Original Court PDF
McdvsAnil Gupta And Ors
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
