01Facts
The State granted the petitioner permission under Section 118 of the H.P. Tenancy and Land Reforms Act, 1972 ("the Act") by letter dated 24.1.1994 to purchase land measuring 5-10 bighas at Village Sakori, Tehsil Kandaghat, District Solan, for construction of a hotel/resort.
¶ 2The permission letter contained no time-bound condition for putting the land to use.
¶ 8The District Collector initiated vesting proceedings in 2009, alleging failure to start construction and use the land within two years.
¶ 3The Collector dropped the proceedings on 25.7.2014.
¶ 3The Divisional Commissioner dismissed the State's appeal on 29.8.2017.
¶ 4The Financial Commissioner (Appeals) allowed the State's revision on 2.4.2026, setting aside the concurrent findings.
¶ 4The petitioner's case is that it built a 350–400 metre road, constructed labour huts, and laid pillar foundations within two years, and that work stalled only because its Managing Director died.
¶ 5, 10The State contended that these works did not amount to commencement of construction and that the land was not put to use within two years.
¶ 602Issues
i.1. Whether the petitioner's failure to complete the resort within two years, though it had undertaken road construction, hut construction and pillar foundation work, amounted to a failure attracting vesting under the second proviso to Section 118(2) of the Act.
¶ 11ii.2. Whether the failure, if any, was due to conscious default, negligence or refusal on the petitioner's part, as opposed to circumstances beyond its control.
¶ 5, 12, 13iii.3. Whether the Financial Commissioner was justified in interfering with the concurrent findings of the Collector and Divisional Commissioner.
¶ 5, 1403Law Applied
The Court applied the second proviso to Section 118(2) of the Act, which provides for vesting of land if the permission holder fails to put it to the permitted use within two years (extendable by one year).
¶ 6The Court relied on Ravinder Chauhan v. State of H.P., AIR 1999 HP 43 (DB), which holds that vesting is not automatic, that it operates only as a condition precedent on the failure being due to conscious default, negligence or refusal, and that a natural-justice inquiry is required before vesting.
¶ 12The Court followed M/s Barog Resorts Pvt. Ltd., CWP No. 5544 of 2020 (decided 22.8.2023), which applied Ravinder Chauhan.
¶ 12The Court followed M/s Noble House Creation Pvt. Ltd., CWP No. 1182 of 2026 (decided 26.2.2026), which held that the phrase "put the land to use" is not to be read myopically and that the test is whether the permission holder took cogent and meaningful steps toward the permitted use.
¶ 14The decision in Noble House Creation relied on M/s Springdale Resorts and Villas Pvt. Ltd., CWP No. 3363 of 2025 (decided 26.9.2025), as quoted therein.
¶ 14Provisions in the judgment · 1
Himachal Pradesh Tenancy and Land Reforms Act, 1972 Section 118
04Reasoning
The Court first held that the permission letter imposed no time condition, and the statutory two-year period could not be enforced in the abstract without a finding of default by the petitioner.
¶ 8–9The Court then found that the petitioner had taken concrete steps toward the permitted use within two years: a 350–400 metre access road, labour huts and pillar foundations.
¶ 10The Court rejected the State's argument that the work had to be a completed resort within two years. It reasoned that resorts are built in phases, and that the road, huts and foundations were development activities towards the resort, not unrelated steps.
¶ 11Applying Ravinder Chauhan and Noble House, the Court held that the stall in work was attributable to the death of the Managing Director, a circumstance beyond the petitioner's control, and that the State had not disputed this fact.
¶ 12–13The Court therefore found no conscious default or negligence warranting vesting.
¶ 12–13The Court also noted that the Financial Commissioner's interference with two concurrent findings was not sustainable on this record.
¶ 5, 14Because the work was substantial and could be completed within about one and a half years, as the petitioner's counsel undertook, the Court allowed a limited extension rather than vesting.
¶ 1505Holding
The Court held that vesting under the second proviso to Section 118(2) is not automatic. Where a permission holder has taken meaningful steps toward the permitted use and the delay results from circumstances beyond its control, such as the death of the Managing Director, no conscious default is established and vesting cannot be ordered.
¶ 12–13, 16The writ petition was allowed. The Financial Commissioner's order dated 2.4.2026 was quashed and set aside, and the petitioner was permitted to complete construction within one and a half years from the date of the order. If construction is not completed within that period, the land will vest in the State of Himachal Pradesh. Pending applications, if any, were disposed of.
¶ 16Original Court PDF
M/S RIKHI RESORTS PVT LTDvsTHE STATE OF HP AND OTHERS
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
