Facts
The Appellant was awarded a contract by Respondent No. 1 (GAIL) for terminal station works via a Letter of Acceptance dated 28.05.2018
Source reference: p. 2The Appellant claimed works were completed on 30.11.2022 following various delays
Source reference: p. 3The Appellant submitted a final bill, which it alleged was certified by the Project Management Consultant for a net release of approx. Rs. 2.08 Crores
Source reference: p. 3-4Claiming GAIL withheld payment and attempted unlawful cross-recoveries from other contracts, the Appellant filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996
Source reference: p. 4The learned Single Judge dismissed the petition on 23.04.2026, holding that Section 9 cannot be a substitute for the recovery of money
Source reference: p. 4Execution of the contract involved disputes over performance, delays, and financial liabilities
Source reference: p. 6Issues
1. Whether relief under Section 9 of the Arbitration and Conciliation Act, 1996, seeking payment of alleged admitted contractual dues, can be granted when the relief amounts to enforcement of a monetary claim.
Source reference: p. 1-2 / para. 22. Whether the Appellant demonstrated exceptional circumstances or a real likelihood of frustration of arbitral proceedings to warrant interim protection.
Source reference: p. 9-10 / para. 21, 30Law Applied
Section 9 of the Arbitration and Conciliation Act, 1996, which empowers courts to grant interim measures of protection to preserve the efficacy of arbitral proceedings or the subject matter of the dispute
Source reference: p. 8-9Section 9(1)(ii)(b) regarding "securing the amount in dispute," noting it is a protective and interim jurisdiction, not intended for final adjudication or enforcement of money claims
Source reference: p. 9Principles governing discretionary jurisdiction and the limited scope of appellate interference under Section 37 of the Act
Source reference: p. 13-14Reasoning
The court reasoned that Section 9 is intended to aid arbitration by preserving the status quo, not to bypass the adjudicatory mechanism by granting final relief at an interlocutory stage
Source reference: p. 9, 11It found that the Appellant’s claims regarding "admitted liability"—based on bill certification, TDS deduction, and completion certificates—did not constitute conclusive determination of liability and remained matters for arbitral adjudication
Source reference: p. 11The court observed that the Appellant's own pleadings regarding "wrongful withholding" and "arbitrary deductions" proved the existence of a live dispute
Source reference: p. 11Crucially, the court found no evidence of imminent dissipation of assets by GAIL (a Public Sector Undertaking) or any risk that an eventual award would be unenforceable
Source reference: p. 12The court held that the petition was a suit for money recovery "couched" as an interim measures application
Source reference: p. 11-12Holding
The court answered the primary issue in the negative, holding that Section 9 cannot be used as a substitute for final monetary recovery in the absence of a threat to the arbitral process
The court upheld the Single Judge's order and dismissed the appeal, clarifying that the Appellant remains free to invoke arbitration to resolve the merits of the dispute
Source reference: p. 14-15The court held that there was no jurisdictional error or perversity in refusing to grant a mandatory direction for payment at the pre-arbitral stage
Source reference: p. 14Original Court PDF
M/S Slr Construction Pvt LtdvsGail India Ltd And Anr
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in