Delhi High CourtArbitration and MediationContract Law

Interim Relief Under Section 9 Cannot Be Invoked for Recovery of Admitted Contractual Dues Absent Exceptional Circumstances.

M/S Slr Construction Pvt Ltdv.Gail India Ltd And Anr

Interim Relief Under Section 9 Cannot Be Invoked for Recovery of Admitted Contractual Dues Absent Exceptional Circumstances.. M/S Slr Construction Pvt Ltd vs Gail India Ltd And Anr. Delhi High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether relief under Section 9 of the Arbitration and Conciliation Act, 1996, seeking payment of alleged admitted contractual dues, can be granted when the relief amounts to enforcement of a monetary claim.

The court held

The court answered the primary issue in the negative, holding that Section 9 cannot be used as a substitute for final monetary recovery in the absence of a threat to the arbitral process

It also directed

The court upheld the Single Judge's order and dismissed the appeal, clarifying that the Appellant remains free to invoke arbitration to resolve the merits of the dispute

The court held that there was no jurisdictional error or perversity in refusing to grant a mandatory direction for payment at the pre-arbitral stage

01Facts

The Appellant was awarded a contract by Respondent No. 1 (GAIL) for terminal station works via a Letter of Acceptance dated 28.05.2018

p. 2

The Appellant claimed works were completed on 30.11.2022 following various delays

p. 3

The Appellant submitted a final bill, which it alleged was certified by the Project Management Consultant for a net release of approx. Rs. 2.08 Crores

pp. 3-4

Claiming GAIL withheld payment and attempted unlawful cross-recoveries from other contracts, the Appellant filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996

p. 4

The learned Single Judge dismissed the petition on 23.04.2026, holding that Section 9 cannot be a substitute for the recovery of money

p. 4

Execution of the contract involved disputes over performance, delays, and financial liabilities

p. 6

02Issues

i.1. Whether relief under Section 9 of the Arbitration and Conciliation Act, 1996, seeking payment of alleged admitted contractual dues, can be granted when the relief amounts to enforcement of a monetary claim.

pp. 1-2 / para. 2

ii.2. Whether the Appellant demonstrated exceptional circumstances or a real likelihood of frustration of arbitral proceedings to warrant interim protection.

pp. 9-10 / para. 21, 30

03Law Applied

Section 9 of the Arbitration and Conciliation Act, 1996, which empowers courts to grant interim measures of protection to preserve the efficacy of arbitral proceedings or the subject matter of the dispute

pp. 8-9

Section 9(1)(ii)(b) regarding "securing the amount in dispute," noting it is a protective and interim jurisdiction, not intended for final adjudication or enforcement of money claims

p. 9

Principles governing discretionary jurisdiction and the limited scope of appellate interference under Section 37 of the Act

pp. 13-14

Provisions in the judgment · 4 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 9Section 17Section 36Section 37

04Reasoning

The court reasoned that Section 9 is intended to aid arbitration by preserving the status quo, not to bypass the adjudicatory mechanism by granting final relief at an interlocutory stage

p. 9, 11

It found that the Appellant’s claims regarding "admitted liability"—based on bill certification, TDS deduction, and completion certificates—did not constitute conclusive determination of liability and remained matters for arbitral adjudication

p. 11

The court observed that the Appellant's own pleadings regarding "wrongful withholding" and "arbitrary deductions" proved the existence of a live dispute

p. 11

Crucially, the court found no evidence of imminent dissipation of assets by GAIL (a Public Sector Undertaking) or any risk that an eventual award would be unenforceable

p. 12

The court held that the petition was a suit for money recovery "couched" as an interim measures application

pp. 11-12

05Holding

The court answered the primary issue in the negative, holding that Section 9 cannot be used as a substitute for final monetary recovery in the absence of a threat to the arbitral process

p. 12, 14

The court upheld the Single Judge's order and dismissed the appeal, clarifying that the Appellant remains free to invoke arbitration to resolve the merits of the dispute

pp. 14-15

The court held that there was no jurisdictional error or perversity in refusing to grant a mandatory direction for payment at the pre-arbitral stage

p. 14
Delhi High Court

Original Court PDF

M/S Slr Construction Pvt LtdvsGail India Ltd And Anr

Delhi High Court · July 01, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment