Facts
The Petitioner-tenant challenged the judgment dated 10.02.2026 of the learned Additional Rent Controller, Central District, Tis Hazari Courts, Delhi, in RC ARC/735/2023, arising from the Respondent-landlord’s eviction proceedings under the Delhi Rent Control Act, 1958.
Source reference: p.1, para.1The tenant had specifically objected that the landlord’s plea of bona fide requirement was premature because the landlord had only applied, on 15.05.2023, for a licence from the Town and Country Planning Department, Haryana, to establish a Cyber City, and no licence or permission had allegedly been granted.
Source reference: pp.2–3, paras.2–3The tenant further contended that the impugned judgment did not consider this objection.
Source reference: pp.2–3, paras.4–5The landlord accepted that the objection had not been specifically addressed but argued that the omission did not justify revisional interference and relied on Maganlal s/o Kishanlal Godha v. Nanasaheb s/o Udhaorao Gadewar, (2010) 13 SCC 98.
Source reference: p.3, para.6The landlord also submitted that the tenant could seek restitution under Section 19 of the DRC Act if the asserted bona fide requirement ultimately proved unfounded.
Source reference: p.3, para.7Issues
Whether the High Court, while exercising supervisory and revisional jurisdiction under the proviso to Section 25B(8) of the DRC Act, could interfere where the learned ARC failed to consider a specific and substantive objection concerning the absence of the requisite licence for the proposed Cyber City.
Source reference: pp.4–6, paras.9–17Whether the landlord’s plea of bona fide requirement was premature or otherwise legally sustainable in the absence of the requisite licence or permission from the competent authority.
Source reference: pp.2–3, paras.2–3; p.6, para.17Law Applied
The Court applied the proviso to Section 25B(8) of the Delhi Rent Control Act, 1958, under which the High Court exercises limited supervisory and revisional jurisdiction rather than appellate jurisdiction.
Source reference: pp.4–5, paras.9–14Relying on Sarla Ahuja v. United India Insurance Co. Ltd., (1998) 8 SCC 119, Hindustan Petroleum Corporation Ltd. v. Dilbahar Singh, (2014) 9 SCC 78, and Abid-Ul-Islam v. Inder Sain Dua, (2022) 6 SCC 30, the Court held that interference is confined to examining the legality, propriety, and fairness of the decision-making process and is warranted where there is an error apparent on the face of the record, jurisdictional error, material irregularity, perversity, or absence of adjudication.
Source reference: pp.4–5, paras.10–12The Court also relied on Pankaj Pahwa v. Prem Wati, 2024:DHC:9322, and Sanjeev Hiranandani v. Sunny Grover, 2025:DHC:11285, for the limited scope of revisional scrutiny.
Source reference: p.4, para.11; p.5, para.13Section 19 of the DRC Act was noted as providing a possible remedy of restitution if the landlord’s bona fide requirement was later found to be absent.
Source reference: p.3, para.7The landlord relied on Maganlal s/o Kishanlal Godha, which was cited for the proposition that a landlord need not await uncertain statutory approvals before asserting bona fide requirement.
Source reference: p.3, para.6Reasoning
The Court found that the tenant had raised a specific, substantive, and document-supported objection that the landlord had merely applied for the Cyber City licence and had not obtained the requisite permission.
Source reference: p.6, para.16Although the learned ARC had considered several other objections, the impugned judgment contained no reference to or determination of this particular contention.
Source reference: p.6, para.16The High Court did not decide whether the absence of the licence ultimately defeated the landlord’s bona fide requirement; that question was left for the ARC to determine independently on the material available.
Source reference: p.7, para.17However, because the objection went to the root of the controversy, its complete omission constituted a material infirmity and failure to exercise jurisdiction, thereby vitiating the decision-making process and justifying interference under Section 25B(8).
Source reference: pp.6–7, paras.16–17Holding
The Court held that the impugned judgment could not be sustained because the learned ARC had failed to adjudicate the tenant’s material objection regarding the absence of the requisite licence for the proposed Cyber City.
The judgment dated 10.02.2026 was accordingly set aside, and the matter was restored to the learned ARC for fresh consideration.
Source reference: p.7, para.18The parties were directed to appear before the learned ARC on 11.08.2026, and the revision petition and pending applications were disposed of in those terms.
Source reference: p.7, paras.19–20Original Court PDF
Sports Goods Toys Export Promotion CouncilvsM/S Mohan Investments Properties Pvt Ltd
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in