Delhi High Court

### Interim Protection Against Termination Triggered by Section 9 Notice Where Default Procedures Are Bypassed

Mr. Pradeep Dass vs Splendor Landbase Limited & Ors.

Delhi High CourtJUDGMENT: May 06, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Petitioner entered into an Agreement for Sale (dated 26.03.2019) and subsequent Supplemental Agreements with the Respondents regarding commercial units in Gurugram

Source reference: p. 2-3

On 27.04.2026, the Petitioner served a Section 9 notice under the Arbitration and Conciliation Act, 1996, upon the Respondents seeking to protect his rights

Source reference: para. 2

On 28.04.2026, the Respondents issued a letter terminating the allotment, citing "force majeure" and commercial frustration

Source reference: para. 2, 12, 21

On 30.04.2026, the Respondents purportedly allotted the same units to a third party (M/s Amrit Skyline Builders) for nominal token amounts

Source reference: para. 9-10, 18

The Petitioner moved the High Court seeking interim stay on the termination and a restraint on the creation of third-party rights

Source reference: p. 2
02

Issues

1. Whether the court can grant interim protection under Section 9 of the Act to stay a termination letter and preserve the status quo of immovable property

Source reference: para. 16-17

2. Whether the Respondents’ invocation of "force majeure" for events dating back to 2020 justifies termination in 2026 after subsequent affirming conduct

Source reference: para. 21-22

3. Whether the purported third-party allotments were bona fide commercial transactions or sham proceedings intended to frustrate the Petitioner's rights

Source reference: para. 10, 18, 24
03

Law Applied

The court primarily applied Section 9 of the Arbitration and Conciliation Act, 1996, regarding interim measures

Source reference: p. 1-2

It relied on Rahul Bhargava v. Neo Developers (P) Ltd., establishing that in real estate disputes, preservation of property is central to ensuring final adjudication remains effective

Source reference: para. 7

The court noted the 2018 amendment to Section 10 of the Specific Relief Act, 1963, which emphasizes the enforcement of contractual rights in immovable property

Source reference: para. 6, 8

Regarding the non-enforceability of terminated contracts, the court distinguished JLT Energy SAS v. Hindustan Cleanenergy Ltd. and Bharat Catering Corpn. v. IRCTC, holding that there is no "straitjacket" rule barring protective relief if the termination appears prima facie retaliatory or contrary to agreed contractual procedures

Source reference: para. 11-16
04

Reasoning

The court found the timing of the termination (one day after the Section 9 notice) to be prima facie retaliatory and intended to defeat the Petitioner’s rights

Source reference: para. 17

It observed that the Respondents failed to comply with the mandatory notice and 90-day cure period stipulated under Clauses 7.10.1 and 7.10.2 of the Agreement

Source reference: para. 19-20

The "force majeure" plea was rejected at the prima facie stage because the Respondents had executed Supplemental Agreements and transfer certificates as recently as 2024 and 2025, long after the COVID-19 events cited

Source reference: para. 21-22

Furthermore, the court viewed the third-party allotments with suspicion, noting that units worth crores were purportedly transferred for only nominal token amounts immediately following the termination

Source reference: para. 10, 18, 24

Consequently, the court determined that the balance of convenience favored the Petitioner to prevent irreparable prejudice

Source reference: para. 23
05

Holding

The court stayed the impugned termination letter and directed that consequential third-party allotments shall not be given effect

The court appointed Hon’ble Mr. Justice Rajesh Bindal (Retd.) as the Sole Arbitrator to resolve the disputes

Source reference: para. 31

The Section 9 petition was ordered to be treated as an application under Section 17 before the learned Arbitrator. The petition was disposed of with all rights and contentions left open for the merits of the arbitration

Source reference: para. 36, 35-39
Delhi High Court

Original Court PDF

Mr. Pradeep DassvsSplendor Landbase Limited & Ors.

Delhi High Court · May 06, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment