Facts
The Appellant, Tata Steel, a licensee and electricity procurer from Damodar Valley Corporation (DVC), challenged an order dated 24.07.2019 passed by the Jharkhand State Electricity Regulatory Commission (JSERC).
Source reference: p. 2In 2002, DVC raised bills for Additional Minimum Guarantee (AMG) charges totaling ₹37.57 Crore.
Source reference: p. 4Tata Steel requested payment in installments, which DVC allowed but refused to waive the Delayed Payment Surcharge (DPS).
Source reference: p. 4DVC subsequently adjusted ₹77.60 lacs as DPS against Tata Steel’s monthly advance payments.
Source reference: p. 5The State Commission later ruled that DVC was not entitled to DPS on these AMG installments and ordered a refund with 6% annual interest.
Source reference: p. 8Tata Steel appealed, seeking a higher interest rate on the refund.
Source reference: p. 7Issues
1. Whether the rate of interest (6% per annum) allowed by the State Commission on the refund of DPS realized on AMG bills was adequate and compensatory.
Source reference: p. 4 / para 5Law Applied
Section 62(6) of the Electricity Act, 2003, which mandates that if a licensee recovers charges exceeding the determined tariff, the excess is recoverable with interest equivalent to the "bank rate".
Source reference: p. 10JSERC (Electricity Supply Code) Regulations, 2015, specifically Clause 10.7.4 (disputed bills) and Clause 10.6.3 (advance deposits).
Source reference: p. 8-9The principle of restitution and fairness as discussed in Rajnesh Sharma v. Business Park (2025 SCC OnLine SC 2061).
Source reference: p. 9-10Reasoning
The Tribunal rejected DVC’s new argument that no DPS was ever actually realized, noting that DVC had admitted to the State Commission that it adjusted the surcharge against the Appellant's advance payments.
Source reference: p. 6-7Regarding the interest rate, the Tribunal found that Clause 10.7.4 of the JSERC Supply Code did not apply because the refund did not arise from a formal "disputed bill" complaint process.
Source reference: p. 8Similarly, Clause 10.6.3 was inapplicable as the amount was not a voluntary advance deposit but an unauthorized recovery.
Source reference: p. 9Consequently, the Tribunal determined that the State Commission’s 6% interest rate lacked a regulatory basis.
Source reference: p. 9By invoking the spirit of Section 62(6) of the Electricity Act, the Tribunal reasoned that any recovery exceeding the authorized tariff/charge must be compensated at a rate equivalent to the bank rate to ensure justice and restitution.
Source reference: p. 10Holding
The Tribunal held that the 6% interest rate was inadequate and set aside the Impugned Order on this specific issue.
The Tribunal directed DVC to pay interest equivalent to the SBI Prime Lending Rate (applicable from time to time) instead of 6% on the DPS amount realized from the date of recovery until the date of refund or adjustment.
Source reference: p. 11All pending applications were disposed of accordingly.
Source reference: p. 11Original Court PDF
M/s TATA STEEL LTDvsThe Secretary, Jharkhand State Electricity Regulatory Commission Ors
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in