Supreme Court

HEADLINE: Section 33(1) of the Arbitration Act permits only clerical corrections and prohibits substantive modification of interest types.

Gujarat Water Supply And Sewerage Board vs Saryu Plastics Pvt. Ltd.

Supreme CourtJUDGMENT: May 26, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Appellant (the Board) awarded rate contracts to the Respondent (the Company) for PVC pipes between 1998 and 2002. Following an audit alleging excess payments, the Board blacklisted the Company in 2003.

Source reference: para 2.3

In 2012, the parties executed an Arbitration Agreement with a six-month mandate.

Source reference: para 2.4

The proceedings were delayed primarily due to the Board’s failure to file replies and attend meetings.

Source reference: paras 3.9–3.15

The Arbitrator unilaterally extended the mandate several times up to September 30, 2015, with the Board’s tacit participation.

Source reference: paras 15–17

On October 27, 2015, the Arbitrator passed an Award for ₹1.01 Crores with simple interest at 21.675% for the pendente lite period and compound interest post-award.

Source reference: paras 3.29–3.30

The Board challenged the Award under Section 34, while the Company sought a "correction" under Section 33 to change "simple interest" to "compound interest".

Source reference: para 4

The Commercial Court modified the Award in a review proceeding, granting compound interest for the pendente lite period, which significantly increased the Board's liability.

Source reference: paras 7–8, 26

The High Court of Gujarat dismissed the Board’s appeals.

Source reference: para 9
02

Issues

1. Whether the arbitral mandate had validly subsisted at the time the Arbitral Award was passed.

Source reference: para 14

2. Whether the arbitral proceedings were conducted in accordance with principles of natural justice.

Source reference: para 14

3. Whether the Commercial Court possessed jurisdiction to modify the Award under Section 33(1)(a) of the Act to substitute simple interest with compound interest.

Source reference: para 14
03

Law Applied

The Court applied the principle of acquiescence and estoppel regarding the extension of an arbitrator's mandate in cases not governed by the 2015 Amendment.

Source reference: para 21

Section 33(1)(a) of the Arbitration and Conciliation Act, 1996, which limits the Tribunal's power to "computational, clerical, or typographical errors".

Source reference: para 30

Precedents including State of Arunachal Pradesh v. Damani Construction Co. and Gyan Prakash Arya v. Titan Industries Ltd. were cited to establish that Section 33 does not permit a substantive review or modification of the merits of an Award.

Source reference: para 30
04

Reasoning

The Court found that while the initial mandate was for six months, the Board never objected to the Arbitrator’s unilateral extensions and continued to participate, thereby tacitly consenting to the extension.

Source reference: para 19

Regarding natural justice, the Court noted that the Board’s own dilatory tactics and failure to attend the final hearing after three and a half years of proceedings precluded it from claiming a lack of opportunity.

Source reference: paras 23–25

On the substantive modification of interest, the Court held that the choice between "simple" and "compound" interest is a deliberate merit-based decision by the Arbitrator.

Source reference: para 31

Changing the interest type is not a clerical or typographical correction under Section 33(1)(a). The Commercial Court’s modification, which increased liability from ₹30.38 crores to ₹144.93 crores, was held to be an impermissible exercise of review jurisdiction.

Source reference: paras 26, 32
05

Holding

The Arbitrator had a valid mandate and followed natural justice.

A court or tribunal cannot use Section 33(1)(a) to substantively alter the nature of interest awarded.

Source reference: para 32

The Supreme Court allowed the appeals in part. It set aside the Commercial Court’s order modifying the interest. The Company is entitled only to "simple interest" at 21.675% for the pendente lite period as originally awarded.

Source reference: para 34
Supreme Court

Original Court PDF

Gujarat Water Supply And Sewerage BoardvsSaryu Plastics Pvt. Ltd.

Supreme Court · May 26, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment