Facts
The Petitioner, a civil engineering firm, participated in a tender (NIT No. 08/SAC/25-26) issued by the Water Resources Department for canal lining and remodeling works valued at ₹28.81 crores
Source reference: para. 3, 12Despite submitting a bid significantly lower than Respondent No. 6, the Petitioner was disqualified by the Pre-Qualification Committee
Source reference: para. 4, 12The disqualification was based on the Petitioner’s failure to satisfy eligibility criteria regarding "bid capacity" and "proof of execution of works," specifically that certain documents were submitted after the bid deadline and others lacked verifiable payment details
Source reference: para. 8, 12The Petitioner challenged the disqualification via writ petition, alleging it was arbitrary, non-transparent, and violative of the "level playing field" doctrine
Source reference: para. 5, 6Issues
1. Whether the disqualification of the Petitioner’s technical bid by the respondent authorities was arbitrary, discriminatory, or in violation of the principles of natural justice
Source reference: para. 6, 122. Whether the Court can interfere in the technical evaluation of a tender process involving expert committees under Article 226 of the Constitution
Source reference: para. 9, 21Law Applied
The Court relied on the Wednesbury principle of reasonableness and the doctrine of judicial restraint in administrative actions
Source reference: para. 24It cited Jagdish Mandal v. State of Orissa, which established that interference is only warranted if the process is mala fide, intended to favor a party, or so irrational that no responsible authority could reach such a decision
Source reference: para. 22The Court also applied Tata Cellular v. Union of India, emphasizing that courts do not sit as an appellate authority over technical experts and must allow "fair play in the joints" for the executive
Source reference: para. 22It further referenced M/S. Steag Energy Services (India) Pvt. Ltd. v. GSPC Pipavav Power Company Ltd. regarding the owner’s final right to choose and the need for flexibility in contractual matters
Source reference: para. 23Reasoning
The Court found that the tender process was conducted strictly in accordance with NIT terms
Source reference: para. 13It observed that the Petitioner was provided adequate opportunity to rectify document deficiencies, and the Pre-Qualification Committee reconvened twice (01.04.2026 and 08.04.2026) to consider the Petitioner’s representations and additional documents
Source reference: para. 12, 14However, because the submitted documents were "post-bid date" or lacked necessary verification details, the Committee’s decision to maintain disqualification was deemed a reasoned exercise of power
Source reference: para. 12, 14The Court rejected the Petitioner’s argument regarding the lower financial bid, noting that price comparison arises only among technically qualified bidders; a disqualified bidder has no right to have their financial bid considered
Source reference: para. 16The Court concluded that the evaluation was a technical matter within the expertise of the Department, and no evidence of mala fides or procedural irregularity was presented to justify judicial intervention
Source reference: para. 15, 19Holding
The Court answered the issues in the negative, holding that the disqualification was neither arbitrary nor irrational
The Writ Petition was dismissed, and previous interim directions keeping the tender in abeyance were effectively vacated. No order as to costs was made
Source reference: para. 24, 25Original Court PDF
M/S SUNIL KUMAR AGRAWALvsSTATE OF CHHATTISGARH
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in