Odisha High Court
Civil Procedure and EvidenceAdministrative and Public Law

Inter-departmental file movement does not constitute sufficient cause for condoning governmental delay.

STATE OF ODISHA vs RANGADHAR PAIKARAY

Odisha High CourtJUDGMENT: September 03, 20263 MIN READSOURCE JUDGMENT
Inter-departmental file movement does not constitute sufficient cause for condoning governmental delay.. STATE OF ODISHA vs RANGADHAR PAIKARAY. Odisha High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The appellants—State of Odisha and its higher-education authorities—filed an application seeking condonation of a 325-day delay in presenting an intra-court writ appeal against the judgment dated 23 August 2024 in W.P.(C) No.18641 of 2009.

Source reference: p.3, paras.3–4

The State claimed that the judgment was received on 23 August 2024; a decision to appeal was allegedly taken on 25 August 2024, followed by movement of the file through the Administrative Department, Legal Section, Law Department and the Office of the Advocate General.

Source reference: pp.3–4, paras.5–6

The Law Department approved the proposal on 14 May 2025, the records reached the Advocate General’s office on 17 June 2025, and the appeal memo was prepared and finalised by 25 June 2025.

Source reference: pp.3–4, paras.5–6

Respondent No.1 opposed the application, contending that the explanation merely described inter-departmental movement of files and amounted to bureaucratic indifference rather than sufficient cause.

Source reference: pp.7–8, paras.10–12
02

Issues

Whether the appellants had shown sufficient cause for condonation of the 325-day delay in filing the intra-court writ appeal?

Source reference: p.3, para.3; pp.16–17, paras.23–24

Whether inter-departmental processing and movement of files, without a specific and satisfactory explanation for the delay, entitled the State to a more liberal treatment than a private litigant?

Source reference: pp.12–13, para.15; pp.16–17, paras.23–24

Whether the writ appeal should consequently be dismissed as barred by delay and laches, with the interim orders vacated?

Source reference: p.17, paras.24–25
03

Law Applied

The Court applied the principles governing condonation of delay under the applicable procedural framework, including Article 4 of the Odisha High Court Order, 1948, Clause 10 of the Letters Patent and the relevant High Court Rules.

Source reference: p.1

The controlling principle is that the length of delay is not decisive; the applicant must establish “sufficient cause” through a bona fide, diligent and judicially acceptable explanation.

Source reference: pp.4–5, paras.7–8

The Court considered Collector, Land Acquisition, Anantnag v. Mst. Katiji, which supports a liberal approach where sufficient cause exists, and G. Ramegowda v. Special Land Acquisition Officer, which recognises that governmental decision-making may involve procedural delay.

Source reference: pp.4–5, paras.7–8

However, it relied on Postmaster General v. Living Media India Ltd., Commissioner of Wealth Tax v. Amateur Riders Club, Delhi Development Authority v. Tejpal, Sheo Raj Singh v. Union of India, and State of Odisha v. Managing Committee of Namatara Girls High School for the qualification that bureaucratic file movement or general administrative indifference is not, by itself, sufficient cause; the State is not entitled to automatic or unlimited latitude and must demonstrate a credible explanation, bona fides and due diligence.

Source reference: pp.5–6, 8–15, paras.8, 11, 13–18

The Court also adopted the distinction between an “explanation,” which clarifies the circumstances and lack of fault, and an “excuse,” which merely seeks to avoid responsibility.

Source reference: p.6, para.8
04

Reasoning

The Court found that the appellants’ explanation consisted essentially of dates showing movement of the file between the Director’s office, the Administrative Department, the Legal Section, the Law Department and the Advocate General’s office.

Source reference: pp.3–4, para.6

Although governmental decisions may legitimately require institutional consultation, the appellants did not explain why the decision to file the appeal, preparation of the papers and presentation of the appeal could not be completed within the prescribed period.

Source reference: no citation

The Court held that the explanation was substantially the same as the stereotyped explanations rejected in the authorities cited, and that the State’s status as a governmental entity could not displace the requirement of equality before law or justify a separate limitation standard.

Source reference: pp.9–12, paras.12–15

In the Court’s view, the delay resulted from a lackadaisical and leisurely approach, and the asserted inter- and intra-departmental communications were “mere excuses,” not a sufficient cause supported by bona fide diligence.

Source reference: p.16, para.23
05

Holding

The Court held that the appellants failed to establish sufficient cause for the 325-day delay.

I.A. No.3601 of 2025 was therefore dismissed, and W.A. No.1450 of 2025 was consequentially dismissed on the ground of delay and laches.

Source reference: p.17, para.24

All interim orders, including the order dated 7 July 2026, were vacated.

Source reference: p.17, para.25

The State authorities were directed to comply with the Single Judge’s judgment dated 23 August 2024 in W.P.(C) No.18641 of 2009, in letter and spirit, preferably within two months.

Source reference: p.17, para.26
06

Acts & Sections Cited

2 provisions across 2 statutes referred to in this judgment. Linked provisions open on LawLens.

Rules of Procedure and Conduct of Business in Lok Sabha1

Section 5

Land Acquisition Act, 18941

Section 18
Odisha High Court

Original Court PDF

STATE OF ODISHAvsRANGADHAR PAIKARAY

Odisha High Court · September 03, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment