Facts
TANGEDCO issued a 2017 tender for procurement of 1,500 MW of solar power. VSR Solar Power Private Limited was declared the L-1 bidder, furnished performance bank guarantees totalling ₹10 crores, and executed a 25-year Power Purchase Agreement (PPA) with TANGEDCO on 22 March 2018.
Source reference: pp.3–4; paras.4–6The Appellant subsequently selected and purchased project land at Vilathikulam, Tuticorin District, and commenced preliminary development work.
Source reference: p.4; para.7It contended that the imposition of safeguard duty on imported solar modules, followed by Cyclone Gaja and heavy rains in November–December 2018, adversely affected the project, including through waterlogging and inaccessibility of the site.
Source reference: pp.5–6; paras.9–12The Appellant sought extension of the scheduled commercial operation date (SCOD), but TANGEDCO declined the request and later invoked and encashed a performance bank guarantee of ₹5.10 crores.
Source reference: pp.6–7; paras.12, 14–16The Appellant filed DRP No. 7 of 2020 before the Tamil Nadu Electricity Regulatory Commission (TNERC), seeking extension of COD, protection against enforcement of securities, and repayment of the encashed amount.
Source reference: p.8; para.17By order dated 2 February 2021, TNERC refused the extension, held that the PPA had automatically terminated upon non-commissioning within the stipulated period, and upheld TANGEDCO’s entitlement to invoke the bank guarantee and claim liquidated damages.
Source reference: p.9; para.18The Appellant challenged that order before APTEL.
Source reference: no citationIssues
Whether TNERC failed to adjudicate the Appellant’s pleaded case that Cyclone Gaja and consequential heavy rains constituted a Force Majeure event under Clause 16 of the PPA and materially affected the project’s progress.
Source reference: pp.9–18; paras.20–30Whether the impugned order was unsustainable because TNERC discussed contractual provisions and timelines belonging to other project developers rather than the PPA executed between the parties.
Source reference: p.18; para.31Whether the issues concerning TANGEDCO’s entitlement to encash the performance bank guarantees and the Appellant’s liability to pay liquidated damages could be determined without first deciding the effect of the alleged Force Majeure event.
Source reference: p.19; para.32Law Applied
The Tribunal applied the contractual framework governing the parties, particularly Clause 14 of the PPA concerning commissioning timelines, termination, performance security and liquidated damages, and Clause 16 concerning Force Majeure.
Source reference: pp.2–3, 19; paras.1, 28, 33It held that where a material factual ground is specifically pleaded, denied by the opposite party, and reaffirmed in rejoinder, the adjudicating authority must consider it, analyse the applicable contractual provision, and record findings on it in the final order.
Source reference: pp.17–18; para.30An order that fails to decide a material issue or proceeds on the basis of contractual terms belonging to another agreement reflects non-application of mind and is liable to be set aside.
Source reference: p.18; para.31The Tribunal also directed the Commission to keep in view its judgment dated 29 July 2026 in Appeal No. 151 of 2021, arising in a similar factual and procedural context.
Source reference: p.19; para.33Reasoning
Although the Appellant expressly pleaded that the cyclone and heavy rains inundated the project site, prevented access, and delayed construction, and although TANGEDCO disputed that assertion, TNERC merely recorded the parties’ pleadings without determining whether the event occurred, whether it affected this particular project, or whether it fell within Clause 16 of the PPA.
Source reference: pp.10–17; paras.21–29TNERC’s discussion under the Force Majeure issue addressed only the safeguard duty and omitted the alleged natural disaster altogether.
Source reference: pp.16–17; paras.28–29The Tribunal held that the Commission was required to adjudicate this material issue before deciding COD extension, termination, bank-guarantee invocation or liquidated damages.
Source reference: no citationFurther, TNERC had relied on Clause 14 and commissioning timelines from other PPAs, rather than the Appellant’s PPA, demonstrating a material factual and contractual mismatch.
Source reference: p.18; para.31Since the consequences of delay depended on the unresolved Force Majeure question, the Tribunal declined to decide the bank-guarantee and liquidated-damages issues itself.
Source reference: p.19; para.32Holding
APTEL set aside TNERC’s order dated 2 February 2021 as unsustainable for failure to consider and decide the Appellant’s material Force Majeure case and for reliance on contractual provisions relating to other projects.
The matter was remanded to TNERC for fresh consideration of the effect of the cyclone and consequential heavy rains under Clause 16 of the PPA, along with the consequential issues concerning COD extension, termination, encashment of performance bank guarantees and liquidated damages.
Source reference: p.19; para.33TNERC was directed to provide all parties a reasonable opportunity of hearing and pass a fresh order within three months from receipt of the judgment, while considering APTEL’s observations in Appeal No. 151 of 2021.
Source reference: p.19; para.33Original Court PDF
VSR Solar Power Private LimitedvsTamil Nadu Electricity Regulatory Commission & Ors
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in