01Facts
The Hooghly River Bridge Commissioners invited e-tenders for construction of two flyovers, and the petitioner submitted an EMD of ₹73,97,650.
pp. 2–5 · ¶ 2(i)–(v)After the petitioner was declared the successful bidder, the Commissioners issued a letter of acceptance-cum-work order on 18 November 2016.
pp. 2–5 · ¶ 2(i)–(v)The petitioner then sought to withdraw from the tender on 5 December 2016, having neither furnished performance security nor executed the agreement.
pp. 2–5 · ¶ 2(i)–(v)The Commissioners terminated the award on 7 December 2016, invoking the tender conditions.
pp. 2–5 · ¶ 2(i)–(v)Following unsuccessful requests for refund, the petitioner challenged the Commissioners’ memo dated 2 December 2021 forfeiting the EMD.
pp. 2–5 · ¶ 15–1702Issues
i.1. Whether the Commissioners were entitled under the Instructions to Bidders to forfeit the petitioner’s EMD after it failed to execute the agreement and furnish performance security.
pp. 11–12 · ¶ 17–18ii.2. Whether Section 74 of the Indian Contract Act, 1872 governed the forfeiture and required the Commissioners to establish loss or damages.
p. 12 · ¶ 1803Law Applied
Clause 15.6 of the Instructions to Bidders permitted forfeiture of bid security where a successful bidder failed to sign the agreement or furnish performance security; Clauses 31–33 required execution of the agreement and performance security and treated non-compliance as grounds for annulment and forfeiture.
p. 8 · ¶ 14The Court relied on National Highways Authority of India v. Ganga Enterprises, (2003) 7 SCC 410; State of Haryana v. Malik Traders, (2011) 13 SCC 200; and National Thermal Power Corporation Ltd. v. Ashok Kumar Singh, (2015) 4 SCC 252, for the principle that a bidder who agrees to forfeiture of bid security upon specified non-performance cannot claim its return merely because the bidder could withdraw or failed to proceed with the contract.
pp. 12–16 · ¶ 19–22, 25The Court held that Section 74 did not apply to the bid-security forfeiture in the circumstances of this case.
pp. 12–16 · ¶ 19–22, 25Provisions in the judgment · 3 · Linked ones open on LawLens
Indian Contract Act, 1872 Section 5Section 74
Limitation Act, 1963 Section 113
04Reasoning
The letter of acceptance was both acceptance of the petitioner’s bid and a formal work order, subject to the requirements of furnishing performance security and signing the agreement.
pp. 10–11 · ¶ 15–17The petitioner did neither and instead sought to step down from the tender; the Commissioners then terminated the award under the tender conditions.
pp. 10–11 · ¶ 15–17The Court concluded that the forfeiture fell within the express terms of Clauses 15.6 and 33 and was consistent with the Supreme Court authorities on bid security.
pp. 10–11 · ¶ 15–17 · pp. 16–18 · ¶ 22–25It distinguished the petitioner’s cited decisions, including Kailash Nath Associates v. DDA, because those cases did not govern the specific contractual forfeiture of bid security at issue here.
pp. 16–18 · ¶ 22–2505Holding
The Court answered the forfeiture issue in the Commissioners’ favour and held that Section 74 did not entitle the petitioner to recover the EMD.
pp. 18–19 · ¶ 25–30Finding no merit in the writ petition, it dismissed the petition, vacated any interim order, dismissed pending interlocutory applications, and made no order as to costs.
pp. 18–19 · ¶ 25–30Original Court PDF
CORROGANON INDIA PRIVATE LIMITEDvsTHE STATE OF WEST BENGAL AND ORS
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
