Bombay High Court

Headline: Contemplated urgent interim relief exempts Section 12-A compliance despite pending mediation or missing non-starter report.

Phoenix Arc Private Limited vs Future Brands Limited

Bombay High CourtJUDGMENT: April 15, 20263 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Plaintiff, an asset reconstruction company, filed a suit for a mandatory injunction to compel Defendant No. 1 to infuse equity of Rs. 250 crores into Defendant No. 2 and to restrain the disposal of certain brands.

Source reference: para. 1-2

The Plaintiff is the assignee of loan facilities originally granted to Defendant No. 2, which were secured by royalty income from trademark license agreements.

Source reference: para. 2/8

These agreements were set to expire on July 1, 2025.

Source reference: para. 10

On March 21, 2025, the Plaintiff initiated pre-institution mediation under Section 12-A of the Commercial Courts Act ("the Act").

Source reference: para. 4/16

The mandatory three-month period for mediation expired on June 20, 2025, without a settlement.

Source reference: para. 12

The Plaintiff filed the present suit on July 4, 2025, citing the imminent expiry of the trademark agreements as a ground for urgent interim relief.

Source reference: para. 14/16

The Defendants raised a preliminary objection under Order VII Rule 11 of the CPC, arguing the suit was barred for non-compliance with Section 12-A, as no "Non-Starter Report" had been issued before filing, and alleged suppression of the Plaintiff's failure to pay mediation fees.

Source reference: para. 3-4
02

Issues

1. Whether the suit is liable to be rejected under Order VII Rule 11 CPC for non-compliance with the mandatory pre-institution mediation requirement under Section 12-A of the Act.

Source reference: para. 19

2. Whether the initiation of mediation, followed by the filing of a suit after the expiry of the statutory three-month period but before a Non-Starter Report is issued, satisfies the "exhaustion of remedy" under Section 12-A.

Source reference: para. 19/36

3. Whether the suit contemplated "urgent interim relief" from the Plaintiff's standpoint, thereby exempting it from the bar under Section 12-A.

Source reference: para. 19/29

4. Whether the Plaintiff’s conduct in the mediation process amounted to material suppression warranting dismissal at a preliminary stage.

Source reference: para. 19-20
03

Law Applied

Section 12-A of the Commercial Courts Act, 2015, which mandates pre-institution mediation unless the suit contemplates urgent interim relief.

Source reference: para. 29

Commercial Courts (Pre-Institution Mediation and Settlement) Rules, 2018, specifically Rule 3(8), which prescribes a three-month timeline for mediation.

Source reference: para. 35

Patil Automation Pvt. Ltd. v. Rakheja Engineers Pvt. Ltd. (2022) regarding the mandatory nature of Section 12-A.

Source reference: para. 24

Yamini Manohar v. T.K.D. Keerthi (2024) and Dhanbad Fuels Pvt. Ltd. v. Union of India (2025), which established that "urgent interim relief" must be assessed holistically from the plaintiff's standpoint.

Source reference: para. 24

Novenco Building and Industry A/S v. Xero Energy Engineering Solutions Pvt. Ltd. (2025), holding that a real need for urgent intervention to prevent irreparable harm exempts a party from mediation.

Source reference: para. 25-26
04

Reasoning

The court reasoned that the purpose of Section 12-A is to decongest courts through settlement, but it cannot be interpreted to strip a party of the right to seek urgent relief when a "peril" arises.

Source reference: para. 33-34

The court found that the Plaintiff did not abandon mediation; rather, the initial three-month period under Rule 3(8) expired on June 20, 2025, and no extension was granted by mutual consent.

Source reference: para. 40

The court observed that the trademark agreements—constituting the primary security for a debt exceeding Rs. 500 crores—expired on July 1, 2025, creating a genuine and objective urgency for interim protection.

Source reference: para. 39

The court rejected the "suppression" argument, noting that the Non-Starter Report was only generated on August 20, 2025 (after the suit was filed), and the Plaintiff had disclosed the mediation's initiation in the pleadings.

Source reference: para. 16/21

It held that "contemplating" urgent relief is a subjective standard based on the plaintiff's standpoint at the time of filing; the prior attempt at mediation did not preclude the Plaintiff from subsequently seeking court intervention when the situation became critical.

Source reference: para. 33/41
05

Holding

The court rejected the Defendants’ preliminary objections and held the suit maintainable.

It ruled that the bar under Section 12-A of the Commercial Courts Act did not apply because: (i) the Plaintiff had substantively exhausted the mediation period prescribed by the Rules; and (ii) the suit genuinely contemplated urgent interim relief due to the imminent expiry of security interests.

Source reference: para. 39/41

The court emphasized that insisting on a Non-Starter Report despite a valid need for urgent relief would render the Plaintiff remediless and defeat the object of the Act.

Source reference: para. 41
Bombay High Court

Original Court PDF

Phoenix Arc Private LimitedvsFuture Brands Limited

Bombay High Court · April 15, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment