Jammu and Kashmir High Court

J&K HC Won’t Bar Completed Sher-e-Kashmir Bridge Extension, Gives Poonch Petitioners 8 Weeks To Seek Property-Damage Compensation

BHAGAT RAJ AND ORS. vs STATE TH.P.W.D.AND ORS.

Jammu and Kashmir High CourtJUDGMENT: October 22, 20263 MIN READSOURCE JUDGMENT
J&K HC Won’t Bar Completed Sher-e-Kashmir Bridge Extension, Gives Poonch Petitioners 8 Weeks To Seek Property-Damage Compensation. BHAGAT RAJ AND ORS. vs STATE TH.P.W.D.AND ORS.. Jammu and Kashmir High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioners challenged a proposed extension of the Sher-e-Kashmir Bridge at Poonch, seeking to restrain the work and strengthen the adjoining protection walls, alleging that the extension could expose their properties to flooding and damage. They also sought acquisition and compensation if their properties were affected.

Source reference: p. 2–3

The respondents stated that the bridge had originally been designed for a flood discharge of about 6,000 cumecs, while subsequent assessment indicated approximately 7,450 cumecs, making an increased waterway necessary.

Source reference: p. 3

On 29 May 2015, the Court directed a government committee to examine the issue. The committee recommended extension of the flood-protection bund and consideration of compensation for affected landholders.

Source reference: p. 3–4

During the petition’s pendency, the extension work was completed following technical examination.

Source reference: p. 9

A connected contempt petition arose from the interim order of 29 May 2015.

Source reference: p. 10
02

Issues

1. Whether the Court should restrain the bridge-extension work in light of the subsequent technical assessment finding the extension necessary.

Source reference: p. 4–9

2. Whether the petitioners may claim compensation for property damage caused by the extension work.

Source reference: p. 7–10

3. Whether the connected contempt proceedings survived after the interim order merged into the final judgment.

Source reference: p. 10
03

Law Applied

Under Article 226 of the Constitution, judicial review ordinarily examines the decision-making process, rather than substituting the Court’s view on the merits of a technical decision.

Source reference: p. 5

As explained in Tata Cellular v. Union of India, (1994) 6 SCC 651, intervention is warranted where the decision-making process is unlawful, arbitrary, irrational, mala fide, or otherwise legally flawed.

Source reference: p. 5

Courts should give due weight to expert technical assessments and exercise restraint unless grounds such as arbitrariness, perversity, or lack of relevant material are demonstrated.

Source reference: p. 6–7

A court may also consider subsequent events where they materially affect the relief sought and are relevant to doing complete justice.

Source reference: p. 4–5

The State may pursue a technically necessary public project, but must act in accordance with law and cannot enter upon, acquire, or demolish private property without lawful authority.

Source reference: p. 7–8
04

Reasoning

The petitioners’ challenge rested substantially on the premise that the extension was unnecessary and would endanger their properties. The later hydraulic assessment and the committee constituted on the Court’s direction indicated increased flood discharge and supported the need for extension; the petitioners produced no material establishing that the committee’s conclusion was arbitrary, perverse, or otherwise legally defective.

Source reference: p. 4–7

Because the matter involved technical questions and the work had been completed, the Court declined to prohibit the extension, while emphasizing that project execution remained subject to applicable legal, technical, environmental, and safety requirements.

Source reference: p. 8–9

The possibility of property damage did not justify a blanket prohibition, but warranted consideration of compensation for any loss established in accordance with law.

Source reference: p. 7–10

In the contempt matter, the interim order had merged into the final judgment, leaving no further issue for consideration.

Source reference: p. 10
05

Holding

The Court partly rejected and partly allowed the writ petition. It declined to restrain the bridge extension, but directed the petitioners to submit claims for property loss to the Deputy Commissioner, Poonch, within eight weeks.

The Deputy Commissioner was directed to verify any damage caused by the extension or construction and, where the petitioners were entitled, take steps to pay compensation expeditiously.

Source reference: p. 9–10

The contempt proceedings were closed because the interim order had merged into the final judgment.

Source reference: p. 10
Jammu and Kashmir High Court

Original Court PDF

BHAGAT RAJ AND ORS.vsSTATE TH.P.W.D.AND ORS.

Jammu and Kashmir High Court · October 22, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment