Bombay High Court

Ineligibility of Third Parties Without Privity to Obtain Relief or Intervene in Section 9 Arbitration Proceedings

Mulund Raviraj Co-Operative Housing Society Ltd. vs Rupji Constructions And Anr And Vinita Vilas Sawant (Applicants)

Bombay High CourtJUDGMENT: April 29, 20263 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Petitioner (Society) entered into a Development Agreement (DA) dated May 2, 2013, with the Respondent (Developer) for property redevelopment

Source reference: para. 2-3

Following defaults by the Developer in paying corpus amounts, transit rent, and statutory dues, the Society filed a Section 9 Petition in 2017

Source reference: para. 4

In December 2017, the High Court issued an injunction restraining the Developer and its partners from alienating any assets across all their projects and directed the attachment of various personal assets

Source reference: para. 5, 32

Over the years, 31 Interim Applications (IAs) were filed, including many by third-party decree-holders and allottees from unrelated projects of the Developer seeking to claim funds deposited in Court

Source reference: para. 1, 11-14

An Arbitral Tribunal was finally constituted on September 2, 2024, which subsequently passed an order under Section 17 of the Act on February 4, 2026

Source reference: para. 5, 7
02

Issues

1. Whether a Section 9 Court should continue to entertain interim measures and third-party applications once an Arbitral Tribunal has been constituted and an application under Section 17 is being pursued.

Source reference: para. 19, 22

2. Whether third-party decree-holders and allottees of unrelated projects, who are not signatories to the arbitration agreement, can intervene in Section 9 proceedings to claim attached assets.

Source reference: para. 27-29
03

Law Applied

The court primarily applied Section 9 and Section 17 of the Arbitration and Conciliation Act, 1996.

Source reference: para. 1, 19

The court relied on the definition of "party" under Section 2(1)(h) as a party to an arbitration agreement.

Source reference: para. 20

Regarding non-signatories, it applied the "veritable parties" doctrine as established in Cox and Kings Ltd. v. SAP India (P) Ltd. [2024], ASF Buildtech v. Shapoorji Pallonji [2025], and Adavya Projects v. Vishal Structurals [2025], requiring demonstrable proximity, consent, or a de facto connection to the dispute to bind non-signatories.

Source reference: para. 27-28
04

Reasoning

The Court reasoned that Section 9 is not a standalone equity jurisdiction but is limited to protecting the specific subject matter of the arbitration agreement.

Source reference: para. 21

Since an Arbitral Tribunal is now seized of the matter, Section 9(3) mandates that the Court shall not entertain such applications unless Section 17 is inefficacious.

Source reference: para. 19, 22

The Court found that the third-party applicants (decree-holders from other projects, family members, etc.) lacked privity of contract and did not qualify as "veritable parties" because their disputes were distinct from the Society’s DA.

Source reference: para. 29, 49

The Court noted that continuing the Section 9 proceedings for execution of third-party decrees would be coram non judice.

Source reference: para. 46

Consequently, the Court determined that the Learned Arbitral Tribunal is the appropriate forum to assess what portion of the deposited funds is necessary to secure the Society's claims (quantified at Rs. 18.65 Crores) and what can be released.

Source reference: para. 37-38
05

Holding

The Court disposed of the Section 9 Petition and all 31 Interim Applications.

The Court held that all third-party interventions by non-signatories are rejected as they have no nexus to the arbitration agreement.

Source reference: para. 51-54

The Arbitral Tribunal is directed to assess, within three months, the amount required to protect the Society’s interests; any surplus funds deposited in Court shall then be released to the Developer.

Source reference: para. 70(C)-(D)

The restraint order of December 2017 remains subject to the Tribunal's modification; the Court Commissioner is to hand over charge to an official Commissioner, and the Society is granted liberty to pursue its dues through the Section 17 proceedings.

Source reference: para. 58, 68-70/para. 70(E)
Bombay High Court

Original Court PDF

Mulund Raviraj Co-Operative Housing Society Ltd.vsRupji Constructions And Anr And Vinita Vilas Sawant (Applicants)

Bombay High Court · April 29, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment