Madhya Pradesh High CourtArbitration and MediationCivil Procedure and Evidence

Issue of Limitation in Appointment of Arbitrator Must Be Determined by Arbitral Tribunal, Not Referral Court

M/S Haridad Railway Contractorv.Union Of India

Issue of Limitation in Appointment of Arbitrator Must Be Determined by Arbitral Tribunal, Not Referral Court. M/S Haridad Railway Contractor vs Union Of India. Madhya Pradesh High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the present application for the appointment of an arbitrator is barred by the period of limitation.

The court held

The court allowed the application, holding that all questions regarding limitation and jurisdiction are to be decided by the Arbitrator.

It also directed

The court appointed Justice Shri Ajit Singh (Former Judge, High Court of M.P.) as the sole Arbitrator to resolve the dispute.

The parties were directed to deposit necessary charges as per the M.P. Arbitration Centre Rules, 2019, and the arbitration is to be conducted at Jabalpur.

01Facts

The applicant was awarded a contract for construction work by the respondents via an agreement dated May 23, 2016.

¶ 2

The work was completed on September 20, 2019, and the final bill was paid on September 7, 2020.

¶ 2

However, a dispute arose regarding the non-payment of the second and final escalation bill amounting to ₹27,28,030/-.

¶ 2

The applicant requested the appointment of an Arbitrator via a notice dated March 22, 2023, but the respondents failed to take action under Clause 64 of the agreement.

¶ 2

Consequently, the applicant filed the present application under Section 11(6) and 11(8) of the Arbitration and Conciliation Act, 1996.

¶ 1

The respondents opposed the application, contending it was barred by limitation as it was filed more than three years after the initial cause of action arose on September 7, 2020.

¶ 3

02Issues

i.1. Whether the present application for the appointment of an arbitrator is barred by the period of limitation.

¶ 5

03Law Applied

Section 11(6-A) of the Arbitration and Conciliation Act, 1996, which confines judicial examination to the existence of an arbitration agreement.

¶ 7.3

The kompetenz-kompetenz principle enshrined in Section 16, affirming that the Arbitral Tribunal is empowered to rule on its own jurisdiction, including issues of limitation.

¶ 7.11

Uttarakhand Purv Sainik Kalyan Nigam Ltd. v. Northern Coal Field Ltd. (2020), which established that limitation is a jurisdictional issue to be decided by the arbitrator.

¶ 7

SBI General Insurance Co. Ltd. v. Krish Spinning (2024), which clarified that the referral court should only perform a prima facie scrutiny of the agreement's existence.

¶ 11

Provisions in the judgment · 8 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 6Section 8Section 11Section 15Section 16Section 21Section 34

Indian Contract Act, 1872 Section 7

04Reasoning

The court observed that the existence of the arbitration agreement and the arbitrability of the dispute were not denied by the respondents.

¶ 5

Regarding the objection of limitation, the court noted that the legislative intent of the 2015 Amendment (Section 11(6-A)) was to minimize judicial intervention at the pre-reference stage.

¶ 7.7-7.8

The court reasoned that limitation is a mixed question of fact and law and falls under the "kompetenz-kompetenz" doctrine, meaning it must be determined by the Arbitrator under Section 16 rather than the High Court under Section 11.

¶ 7.13

The court further found that since the notice invoking arbitration was sent on March 22, 2023, the application was prima facie within time from that date for the purpose of referral, and any intricate inquiry into whether the claim was "stale" should be left to the tribunal.

¶ 8, 12

05Holding

The court allowed the application, holding that all questions regarding limitation and jurisdiction are to be decided by the Arbitrator.

¶ 9, 13

The court appointed Justice Shri Ajit Singh (Former Judge, High Court of M.P.) as the sole Arbitrator to resolve the dispute.

¶ 14

The parties were directed to deposit necessary charges as per the M.P. Arbitration Centre Rules, 2019, and the arbitration is to be conducted at Jabalpur.

¶ 14
Madhya Pradesh High Court

Original Court PDF

M/S Haridad Railway ContractorvsUnion Of India

Madhya Pradesh High Court · July 01, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment