Facts
The Respondent, an industrial entity, challenged demand notices issued by the Tamil Nadu Electricity Board (Appellants) for recovery of monthly minimum charges totaling approximately Rs. 2.18 Crores.
Source reference: p. 3The Board alleged that despite completing works for HT supply and issuing a notice on 28.04.2007, the Respondent failed to avail supply within the three-month statutory period.
Source reference: p. 3The Respondent denied receipt of the first notice, claiming they only received a second notice dated 07.08.2007, and argued that the charges were inapplicable to an "additional load" scenario.
Source reference: p. 3-4A Single Judge of the High Court allowed the writ petitions on the grounds that the Board failed to prove service of the first notice.
Source reference: p. 3The Board preferred these intra-court appeals.
Source reference: p. 2Issues
1. Whether the High Court, under Article 226, should adjudicate complex factual disputes regarding the "readiness" of a consumer and the service of statutory notices.
Source reference: p. 5 / para. 82. Whether a writ petition is maintainable when specialized statutory alternate remedies are available under the Electricity Act, 2003, and the TNERC Supply Code.
Source reference: p. 8-9 / para. 17-19Law Applied
The Court applied Clause 31 of the TNERC Electricity Distribution Code, which mandates that an HT consumer must avail supply within three months of a written notice or remain liable for monthly minimum charges.
Source reference: p. 6-7 / para. 12-13It relied on Clause 18 of the Tamil Nadu Electricity Supply Code and Section 42(5) & (6) of the Electricity Act, 2003, which establish the Consumer Grievance Redressal Forum (CGRF) and the Electricity Ombudsman as the appropriate hierarchy for dispute resolution.
Source reference: p. 8-9 / para. 16-17Further, the Court applied the precedent from *Jaipur Vidyut Vitran Nigam Limited v. MB Power (Madhya Pradesh) Limited* (2024) 8 SCC 513, holding that the Electricity Act is an exhaustive code and discretionary writ jurisdiction should be restrained where statutory remedies exist.
Source reference: p. 9-10 / para. 18Reasoning
The Court observed that the core of the dispute—whether the notice dated 28.04.2007 was actually served—is a "trial-natured" factual controversy.
Source reference: p. 8 / para. 15It reasoned that the Writ Court cannot conduct a "roving enquiry" into voluminous documents or selective evidence to determine "readiness" to supply or consume electricity, as doing so risks a miscarriage of justice.
Source reference: p. 5 / para. 8-10The Court emphasized that the CGRF and Ombudsman are expert bodies designed to scrutinize original documents and oral evidence.
Source reference: p. 10 / para. 20Consequently, the Court held that the Single Judge erred by bypassing the statutory machinery provided under the Electricity Act.
Source reference: p. 10 / para. 18-19Holding
The Division Bench set aside the order dated 25.07.2022 and allowed the Writ Appeals.
It held that writ petitions challenging demand notices are generally not maintainable unless there is a total lack of jurisdiction or proven *mala fides*.
Source reference: p. 11 / para. 22The Respondent was granted liberty to approach the Consumer Grievance Redressal Forum within four weeks, with a direction to the Forum to decide the matter on merits by condoning the delay.
Source reference: p. 11 / para. 21Original Court PDF
The Superintending Engineer, TNEB & Anr. v. Khivaraj Tech Park Pvt. Ltd. [2026:MHC:931 (W.A. Nos. 1928 and 1936 of 2023)]
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in