Madras High Court
Employment and Labour LawAdministrative and Public Law

Higher civil engineering qualifications satisfy the prescribed ITI civil draftsmanship requirement.

THE DISTRICT COLLECTOR vs B.LAKSHMANA MURALI

Madras High CourtJUDGMENT: September 25, 20262 MIN READSOURCE JUDGMENT
Higher civil engineering qualifications satisfy the prescribed ITI civil draftsmanship requirement.. THE DISTRICT COLLECTOR vs B.LAKSHMANA MURALI. Madras High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioner was appointed as Road Inspector Grade-II after participating in a written examination and securing first rank. He held a Diploma in Civil Engineering, a Certificate Course in Civil Draftsmanship from Tamil Nadu Government Polytechnic College, Madurai, and a B.Tech. in Civil Engineering.

Source reference: para. 4

The Department later cancelled his appointment on the ground that he did not possess the prescribed ITI Certificate in Civil Draftsmanship from a Government-recognised institute. The Single Judge set aside the cancellation and awarded 25% of the monetary benefits. The District Collector and Block Development Officer appealed.

Source reference: paras. 4–8
02

Issues

Whether the petitioner’s qualifications satisfied the prescribed requirement of an ITI Certificate in Civil Draftsmanship from a Government-recognised institute

Source reference: paras. 4–5, 9

Whether the Department’s cancellation of the petitioner’s appointment was sustainable after it had verified his certificates and appointed him

Source reference: paras. 7–10

Whether the petitioner was entitled to monetary benefits for the period he remained out of service

Source reference: para. 10
03

Law Applied

The Court considered the qualification prescribed for the Road Inspector post—an ITI Certificate in Civil Draftsmanship from a Government-recognised institute—although it did not identify the applicable Service Rule by name or citation.

Source reference: para. 4

It also applied the principle of “no work, no pay” in determining entitlement to monetary benefits for the period the petitioner was out of service.

Source reference: para. 10
04

Reasoning

The Court found that the petitioner’s Diploma in Civil Engineering, Civil Draftsmanship certificate, and B.Tech. in Civil Engineering were sufficient to meet the prescribed qualification.

Source reference: para. 9

It also noted that the Department had verified his certificates, accepted his qualifications, and appointed him before later cancelling the appointment; on these facts, the cancellation lacked merit.

Source reference: paras. 7, 10

However, because the petitioner had been out of employment, the Court applied “no work, no pay” and set aside the award of 25% monetary benefits.

Source reference: para. 10
05

Holding

The appeal was dismissed, and the Single Judge’s decision setting aside the cancellation of the petitioner’s appointment was confirmed.

The direction granting 25% of the monetary benefits was set aside; the respondents were directed to reinstate the petitioner within four weeks.

Source reference: para. 10(ii)

He was denied salary arrears for the period out of service, but that period was to count towards continuity of service and other service benefits as permitted by the applicable rules.

Source reference: para. 10(iii)–(iv)

No costs were awarded, and the connected miscellaneous petition was closed.

Source reference: para. 10
Madras High Court

Original Court PDF

THE DISTRICT COLLECTORvsB.LAKSHMANA MURALI

Madras High Court · September 25, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment