01Facts
The Petitioner, a construction company, was awarded two EPC contracts by Respondent No. 1 (NHIDCL) for road works on NH-37 in January 2024.
¶ 3-4Pursuant to the agreements, the Petitioner furnished two Performance Bank Guarantees (PBGs) and one Mobilization Bank Guarantee (MBG) totaling approximately ₹8.63 Crores.
¶ 5Following delays in project completion—which the Petitioner attributed to authority defaults and force majeure—NHIDCL issued a letter on 14.01.2026 seeking to encash the BGs to recover "undisputed vendor dues" and "funds released on assurances not honoured".
¶ 7, 9, 15Subsequently, a Termination Notice was issued on 15.01.2026.
¶ 9The Petitioner filed this Section 9 petition seeking to restrain the bank guarantee invocation and the termination of the contracts.
¶ 102Issues
i.1. Whether the Court can grant an injunction against the termination of a contract that is by its nature determinable.
¶ 35ii.2. Whether the invocation of Performance and Mobilization Bank Guarantees can be stayed when the grounds for invocation fall outside the specific contractual default clauses.
¶ 41, 4803Law Applied
The court applied Section 9 of the Arbitration and Conciliation Act, 1996, which empowers courts to grant interim measures to preserve the subject matter of the dispute.
¶ 30-32It relied on *Indian Oil Corporation v. Amritsar Gas Service & Ors.*, establishing that under Section 14(1) of the Specific Relief Act, a determinable contract cannot be specifically enforced or its termination stayed.
¶ 36Regarding bank guarantees, the court followed *Hindustan Construction Co. Ltd v. State of Bihar*, holding that invocation must be in strict accordance with the terms of the guarantee.
¶ 53It distinguished between unconditional and Conditional Bank Guarantees (CBG), noting that CBGs require the fulfillment of predefined contingencies before invocation.
¶ 51-52Finally, it cited *M/S Jindal Steel & Power Ltd v. M/S Bansal Infra Projects Pvt. Ltd* to justify intervention where invocation would render arbitral proceedings infructuous.
¶ 53Provisions in the judgment · 2 · Linked ones open on LawLens
Specific Relief Act, 1963 Section 14
Arbitration and Conciliation Act, 1996 Section 9
04Reasoning
The Court first determined that the EPC contract was determinable, meaning no injunction could be granted against the Termination Notice.
¶ 35-37However, regarding the BGs, the Court found they were "Conditional Bank Guarantees" tied specifically to "due and faithful performance" of contractual obligations.
¶ 43-44, 51The Court observed that Respondent No. 1 sought encashment for "extra-contractual" reasons—specifically the recovery of funds released on informal assurances and the settlement of third-party vendor disputes—which did not constitute "Contractor Default" as defined in Clause 23.1 of the Agreement.
¶ 18, 44-46The Court noted that liquidated damages under Clause 10.3 were to be recovered via deductions from payments, not through BG invocation.
¶ 48Since the grounds for withdrawal were not traceable to the contractual "representation or warranty" clauses, the Court found a prima facie case of illegal invocation.
¶ 44-45, 5405Holding
The Court partially allowed the petition. It refused to stay the Termination Notice, holding that determinable contracts cannot be stayed.
¶ 58However, it granted a stay on the encashment of the three Bank Guarantees (PBGs and MBG), pending adjudication by the Arbitral Tribunal.
¶ 57, 61The Court held that the balance of convenience favoured the Petitioner as the invocation appeared to circumvent contractual terms, and encashment would cause irreparable prejudice before the merits could be arbitrated.
¶ 54-56Original Court PDF
Sadguru Engineers and Allied Services Pvt. Ltd. v. National Highways Infrastructure Development Corporation Ltd. & Ors., O.M.P.(I) (COMM.) 18/2026
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
