01Facts
The petitioner challenged ten orders placing its Importer Exporter Code on the Denied Entry List (DEL) for alleged non-fulfilment of export obligations under Advance and EPCG Authorisations.
¶ 1–2The petitioner’s CIRP commenced on 9 June 2023; nine of the ten impugned orders were issued on 5 September 2023, during the Section 14 moratorium.
¶ 3, 12The respondents filed a claim for approximately ₹15.66 crore in government dues arising from the same alleged defaults.
¶ 4, 13The NCLT approved the petitioner’s resolution plan on 2 August 2024, under which the respondents’ claim was admitted but settled at nil.
¶ 5, 14–15The petitioner’s subsequent representations seeking removal of the DEL status were not acted upon.
¶ 6The respondents raised objections to territorial jurisdiction, an alternative remedy and non-impleadment of DGFT Kanpur; the Court rejected those objections.
¶ 8–1102Issues
i.Whether the Court had territorial jurisdiction to entertain the petition despite the respondents’ objection that the matter arose in Kanpur.
¶ 9ii.Whether the impugned DEL orders and the continued DEL status could be sustained after approval of the resolution plan, where the underlying government dues were settled at nil.
¶ 12–18iii.Whether the respondents could undertake fresh verification or take action for any independent default after the petitioner’s removal from the DEL.
¶ 2003Law Applied
Section 14 of the Insolvency and Bankruptcy Code, 2016 (IBC) imposes a moratorium during CIRP; the Court held that coercive or adverse administrative orders passed against a corporate debtor in breach of that moratorium are void ab initio.
¶ 12Under Section 31(1) of the IBC, an approved resolution plan binds stakeholders, including government authorities.
¶ 16Applying the “clean slate” principle, the Court relied on Ghanshyam Mishra & Sons Private Limited v. Edelweiss Asset Reconstruction Company Limited, (2021) 9 SCC 657, for the rule that claims not forming part of an approved resolution plan stand extinguished and cannot be pursued thereafter.
¶ 18The Court also recognised that extinguishment of monetary claims does not bar fresh verification or action based on an independent, subsequent cause of action.
¶ 20Provisions in the judgment · 2 · Linked ones open on LawLens
Insolvency and Bankruptcy Code, 2016. Section 14Section 31
04Reasoning
The Court found that nine impugned orders were issued during the Section 14 moratorium and were therefore void ab initio.
¶ 12Independently, the government dues underlying the DEL status had been submitted as a claim in the CIRP and recorded in the approved resolution plan as payable at nil.
¶ 13–15Because the respondents had not challenged the NCLT’s approval order, continuing the DEL status to enforce those pre-CIRP defaults would undermine the binding effect of the plan and the IBC’s clean-slate principle.
¶ 16–18The Court rejected the preliminary objections, including territorial jurisdiction, noting that DGFT Headquarters in Delhi was seized of the matter and that the respondents’ counter-affidavit was filed through an officer of DGFT Kanpur.
¶ 9–1105Holding
The Court set aside the impugned DEL orders and directed that the petitioner be removed from the DEL.
¶ 19It clarified that the respondents may conduct fresh verification under applicable law and may take appropriate action if they identify an independent default or non-fulfilment of export obligations.
¶ 20The petition and pending application(s) were disposed of.
¶ 21Original Court PDF
Waaree Transpower Private LimitedvsUnion Of India & Anr.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
