Delhi High Court

Inordinate delay and administrative lethargy in commercial matters do not constitute valid grounds for condonation of delay.

Bharat Sanchar Nigam Limited vs Royal India Technoprojects Limited

Delhi High CourtJUDGMENT: May 07, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The appellant (BSNL) challenged an arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996. On 5 September 2023, the appellant’s counsel withdrew said petition with liberty to take appropriate legal recourse

Source reference: p. 1-2

575 days later, the appellant filed a restoration application (Misc DJ 246/2025), claiming their previous counsel had wrongly advised them to re-file in another forum

Source reference: p. 2

The Commercial Court dismissed the restoration application on 27 November 2025, citing an inordinate delay and lack of sufficient cause

Source reference: p. 2-3

The appellant then preferred this appeal challenging both the withdrawal order of 2023 and the dismissal of the restoration application in 2025, accompanied by an application to condone an 809-day delay in filing the appeal

Source reference: p. 3-4
02

Issues

1. Whether a restoration application is maintainable against an order dismissing a Section 34 petition as withdrawn

Source reference: p. 2, para. 4

2. Whether administrative lethargy and purported wrong legal advice constitute sufficient grounds to condone a 575-day delay in filing a restoration application or an 809-day delay in filing an appeal in commercial matters

Source reference: p. 2-3, para. 6 & 13
03

Law Applied

The court applied Section 37 of the Arbitration and Conciliation Act, 1996, noting that orders disposing of Section 34 petitions are only appealable, not subject to restoration applications

Source reference: p. 2

Regarding limitation, the court relied on Jharkhand Urja Utpadan Nigam Limited v. Bharat Heavy Electricals Limited [2025 SCC OnLine SC 910] and Government of Maharashtra v. Borse Brothers Engineers & Contractors Pvt Ltd [(2021) 6 SCC 460], which establish that in commercial matters, delay must be viewed strictly and explained with cogent material, rather than the latitude allowed in ordinary suits

Source reference: p. 5, para. 13
04

Reasoning

The High Court found the appellant's restoration application legally untenable because an order disposing of a Section 34 petition can only be challenged via appeal under Section 37

Source reference: para. 4

the court determined that the appellant failed to provide a "tenable explanation" for the 575-day delay in seeking restoration and the subsequent 809-day delay in filing the present appeal

Source reference: para. 10, 12

The court rejected the plea of "administrative lethargy" and the vague allegation of incorrect legal advice, noting that the appellant never actually followed the purported advice to file in another forum

Source reference: para. 5-6

Applying the strict standards of the Commercial Courts Act as interpreted by the Supreme Court, the Bench held that the "laxity" displayed by the appellant was fatal to the case

Source reference: para. 13-14
05

Holding

The Court dismissed the appeal in limine. It held that the challenge to the 2023 withdrawal order was "hopelessly barred by time" (809 days) and that the 2025 order dismissing the restoration application was correct, as the application was both non-maintainable and lacked sufficient cause for the 575-day delay

No notice was issued as no sustainable grounds for challenge existed

Source reference: p. 4
Delhi High Court

Original Court PDF

Bharat Sanchar Nigam LimitedvsRoyal India Technoprojects Limited

Delhi High Court · May 07, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment