Madhya Pradesh High Court

Issue of Limitation in Appointment of Arbitrator Must Be Determined by Arbitral Tribunal, Not Referral Court

M/S Haridad Railway Contractor vs Union Of India

Madhya Pradesh High CourtJUDGMENT: July 01, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The applicant was awarded a contract for construction work by the respondents via an agreement dated May 23, 2016.

Source reference: para. 2

The work was completed on September 20, 2019, and the final bill was paid on September 7, 2020.

Source reference: para. 2

However, a dispute arose regarding the non-payment of the second and final escalation bill amounting to ₹27,28,030/-.

Source reference: para. 2

The applicant requested the appointment of an Arbitrator via a notice dated March 22, 2023, but the respondents failed to take action under Clause 64 of the agreement.

Source reference: para. 2

Consequently, the applicant filed the present application under Section 11(6) and 11(8) of the Arbitration and Conciliation Act, 1996.

Source reference: para. 1

The respondents opposed the application, contending it was barred by limitation as it was filed more than three years after the initial cause of action arose on September 7, 2020.

Source reference: para. 3
02

Issues

1. Whether the present application for the appointment of an arbitrator is barred by the period of limitation.

Source reference: para. 5
03

Law Applied

Section 11(6-A) of the Arbitration and Conciliation Act, 1996, which confines judicial examination to the existence of an arbitration agreement.

Source reference: para. 7.3

The kompetenz-kompetenz principle enshrined in Section 16, affirming that the Arbitral Tribunal is empowered to rule on its own jurisdiction, including issues of limitation.

Source reference: para. 7.11

Uttarakhand Purv Sainik Kalyan Nigam Ltd. v. Northern Coal Field Ltd. (2020), which established that limitation is a jurisdictional issue to be decided by the arbitrator.

Source reference: para. 7

SBI General Insurance Co. Ltd. v. Krish Spinning (2024), which clarified that the referral court should only perform a prima facie scrutiny of the agreement's existence.

Source reference: para. 11
04

Reasoning

The court observed that the existence of the arbitration agreement and the arbitrability of the dispute were not denied by the respondents.

Source reference: para. 5

Regarding the objection of limitation, the court noted that the legislative intent of the 2015 Amendment (Section 11(6-A)) was to minimize judicial intervention at the pre-reference stage.

Source reference: para. 7.7-7.8

The court reasoned that limitation is a mixed question of fact and law and falls under the "kompetenz-kompetenz" doctrine, meaning it must be determined by the Arbitrator under Section 16 rather than the High Court under Section 11.

Source reference: para. 7.13

The court further found that since the notice invoking arbitration was sent on March 22, 2023, the application was prima facie within time from that date for the purpose of referral, and any intricate inquiry into whether the claim was "stale" should be left to the tribunal.

Source reference: para. 8, 12
05

Holding

The court allowed the application, holding that all questions regarding limitation and jurisdiction are to be decided by the Arbitrator.

The court appointed Justice Shri Ajit Singh (Former Judge, High Court of M.P.) as the sole Arbitrator to resolve the dispute.

Source reference: para. 14

The parties were directed to deposit necessary charges as per the M.P. Arbitration Centre Rules, 2019, and the arbitration is to be conducted at Jabalpur.

Source reference: para. 14
Madhya Pradesh High Court

Original Court PDF

M/S Haridad Railway ContractorvsUnion Of India

Madhya Pradesh High Court · July 01, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment