Chhattisgarh High Court

Internal experience certificates between company units are invalid as "employer" denotes an independent, external entity.

M/S RKTC-PHIL (JV) vs COAL INDIA LIMITED

Chhattisgarh High CourtJUDGMENT: March 27, 20263 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Respondent, South Eastern Coalfields Limited (SECL), issued a Notice Inviting Tender (NIT) for the construction and maintenance of a Coal Handling Plant on a turnkey basis.

Source reference: para 3

Clause 8.4(A) of the NIT required bidders to possess experience in "similar nature of work" supported by work orders and completion certificates issued by the "employer".

Source reference: para 3, 5

The Petitioner’s technical bid was disqualified because the experience certificates submitted pertained to work assigned internally by one wing of the Petitioner's company to another.

Source reference: para 6

The Petitioner challenged this disqualification, arguing that the NIT did not expressly prohibit internal work orders and that the rejection was hyper-technical and arbitrary.

Source reference: para 5-7

The Respondents contended that an "employer" must be an independent external entity and that a company cannot legally contract with itself.

Source reference: para 9
02

Issues

Whether experience certificates issued internally between different units or departments of the same company satisfy the eligibility criteria requiring certification by an "employer" under the NIT.

Source reference: para 11

Whether the decision of the Tender Evaluation Committee to disqualify the Petitioner was arbitrary or irrational, warranting judicial interference under Article 226 of the Constitution.

Source reference: para 17-18
03

Law Applied

The Court applied the principle of limited judicial review in contractual matters, emphasizing that the Government and its instrumentalities possess the freedom of contract unless the decision-making process is biased, mala fide, or arbitrary.

Source reference: para 19

It relied on Tata Cellular v. Union of India, which established that courts should exercise judicial restraint and not substitute their own expertise for that of the administrative body.

Source reference: para 19, 24

The court further applied the dual test from Jagdish Mandal v. State of Orissa: whether the process is mala fide/intended to favor someone, or so arbitrary that no responsible authority could have reached such a decision, and whether public interest is affected.

Source reference: para 19, 26

Finally, it cited M/S. Steag Energy Services (India) Pvt. Ltd. v. GSPC Pipavav Power Company Ltd., affirming that the final choice and flexibility in tender evaluation rest with the owner/employer.

Source reference: para 20
04

Reasoning

The Court reasoned that while the NIT did not explicitly define "employer," the term inherently denotes an independent, external entity distinct from the bidder, presupposing an arm’s-length contractual relationship.

Source reference: para 12-13

Legally, a company is a single entity and cannot enter into a contract with its own departments; therefore, no valid employer-contractor relationship exists in internal arrangements.

Source reference: para 14

The Court observed that accepting internal certifications would undermine the transparency and sanctity of the bidding process, as such documents lack independent verification and are susceptible to manipulation.

Source reference: para 15-16

Furthermore, the Petitioner’s reliance on a certificate from a Chartered Engineer engaged by itself was deemed equivalent to "self-certification," which does not meet the standard of a completion certificate issued by an independent project authority.

Source reference: para 16

The Court concluded that the Evaluation Committee’s interpretation was plausible and reasonable, aimed at maintaining a level playing field.

Source reference: para 17
05

Holding

The High Court answered the issues in the negative, holding that internal work experience does not satisfy the NIT’s requirement for certification by an "employer".

The Court found no arbitrariness or violation of Article 14 in the Respondents' decision-making process.

Source reference: para 18

Consequently, the Court declined to interfere with the technical disqualification, ruling that the decision fell within the permissible bounds of administrative discretion.

Source reference: para 19-20

The writ petition was dismissed, and no relief was granted to the Petitioner.

Source reference: para 21
Chhattisgarh High Court

Original Court PDF

M/S RKTC-PHIL (JV)vsCOAL INDIA LIMITED

Chhattisgarh High Court · March 27, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment