Patna High Court

High Court lacks writ jurisdiction to declare land acquisition proceedings lapsed under Section 24(2) of 2013 Act.

Vijay Kumar Singh vs The State of Bihar

Patna High CourtJUDGMENT: July 08, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioners, claiming ownership of land in Mauza-Dujra, Patna, sought a declaration that land acquisition proceedings initiated in 1961 (Case No. 63 of 1961-62) had lapsed under Section 24(2) of the 2013 Act

Source reference: p.1-2

The dispute arose when the Patna Municipal Corporation (PMC) issued a letter on 16.05.2026 for the construction of "Prime Minister Ekta Mall" and commenced demolition of existing structures on the land without prior notice

Source reference: p.2

The PMC contended that the petitioners failed to approach the proper forum and failed to implead a necessary party, the Buddha Grih Nirmaan Sahyog Samiti Limited

Source reference: p.3
02

Issues

1. Whether the High Court, exercising writ jurisdiction under Article 226, is the appropriate forum to declare the lapse of land acquisition proceedings involving disputed questions of fact

Source reference: para. 7-8

2. Whether the demolition action by the Patna Municipal Corporation complied with the principles of natural justice

Source reference: para. 9, 12
03

Law Applied

Section 24 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, which stipulates that proceedings under the 1894 Act lapse if an award was made five years prior to the 2013 Act but physical possession was not taken or compensation was not paid

Source reference: para. 7-8

The principle of Audi Alteram Partem (natural justice), requiring a right to be heard before coercive state action

Source reference: para. 12

The established judicial restraint under Article 226 regarding "disputed questions of fact" that require evidentiary examination

Source reference: para. 10
04

Reasoning

The Court reasoned that determining whether a land acquisition has lapsed under Section 24(2) requires a factual inquiry into possession and compensation payment—matters necessitating the verification of documents and evidence

Source reference: para. 8

Such an exercise cannot be performed in writ jurisdiction; instead, the "Collector" is the competent authority to adjudicate these facts

Source reference: para. 8

The Court noted that the petitioners raised "jumbled and disputed questions of facts" and failed to join a necessary party, making the writ petition untenable in its current form

Source reference: para. 10

Acknowledging the PMC’s admission regarding the potential breach of natural justice during demolition, the Court found it necessary to provide interim protection while directing the petitioners to the statutory authority

Source reference: para. 12, 16
05

Holding

The Court declined to grant the declaration of lapse but disposed of the writ petition with liberty to the petitioners to approach the Collector, Patna, within two weeks

The Collector is directed to implead the necessary cooperative society and pass a reasoned order within three weeks after hearing all parties; a status quo is to be maintained and no coercive action taken against the petitioners until final adjudication by the Collector

Source reference: para. 14-16
Patna High Court

Original Court PDF

Vijay Kumar SinghvsThe State of Bihar

Patna High Court · July 08, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment