Facts
The petitioners’ lands in South West Garo Hills, Meghalaya, were acquired in 2017–2018 for construction of the Indo-Bangladesh Border Fencing under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (“2013 Act”).
Source reference: p.3The Collector prepared draft awards dated 4 September 2018 and 9 October 2018, which were approved by the Joint Secretary, Revenue and Disaster Management Department.
Source reference: p.4Despite completion of the statutory formalities and preparation of the draft awards, compensation was not paid to the affected landowners.
Source reference: p.4The State and Union authorities attributed the delay to confusion and requests for clarification regarding the amounts reflected in the draft awards.
Source reference: p.4Several representations and court orders seeking progress in payment did not result in disbursement, leading the petitioners to seek a direction for payment of compensation.
Source reference: pp.3–5Issues
Whether the respondents were legally obligated to disburse compensation for the petitioners’ acquired lands after completion and approval of the draft awards under the 2013 Act.
Source reference: pp.3–4Whether administrative confusion between the State and Union authorities regarding the draft awards could justify the prolonged non-payment of compensation.
Source reference: pp.4–5Whether the Court should direct the respondents to resolve the outstanding issues and pay compensation within a specified time.
Source reference: p.5Law Applied
The Court applied the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, under which land acquired by the State must be followed by lawful determination and payment of compensation after completion of the prescribed acquisition process.
Source reference: p.3It further applied the general public-law principle that governmental authorities cannot retain possession of acquired land while indefinitely withholding compensation on account of administrative delay or inter-departmental confusion; prolonged failure to pay compensation, absent a valid legal justification, may constitute an abuse of governmental power.
Source reference: p.5No specific statutory section or judicial precedent was cited in the order.
Source reference: no citationReasoning
The Court found that the acquisition proceedings had been undertaken under the 2013 Act and that the draft awards had been prepared in 2018 and approved by the competent State authority.
Source reference: pp.3–4Consequently, the respondents’ obligation to proceed with payment could not be defeated by unresolved correspondence or uncertainty between the Union and State authorities concerning the award amounts.
Source reference: p.5The Court held that the explanations offered did not absolve the authorities of their responsibility to ensure timely payment, particularly as possession had been taken and the writ petition had remained pending since 2019.
Source reference: p.5The continuing delay, despite repeated orders intended to facilitate payment, warranted a mandatory time-bound direction.
Source reference: pp.4–5Holding
The Court disposed of the writ petition by directing the concerned State and Union authorities to resolve, without further delay, the prevailing confusion regarding the draft awards and take appropriate steps to disburse compensation to the affected landowners within three months from 21 September 2026.
The petitioners were therefore granted time-bound administrative relief, although the Court did not itself determine or modify the quantum of compensation.
Source reference: p.5Original Court PDF
RAJISON R. MARAK AND 5 ORS.vsSTATE OF MEGHALAYA AND 14 ORS.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
