Facts
The Respondent, an industrial entity, challenged demand notices issued by the Tamil Nadu Electricity Board (Appellants) for recovery of monthly minimum charges totaling approximately Rs. 2.18 Crores.
Source reference: p. 3The Board alleged that despite completing works for HT supply and issuing a notice on 28.04.2007, the Respondent failed to avail supply within the three-month statutory period.
Source reference: p. 3The Respondent denied receipt of the first notice, claiming they only received a second notice dated 07.08.2007, and argued that the charges were inapplicable to an "additional load" scenario.
Source reference: p. 3-4A Single Judge of the High Court allowed the writ petitions on the grounds that the Board failed to prove service of the first notice.
Source reference: p. 3The Board preferred these intra-court appeals.
Source reference: p. 2Issues
1. Whether the High Court, under Article 226, should adjudicate complex factual disputes regarding the "readiness" of a consumer and the service of statutory notices.
Source reference: p. 5 / para. 82. Whether a writ petition is maintainable when specialized statutory alternate remedies are available under the Electricity Act, 2003, and the TNERC Supply Code.
Source reference: p. 8-9 / para. 17-19Law Applied
The Court applied Clause 31 of the TNERC Electricity Distribution Code, which mandates that an HT consumer must avail supply within three months of a written notice or remain liable for monthly minimum charges.
Source reference: p. 6-7 / para. 12-13It relied on Clause 18 of the Tamil Nadu Electricity Supply Code and Section 42(5) & (6) of the Electricity Act, 2003, which establish the Consumer Grievance Redressal Forum (CGRF) and the Electricity Ombudsman as the appropriate hierarchy for dispute resolution.
Source reference: p. 8-9 / para. 16-17Further, the Court applied the precedent from *Jaipur Vidyut Vitran Nigam Limited v. MB Power (Madhya Pradesh) Limited* (2024) 8 SCC 513, holding that the Electricity Act is an exhaustive code and discretionary writ jurisdiction should be restrained where statutory remedies exist.
Source reference: p. 9-10 / para. 18Reasoning
The Court observed that the core of the dispute—whether the notice dated 28.04.2007 was actually served—is a "trial-natured" factual controversy.
Source reference: p. 8 / para. 15It reasoned that the Writ Court cannot conduct a "roving enquiry" into voluminous documents or selective evidence to determine "readiness" to supply or consume electricity, as doing so risks a miscarriage of justice.
Source reference: p. 5 / para. 8-10The Court emphasized that the CGRF and Ombudsman are expert bodies designed to scrutinize original documents and oral evidence.
Source reference: p. 10 / para. 20Consequently, the Court held that the Single Judge erred by bypassing the statutory machinery provided under the Electricity Act.
Source reference: p. 10 / para. 18-19Holding
The Division Bench set aside the order dated 25.07.2022 and allowed the Writ Appeals.
It held that writ petitions challenging demand notices are generally not maintainable unless there is a total lack of jurisdiction or proven *mala fides*.
Source reference: p. 11 / para. 22The Respondent was granted liberty to approach the Consumer Grievance Redressal Forum within four weeks, with a direction to the Forum to decide the matter on merits by condoning the delay.
Source reference: p. 11 / para. 21Acts & Sections Cited
4 provisions across 4 statutes referred to in this judgment. Linked provisions open on LawLens.
Letters Patent1
TNERC Electricity Distribution Code1
Tamil Nadu Electricity Supply Code1
Tamil Nadu Electricity Act, 20031
Original Court PDF
The Superintending Engineer, TNEB & Anr. v. Khivaraj Tech Park Pvt. Ltd. [2026:MHC:931 (W.A. Nos. 1928 and 1936 of 2023)]
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
![High Court should not adjudicate disputed facts regarding electricity billing when functional statutory alternate remedies exist.. The Superintending Engineer, TNEB & Anr. v. Khivaraj Tech Park Pvt. Ltd. [2026:MHC:931 (W.A. Nos. 1928 and 1936 of 2023)]. Madras High Court. LawLens](/stories/thumbnails/high-court-should-not-adjudicate-disputed-facts-regarding-electricity-billing-when-functio-4935c5ee63e3410eae1bec2e4f82ed69.webp)