01Facts
The Petitioner (MORT&H/PWD) invited bids for the rehabilitation and upgradation of a section of NH-217 in Odisha. An agreement was signed on March 21, 2014, with a 730-day completion period.
p. 2The project faced significant delays from the outset due to discrepancies in benchmarks (TBM values) and failure to hand over encumbrance-free land.
pp. 28-30Despite granting several extensions of time (EOT) without liquidated damages (LD) until March 31, 2022, the Petitioner prematurely closed the contract effective May 31, 2022.
p. 5, 31Post-closure, the Petitioner imposed LD and recovered the amount by invoking Performance Bank Guarantees (PBG).
p. 5The Respondent (contractor) had also undergone Corporate Insolvency Resolution Process (CIRP) between 2018 and 2021.
p. 5, 34A three-member Arbitral Tribunal awarded the Respondent ₹48.57 Crores, finding the Petitioner responsible for the delays. The Petitioner challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996.
pp. 1-202Issues
i.Whether the invocation of arbitration was barred by limitation, specifically considering the impact of CIRP proceedings and the COVID-19 pandemic.
pp. 33-34 / para. 21ii.Whether the imposition of Liquidated Damages (LD) and the subsequent foreclosure of the contract by the Petitioner were legal and valid.
pp. 31-33 / para. 17-19iii.Whether the Arbitral Tribunal’s findings on the attributability of delay and the grant of claims for overheads and machinery costs were perverse or patently illegal.
pp. 36-38 / para. 26-2803Law Applied
The court primarily applied Section 34 of the Arbitration and Conciliation Act, 1996, which restricts judicial interference to "patent illegality" or "conflict with public policy," excluding re-appreciation of evidence.
p. 12, 17, 21It relied on Associate Builders v. DDA and Ssangyong Engg. & Construction Co. Ltd. v. NHAI regarding the limited scope of review and the definition of perversity.
p. 15, 21Section 60(6) of the Insolvency and Bankruptcy Code (IBC), 2016, was applied to exclude the moratorium period for limitation purposes.
p. 34The court also invoked Section 55 of the Indian Contract Act, 1872, regarding the effect of accepting performance at a time other than agreed upon, and and the Cognizance for Extension of Limitation, In re (Supreme Court) regarding COVID-19 limitation tolling.
p. 33, 34Provisions in the judgment · 10 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 28Section 34Section 75Section 81
Indian Contract Act, 1872 Section 23Section 53Section 54Section 55Section 73
Insolvency and Bankruptcy Code, 2016. Section 60
04Reasoning
The court found that the Arbitral Tribunal’s decision was based on a thorough examination of evidence, including the Engineer’s own letters which admitted that delays—such as land encumbrances and TBM discrepancies—were beyond the contractor's control.
pp. 28-31Regarding limitation, the court affirmed that the period during which the Respondent was under CIRP must be excluded under Section 60(6) of the IBC, and additional relief was provided by the Supreme Court’s COVID-19 tolling orders; thus, the 2023 invocation for a 2022 closure was timely.
pp. 34-35On the merits of LD, the court upheld the view that once an employer grants extensions without reserving the right to claim damages or by leading the contractor to believe no LD would be levied, they cannot retrospectively impose penalties after performance is accepted.
pp. 32-33The court also noted that the Petitioner failed to file its claims before the Resolution Professional during the CIRP, thereby extinguishing their counter-claims under the principle of Ghanshyam Mishra v. Edelweiss.
p. 3505Holding
The court held that the Tribunal's interpretation of the contract and the attribution of delay to the Petitioner were "possible" and "reasonable" views.
p. 39The court dismissed the Section 34 petition and upheld the Arbitral Award in its entirety, affirmed the refund of encashed PBGs (Claim 1) and the compensation for overheads, machinery, and GST (Claims 2, 3, 4, 6, and 7) while maintaining that the Petitioner’s counter-claims stood extinguished. The Petition and all pending applications were dismissed.
pp. 35-40 · ¶ 37Original Court PDF
Public Works Department Nh Wing And AnrvsMs Gvr Infra Projects Ltd
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in