Facts
The Petitioner (SAIL) and a Consortium involving the Respondent (NCC Ltd.) entered into a Contract dated 16.10.2007 for a Blast Furnace Complex project
Source reference: p.2The Contract stipulated a Minimum Guaranteed Tax Credit (MGC) of ₹103.85 crores, later apportioned specifically to NCC and POSCO
Source reference: p.2-3During execution, the indirect tax regime changed, leading to a reduction in actual tax credits generated
Source reference: p.3Believing the MGC was an absolute obligation, SAIL withheld ₹16,91,03,984/- from payments due to NCC to cover the alleged shortfall
Source reference: p.3-4NCC invoked ICC arbitration in 2021
Source reference: p.4The Sole Arbitrator, Mr. Andrew G. Moran KC, rendered an Award on 08.01.2024, holding that the MGC was not an absolute obligation independent of tax variations and directed SAIL to refund the withheld amount with interest
Source reference: p.5SAIL challenged the Award under Section 34 of the Arbitration and Conciliation Act, 1996
Source reference: p.2Issues
1. Whether the scope of judicial interference under Section 34 of the Act is restricted in cases of International Commercial Arbitration (ICA) following the 2015 Amendment
Source reference: p.12-162. Whether the Arbitral Tribunal’s interpretation—that the MGC was dependent on actual tax incidence and statutory changes—constituted a plausible contractual construction or an impermissible "rewriting" of the bargain
Source reference: p.22-28Law Applied
The Court applied Section 34 of the Arbitration and Conciliation Act, 1996, specifically the restricted grounds for challenging an International Commercial Arbitration award
Source reference: p.12It relied on Ssangyong Engineering & Construction Co. Ltd. v. NHAI, which established that "patent illegality" is not a ground for setting aside an ICA award
Source reference: p.13-14The court further cited OPG Power Generation (P) Ltd. v. Enexio Power Cooling Solutions, clarifying that "public policy of India" is narrowly construed post-2015 to include only fundamental policy of Indian law, justice, or morality, and strictly prohibits a review on the merits of the dispute
Source reference: p.15-21Reasoning
The Court observed that since the seat was in India and the arbitration involved a foreign entity (making it an ICA), Section 34(2A) expressly excluded "patent illegality" as a ground for challenge
Source reference: p.22The Tribunal had conducted a detailed factual and linguistic analysis of Article 2.1 of the Contract and Clause 14.5.6 of the GCC, concluding that NCC's obligation to provide documentation was predicated on SAIL's primary obligation to pay the full Contract Price, which included the tax components
Source reference: para. 274, p.22-23The Tribunal found that because tax rates reduced, the total tax actually paid by SAIL decreased; thus, the "minimum guaranteed" figure had to be adjusted proportionately under Clause 14.6.2 of the GCC
Source reference: para. 287-288, p.24-25The High Court reasoned that it cannot substitute the Tribunal’s interpretation with its own so long as the Tribunal’s view is "plausible" and "commercially reasonable"
Source reference: p.27The Court held that SAIL’s petition was essentially an attempt to seek an appellate review on merits, which is forbidden under the Ssangyong and Associate Builders standards
Source reference: p.28Holding
The Court dismissed the petition, answering that the Tribunal’s interpretation was a plausible construction of the contract and did not violate the public policy of India
The Court held that no grounds under Section 34(2)(b)(ii) were made out as there was no breach of natural justice or fundamental policy. Consequently, the challenge to Claim No. 1 failed, and the Arbitral Award dated 08.01.2024 was upheld
Source reference: p.28-29Original Court PDF
Steel Authority Of India LtdvsNcc Ltd
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in