Himachal Pradesh High CourtAdministrative and Public LawProperty and Real Estate Law

HP High Court Quashes Land-Vesting Bid Against Resort Firm, Gives 18 Months To Finish Construction After Director's Death

M/S RIKHI RESORTS PVT LTDv.THE STATE OF HP AND OTHERS

HP High Court Quashes Land-Vesting Bid Against Resort Firm, Gives 18 Months To Finish Construction After Director's Death. M/S RIKHI RESORTS PVT LTD vs THE STATE OF HP AND OTHERS. Himachal Pradesh High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the petitioner's failure to complete the resort within two years, though it had undertaken road construction, hut construction and pillar foundation work, amounted to a failure attracting vesting under the second proviso to Section 118(2) of the Act.

The court held

The Court held that vesting under the second proviso to Section 118(2) is not automatic. Where a permission holder has taken meaningful steps toward the permitted use and the delay results from circumstances beyond its control, such as the death of the Managing Director, no conscious default is established and vesting cannot be ordered.

It also directed

The writ petition was allowed. The Financial Commissioner's order dated 2.4.2026 was quashed and set aside, and the petitioner was permitted to complete construction within one and a half years from the date of the order. If construction is not completed within that period, the land will vest in the State of Himachal Pradesh. Pending applications, if any, were disposed of.

01Facts

The State granted the petitioner permission under Section 118 of the H.P. Tenancy and Land Reforms Act, 1972 ("the Act") by letter dated 24.1.1994 to purchase land measuring 5-10 bighas at Village Sakori, Tehsil Kandaghat, District Solan, for construction of a hotel/resort.

¶ 2

The permission letter contained no time-bound condition for putting the land to use.

¶ 8

The District Collector initiated vesting proceedings in 2009, alleging failure to start construction and use the land within two years.

¶ 3

The Collector dropped the proceedings on 25.7.2014.

¶ 3

The Divisional Commissioner dismissed the State's appeal on 29.8.2017.

¶ 4

The Financial Commissioner (Appeals) allowed the State's revision on 2.4.2026, setting aside the concurrent findings.

¶ 4

The petitioner's case is that it built a 350–400 metre road, constructed labour huts, and laid pillar foundations within two years, and that work stalled only because its Managing Director died.

¶ 5, 10

The State contended that these works did not amount to commencement of construction and that the land was not put to use within two years.

¶ 6

02Issues

i.1. Whether the petitioner's failure to complete the resort within two years, though it had undertaken road construction, hut construction and pillar foundation work, amounted to a failure attracting vesting under the second proviso to Section 118(2) of the Act.

¶ 11

ii.2. Whether the failure, if any, was due to conscious default, negligence or refusal on the petitioner's part, as opposed to circumstances beyond its control.

¶ 5, 12, 13

iii.3. Whether the Financial Commissioner was justified in interfering with the concurrent findings of the Collector and Divisional Commissioner.

¶ 5, 14

03Law Applied

The Court applied the second proviso to Section 118(2) of the Act, which provides for vesting of land if the permission holder fails to put it to the permitted use within two years (extendable by one year).

¶ 6

The Court relied on Ravinder Chauhan v. State of H.P., AIR 1999 HP 43 (DB), which holds that vesting is not automatic, that it operates only as a condition precedent on the failure being due to conscious default, negligence or refusal, and that a natural-justice inquiry is required before vesting.

¶ 12

The Court followed M/s Barog Resorts Pvt. Ltd., CWP No. 5544 of 2020 (decided 22.8.2023), which applied Ravinder Chauhan.

¶ 12

The Court followed M/s Noble House Creation Pvt. Ltd., CWP No. 1182 of 2026 (decided 26.2.2026), which held that the phrase "put the land to use" is not to be read myopically and that the test is whether the permission holder took cogent and meaningful steps toward the permitted use.

¶ 14

The decision in Noble House Creation relied on M/s Springdale Resorts and Villas Pvt. Ltd., CWP No. 3363 of 2025 (decided 26.9.2025), as quoted therein.

¶ 14

Provisions in the judgment · 1

Himachal Pradesh Tenancy and Land Reforms Act, 1972 Section 118

04Reasoning

The Court first held that the permission letter imposed no time condition, and the statutory two-year period could not be enforced in the abstract without a finding of default by the petitioner.

¶ 8–9

The Court then found that the petitioner had taken concrete steps toward the permitted use within two years: a 350–400 metre access road, labour huts and pillar foundations.

¶ 10

The Court rejected the State's argument that the work had to be a completed resort within two years. It reasoned that resorts are built in phases, and that the road, huts and foundations were development activities towards the resort, not unrelated steps.

¶ 11

Applying Ravinder Chauhan and Noble House, the Court held that the stall in work was attributable to the death of the Managing Director, a circumstance beyond the petitioner's control, and that the State had not disputed this fact.

¶ 12–13

The Court therefore found no conscious default or negligence warranting vesting.

¶ 12–13

The Court also noted that the Financial Commissioner's interference with two concurrent findings was not sustainable on this record.

¶ 5, 14

Because the work was substantial and could be completed within about one and a half years, as the petitioner's counsel undertook, the Court allowed a limited extension rather than vesting.

¶ 15

05Holding

The Court held that vesting under the second proviso to Section 118(2) is not automatic. Where a permission holder has taken meaningful steps toward the permitted use and the delay results from circumstances beyond its control, such as the death of the Managing Director, no conscious default is established and vesting cannot be ordered.

¶ 12–13, 16

The writ petition was allowed. The Financial Commissioner's order dated 2.4.2026 was quashed and set aside, and the petitioner was permitted to complete construction within one and a half years from the date of the order. If construction is not completed within that period, the land will vest in the State of Himachal Pradesh. Pending applications, if any, were disposed of.

¶ 16
Himachal Pradesh High Court

Original Court PDF

M/S RIKHI RESORTS PVT LTDvsTHE STATE OF HP AND OTHERS

Himachal Pradesh High Court · November 16, 2026