Bombay High Court

Existence of an arbitration clause overrides conflicting departmental mechanisms and necessitates arbitrator appointment despite non-exhaustion of internal appeals.

Generic Engineering Construction And Projects Ltd vs Maharashtra Maritime Board

Bombay High CourtJUDGMENT: April 27, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Petitioner was awarded a contract for constructing an office building for the Respondent (MMB) via a Work Order dated January 25, 2023

Source reference: para. 2

Due to alleged delays and breaches, the Respondent issued a termination order on August 18, 2025

Source reference: para. 2

The Petitioner invoked Clause 25 of the General Conditions of Contract (GCC) to appoint a Dispute Review Expert (DRE), but the Respondent did not comply

Source reference: para. 3

Consequently, the Petitioner invoked arbitration under Section 21 of the Arbitration and Conciliation Act, 1996, and filed an application under Section 11 for the appointment of an arbitrator and a petition under Section 9 for interim measures against the termination and subsequent fresh tender

Source reference: para. 1, 4
02

Issues

1. Whether a valid arbitration agreement exists between the parties that covers disputes relating to the termination of the contract.

Source reference: para. 15, 18

2. Whether the Petitioner was required to exhaust internal departmental remedies (appeals to the Chief Engineer/Secretary) as a mandatory pre-condition before seeking the appointment of an arbitrator.

Source reference: para. 13, 30
03

Law Applied

Section 11 of the Arbitration and Conciliation Act, 1996 regarding the appointment of arbitrators

Source reference: para. 1

Clause 25.2 of the GCC, which provides for referral of disputes to arbitration

Source reference: para. 17

Principle of "harmonious construction" to reconcile conflicting contractual clauses

Source reference: para. 29

Visa International Limited v. Continental Resources (USA) Ltd., establishing that if correspondence shows settlement is impossible, pre-arbitral conditions shouldn't block the appointment of an arbitrator

Source reference: para. 9, 32

Quick Heal Technologies Ltd. v. NCS Computech Pvt. Ltd. to emphasize that headnotes do not override the express content of a clause

Source reference: para. 8, 9
04

Reasoning

The Respondent argued that Clause 36 of the Contractor’s Bid (giving priority under GCC Clause 2.3) only provided for internal appeals and not arbitration

Source reference: para. 11, 22

However, the Court found that Clause 25.2 of the GCC contained an express agreement to arbitrate which was not in conflict with Clause 36, but rather supplementary

Source reference: para. 22

Significantly, the Court noted that Clause 3.3 of the Special Conditions of Contract (SCC), which originally excluded termination from arbitration, had been consciously deleted by the parties, signifying an intent to arbitrate termination disputes

Source reference: para. 28

Regarding pre-arbitral steps, the Court reasoned that since the termination decision was taken by the Chief Executive Officer (CEO)—who is higher in rank than the appellate authorities mentioned in the internal mechanism (Chief Engineer)—such internal remedies were "clearly inapplicable" and "not possible"

Source reference: para. 30, 31

The Court held that in cases of conflicting or confusing clauses, it must rule in favor of arbitration to facilitate de-clogging of courts

Source reference: para. 34
05

Holding

The Court held that a valid arbitration agreement exists and that the dispute is arbitrable

The Court allowed the Section 11 application and appointed Smt. Justice Anuja Prabhudesai (Retd.) as the Sole Arbitrator. The Section 9 Petition was converted into an application under Section 17 to be decided by the newly constituted Arbitral Tribunal. All rights and contentions were kept open for the Tribunal's adjudication

Source reference: para. 37, 38, 39
Bombay High Court

Original Court PDF

Generic Engineering Construction And Projects LtdvsMaharashtra Maritime Board

Bombay High Court · April 27, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment